GLAST Proposal Review - PowerPoint PPT Presentation

About This Presentation
Title:

GLAST Proposal Review

Description:

Title: GLAST Proposal Review Author: Peter F. Michelson Last modified by: Bill Althouse Created Date: 11/21/1999 11:20:13 PM Document presentation format – PowerPoint PPT presentation

Number of Views:86
Avg rating:3.0/5.0
Slides: 19
Provided by: Pet1164
Category:

less

Transcript and Presenter's Notes

Title: GLAST Proposal Review


1
GLAST Large Area Telescope Silicon-Strip
Tracker/Converter Robert P. Johnson U.C. Santa
Cruz Tracker Subsystem Manager johnson_at_scipp.ucsc
.edu
2
Silicon-Strip Tracker/Converter
  • Outline
  • Recommendations from the February review
  • Tracker Peer Design Review
  • Tracker Technical Progress
  • Silicon-Strip Detectors
  • Mechanical Design
  • Tray Assembly
  • Electronics Design
  • Electronics Assembly
  • Tracker Test Plans
  • Tracker LAT PDR Preparations

3
Recommendations from February
  • Build an explicit Tracker reserve of at least 4
    months into the fabrication schedule.
  • This has been done.
  • Produce detailed test plans, including testing of
    the electronics beyond the expected operational
    conditions.
  • Mechanical and electrical test plans have been
    drafted.
  • Detailed procedures for prototype ASIC testing
    have been drafted, and those tests are just
    beginning.
  • Work is in progress on building the electronics
    test systems.
  • Detailed test procedures and verification matrix
    for testing during production remain to be
    written.
  • Add milestones to the Tracker development
    schedule
  • Detailed schedules have been put together (in MS
    Project) for completion of the prototype trays
    and the Tracker engineering model during the
    coming year.

4
LAT Tracker Peer Design Review
  • Draft Preliminary Design Report LAT-TD-00156.
  • 21 additional Tracker documents prepared for the
    PDR
  • Requirements
  • Mechanical/thermal design report
  • Electronics conceptual design and specifications
  • Mechanical and electrical interface
    specifications
  • Grounding and shielding plan
  • Reliability analysis
  • Parts lists
  • Mechanical and electrical test plans
  • The review was held June 19, 2001, with a panel
    that included 2 outside experts one with SSD
    experience in HEP one aerospace expert.
  • The outcome of the review was generally positive.
    All questions were answered. Work is in
    progress on complying with the detailed
    recommendations, in preparation for the PDR.

5
Silicon-Strip Detectors
  • Hamamatsu Photonics (HPK) detector prototypes
    satisfied all of our requirements.
  • A preproduction run is in progress at HPK, with
    gt300 SSDs manufactured and tested.
  • The preproduction SSDs are of excellent quality.
  • SLAC has tendered a contract for the first
    production run at HPK.
  • 2 European firms are still working on prototype
    runs, but HPK production can meet our full
    demand.

Current (nA)
Average leakage current per run for 10
preproduction HPK SSD runs.
6
Mechanical Design
  • Detailed design of the tray panels (thin
    converter, thick converter, top bottom) is
    complete.
  • Prototype tray panels are being fabricated both
    in Italy and the U.S.
  • Two tower-module assembly methods have been
    devised and will be tested in September
  • Stacked trays.
  • External fixture.
  • A full prototype tower will be constructed from
    prototype trays and mass-model trays for
    vibration testing before construction of the
    Tracker engineering model.

7
Tray Panel Construction
Tray panel 4 C-C closeout sides, Al core,
C-fiber face sheets.
Graphite fixture for closeout and tray panel
assembly.
Structural Closeout Wall
MCM Closeout Wall
8
Tracker Mechanical/Thermal Interface
  • A conceptual design was completed for attachment
    of the Tracker to the Grid
  • Blade flexures to avoid stress from CTE
    differences.
  • Thermal gasket to aid the transfer of heat into
    the Grid.
  • Some modeling has been completed (next slide).
  • Some details need more work (such as how to
    ensure adequate compression of the gasket).

9
Tower-Level Mechanical Model
Typical 1st Mode Shape of the Flexure Mounted
Tower Support
1st Mode Flexure Deformation
10
Tray Assembly Ladders
  • Assembly of prototype ladders, including
    encapsulation, has been completed at two Italian
    vendors (MIPOT and GA)
  • Measured alignment of completed ladders meets our
    specifications.

Ladder edge-bonding fixture
Encapsulated Wire Bonds
11
Tray Assembly Ladder Mounting
  • Fixtures for precision mounting of ladders onto
    tray panels have been designed and tested in
    Italy.
  • The same vendors as for ladder assembly will do
    this work during production.

