Title: GLAST Proposal Review
1GLAST Large Area Telescope Mechanical Systems
Peer Review 27 March 2003 Section 4.7
Fabrication Verification Radiator, XLAT,
Heatpipes Brenda Costanzo Lockheed Martin System
Engineer brenda.costanzo_at_lmco.com
2Radiator Fabrication (1 of 2)
Bond Pipes To OB Facesheet
Inspect Thermal Bond Visual
Machine Transfer Datums
Assemble Panel and Bond
Fit Check Core
Verify Cure Profile
Process Samples To Lab
Inspect Holes w/ Pins
Prep and Install Inserts Spools
Inspect Inserts Spools
Bond IB Doublers RT Cure
CMM Inspect Geometry
Bond OB Doublers AC Cure
Verify Cure Profile
Inspect Doublers
Bond Top Edge Closure
A
3Radiator Fabrication (2 of 2)
- Notes
- All panel moves require inspection
documentation of panel for damage packaging for
- transport and flight approved move procedures.
- No outside storage.
- Qualified flight transportation personnel and
equipment.
4M P Plan, EEE Parts
- M P Plan submitted to SLAC (GLS00018-2, dated 1
Feb 2003) - EEE Parts
- Heaters Minco Kapton Foil Heaters per GSFC
S-311-P-079 - Thermistors YSI Thermistors per GSFC S-311-P-18
- RTDs Rosemount PRT per GSFC S-311
- Solid State Thermostats Micropac 52372O
- Submitted to SLAC for approval Nov 2002
5Overall Test Philosophy
- Tests are broken into three categories
- In process
- Assembly
- Joint assembly
- Benchmark tests will be performed to assess any
changes due to environmental testing - IR Heat pipe signature
- Low level sine vibration
- Test plan is document GLS0002-03
- All testing will have procedures written prior to
commencement - Inspection occurs throughout the testing at
points specified in the procedure - Flash reports will be written within 3 working
days of test completion - Full reports will be written within 30 days of
test completion or by pre-ship review, whichever
is earlier
6Overall Test Flow
7Heat Pipe In-Process and Acceptance Testing
- In process testing
- Verification of material certifications
- Inspection of physical dimensions
- Verification that LM procedures are followed
- Acceptance testing
8Radiator and X-LAT Panel In-Process Testing
- Radiator and X-LAT Panels
- Verification of material certifications
- Inspection of physical dimensions
- Verification the LM procedures are followed
- Radiator Panels
- X-LAT Panels
- Visual inspection of pipe/panel bonds
9Radiator Mechanical Acceptance Tests
- Test configuration
- Each radiator panel assembly tested separately
- Test flow
Vibration Testing
Low Level Sine Survey
Pre-Vibration IR Signature
Low Level Sine Survey
Post-Vibration IR Signature
Acoustic Vibration
Sine Vibration
Limit Load Test
10X-LAT Plate Qualification Testing
- Test configuration
- One protoqual X-LAT plate assembly
- Test flow
11X-LAT Assy Mechanical Acceptance Tests
- Test configuration
- X-LAT Assy (two X-LAT panels and one mid-plate)
- Test flow
12X-LAT/Radiator Assy Thermal Testing
- Combining the X-LAT and Radiator Assy thermal
testing - Cost savings (1 test versus 2 tests)
- Minimizes STE
- Tests X-LAT pipe to Radiator pipe thermal joint
- Hardware configuration
- X-LAT Assy
- Radiator Assy
- Heater plate to introduce heat into the system
- Lab electronics to control VCHPs
- Hardware orientation
- X side up
- Level within 0.10
13Test Orientation
NO SCALE
Flight Radiators (2)
Flight X-LAT Assy
MLI Blanket
Gravity is Down
Cold Wall
14X-LAT/Radiator Assy Thermal Test Flow
Thermal Cycle 4
IR Signature
Cold Portion of Thermal Cycle
Post-Cycling Functional Test
Hot Balance Point
Delivery In-Place to SLAC
TCS Thermal Testing
15TCS Thermal Testing
- Hardware Configuration
- Radiator Assy
- X-LAT Assy
- Downspout heat pipes (TBR)
- LAT mass simulator
- Test Objective
- Verify VCHP reservoir heater operational
algorithm - Test Flow
16Further Work
- Determine appropriate structural testing for
Radiator and X-LAT Assemblies - Determine X-LAT Assy and Radiator Assy
configuration for thermal testing (together or
separate) - Design STE (Special Test Equipment) and GSE
(Ground Support Equipment) - Determine if TCS thermal test objective can be
achieved during XLAT / Radiator Assy thermal test - Determine what additional hardware will be
available - If performing separate TCS test, design LAT mass
simulator - Write test procedures