Bias Circuits
SSDs
Panel
Tungsten
MCM
Mounting the first ladder onto a tray panel.
4 ladders mounted
12
Electronics Design Readout ASIC
  • Migrate design from HP 0.8 ?m to HP 0.5 ?m CMOS
    process.
  • Substantial redesign of analog front end (now 2.5
    V).
  • LVDS on all I/O (except hard reset and config.
    reg. output).
  • Configuration register now is SEU hardened
    (tested with heavy ions).
  • Config. reg. divided into 5 pieces now
    nondestructive read.
  • System clock and output-register clock are on
    continuously.
  • Old FIFO for event buffering is now RAM.
  • Full prototype is under test?all features are
    functional.

Control logic, command decoders Standard-cell
auto route
4-deep event memory (addressed by TEM) Custom
layout
Trigger and Data mask registers Standard-cell
auto route
2 custom DACs
I/O Cells
Cap
64 amplifier-discriminator channels. Redesigned
w.r.t. BTEM version. AC coupled to discriminator.
Calibration mask and capacitors
I/O pads and protection structures
13
Electronics Design Controller ASIC
  • All digital, standard cell design, except for
    LVDS I/O cells.
  • SEU hardened configuration register.
  • Ground-up new design in VHDL synthesis, auto
    place and route.
  • Functionality is similar to the BTEM chip, but
    many interface and data format details are
    changed.
  • 25 ?s (TBR) limit on the TOT.

Full prototypes are under test for both the TSMC
(0.25 ?m) and HP (0.5 ?m) CMOS processes.
Layout of the GTRC chip in the TSMC process.
14
Electronics Design PWBs
  • Tracker MCM (readout module)
  • PWB layout is complete.
  • 7-chip mini version for initial system tests is
    in fabrication.
  • Face-to-face meetings were held in L.A. last week
    with the vendor for the full-scale aramid-fiber
    version.
  • Pitch adapter flex circuit. Prototypes are in
    hand from 2 vendors and are being used to study
    MCM assembly.
  • Bias flex circuit prototypes are in fabrication.
  • Flex readout cables
  • Layout was completed on the first of eight.
  • Quotations are in progress at 2 vendors.
  • The final length still is undetermined.

15
Tracker MCM Assembly
  • Teledyne, in L.A., will solder SMT parts, bond
    the pitch adapter, mount ASICs, wire bond, test,
    and encapsulate.
  • Face-to-face meetings were held with Teledyne
    last week in L.A.
  • Work will begin immediately on tooling and on
    assembly of initial (non-functional) prototypes.

Bonding a pitch adapter to an MCM PWB.
Wire bonds from a readout ASIC to flex
16
Tracker Electronics Test Systems
Test system for ASIC wafer probing.
  • Systems for complete testing of the prototype
    ASICs are in progress.
  • Conceptual designs are complete for
  • ASIC wafer probing?probe cards and PWBs are being
    designed.
  • MCM production testing?custom VME module is in
    hand.
  • MCM burn-in?PWB design is in progress.
  • Work is in progress to define the detailed test
    vectors and procedures for tray and tower
    electronics testing.

17
Tracker Test Plans
  • Environmental Testing
  • LAT-TD-00154 Tracker Tray Test Plan
  • LAT-TD-00155 Tracker Tower Test Plan
  • Electronics Testing
  • LAT-TD-00153 Test Systems for the Tracker
    Front-End Electronics
  • LAT-TD-00191 Tracker Tower Electrical Test Plan
  • LAT-TD-00246 Tracker Front-End Chip Test Plan
  • LAT-TD-00247 Tracker Front-End Readout Chip Wafer
    Test Procedure
  • LAT-TD-00248 Tracker Readout-Controller Chip
    Wafer Test Procedure
  • LAT-TD-00249 Tracker TMCM Electrical Test
    Procedure

18
Tracker PDR Preparations
  • Update of the PDR documentation
  • Improvement of the reliability analysis.
  • Improved requirements documents.
  • More complete electronics test plans, test
    procedures, and verification matrix.
  • Completion of the prototype mechanical structure,
    including assembly tests.
  • Vibration tests on trays. Possibly tower
    vibration, as well.
  • Ion-beam SEL and SEU tests on Tracker ASICs.
  • Test results on the Tracker ASICs in the full
    flight design, including an integrated test with
    both ASICs, a mini-MCM, and a full-length SSD
    ladder.
  • Finalized baseline budget and schedule.
Write a Comment
User Comments (0)
About PowerShow.com