Overview of GAOs Implementation of Earned Value Management - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Overview of GAOs Implementation of Earned Value Management

Description:

... Aegis system reflected only the interceptor portion and not the entire Aegis element ... had no insight regarding the Aegis interceptor divert system which was ... – PowerPoint PPT presentation

Number of Views:45
Avg rating:3.0/5.0
Slides: 27
Provided by: GAO162
Category:

less

Transcript and Presenter's Notes

Title: Overview of GAOs Implementation of Earned Value Management


1
Overview of GAOs Implementation of Earned Value
Management
  • Karen Richey
  • Jennifer Echard
  • GAO Cost Analysts
  • Applied Research Methods Team
  • April 28, 2005

2
Table of Contents
  • Using EVM as an Audit Tool at GAO
  • Summary of GAO Report Findings using EVM analysis
  • FAA STARS (GAO-03-343)
  • Missile Defense (GAO-04-409)
  • Airborne Laser (GAO-04-643R)
  • NASA Cost Estimating Process (GAO-04-642)
  • Polar-Orbiting Environment Satellite
    (GAO-04-1054)
  • Navy Shipbuilding (GAO-05-183)
  • Next steps for GAO and EVM

3
Using EVM as an Audit Tool
  • GAO began using EVM analysis in 2002 for selected
    audits
  • Since that time GAO has issued 6 reports using
    EVM analysis as a basis for findings
  • Programs are far ranging covering major Automated
    Information Systems, Shipbuilding, Missile
    Defense and NASA
  • Results vary among programs--Examples include
  • Realism of the Performance Measurement Baseline
    (PMB)
  • Integrated Baseline Reviews (IBRs) data
    validation
  • Number of rebaselines
  • Optimistic Estimates at Completion (EACs)
  • Frequency of reporting

4
Summary of GAO Report Findings using EVM
analysis FAA STARS (GAO-03-343)
  • Background On November 17, 2002, FAA began using
    the Standard Terminal Automation Replacement
    System (STARS) to control air traffic at the
    Philadelphia air route traffic control center.
  • STARS is a joint procurement with DOD, which is
    purchasing up to 199 units for its facilities.
  • STARS will replace controller workstations with
    new color displays, processors, and computer
    software at FAA and DOD terminal air traffic
    control facilities.
  • STARS provides an automation platform that will
    enable efforts to optimally configure the
    terminal airspace around the country, exchange
    digital information between pilots and
    controllers, as well as introduce new position
    and surveillance capabilities for pilots.

5
FAA STARS (GAO-03-343) Website
www.gao.gov/new.items/d03343.pdf
  • FAA was not using CPR data to manage its contract
    because the data did not reflect current effort
    and had not been validated by an IBR after
    changes
  • Major modifications changed the Performance
    Measurement Baseline (PMB) curve
  • PMB never updated when STARS implementations fell
    from 188 to only 74 systems
  • PMB did not reflect 179M of new work authorized
    since contract award

6
FAA STARS (GAO-03-343)
  • Conclusions FAA was unable to effectively
    manage the contract
  • CPR showed program to be on schedule and within 1
    percent of budgeted costs
  • In reality, FAA was contracting to modernize
    fewer than half the systems at more than twice
    the original cost
  • Recommendations GAO recommended that FAA
  • Maintain current baselines,
  • Negotiate all authorized work within 3 months,
    and
  • Conduct IBRs after any major contract
    modifications within 6 months
  • Result FAA concurred with recommendations.

7
Summary of GAO Report Findings using EVM
analysis Missile Defense (GAO-04-409)
  • Background GAO has an annual congressional
    mandate to assess the extent to which MDA
    achieves program goals.
  • In 2002 two key events transformed DODs approach
    to missile defense
  • The Secretary of Defense consolidated existing
    missile defense elements into a single
    acquisition program and placed them under the
    management of the Missile Defense Agency (MDA)
  • The President directed MDA to begin fielding an
    initial configuration, or block, of missile
    defense capabilities in 2004.

1 Airborne Laser 2 Ground Based
Midcourse Defense
8
Missile Defense (GAO-04-409) (cont) Website
www.gao.gov/new.items/d04409.pdf
  • Prime contractors for 4 system elements completed
    work at or near budgeted costs, but contractors
    for two system elements overran budgeted costs by
    a total of 380 million during fiscal year 2003
  • ABL1 underestimated the complexity of integrating
    subcomponents into a flight-worthy
    configuration causing major cost overruns
  • Initial PMB was highly optimistic given the
    cutting edge technology
  • Unrealistic schedule contributed to both cost and
    schedule problems
  • Developmental and delivery problems with the GMD2
    interceptor were the leading contributors to cost
    overruns and schedule slips
  • CPRs for Aegis system reflected only the
    interceptor portion and not the entire Aegis
    element
  • MDA had no insight regarding the Aegis
    interceptor divert system which was experiencing
    development problems at the time

1 Airborne Laser 2 Ground Based
Midcourse Defense
9
Missile Defense (GAO-04-409) (cont)
  • Conclusions GAO found that MDAs program goals
    do not serve as a reliable and complete baseline
    for accountability purposes and investment
    decision making because
  • they can vary year to year,
  • do not include life cycle costs,
  • are based on assumptions about performance not
    explicitly stated,
  • does not explain some critical assumptions such
    as an enemys type and number of
    decoysunderlying its performance goals
  • As a result, decision makers in DOD and Congress
    do not have a full understanding of the overall
    cost of developing and fielding the Ballistic
    Missile Defense System and what the systems true
    capabilities will be.

1 Airborne Laser 2 Ground Based
Midcourse Defense
10
Missile Defense (GAO-04-409) (cont)
  • Recommendations GAO recommended that MDA
  • Establish cost, schedule, and performance
    measurement baselines (including full life cycle
    costs) for each system being fielded
  • Result DoD concurred with baseline
    recommendations.

1 Airborne Laser 2 Ground Based
Midcourse Defense
11
Summary of GAO Report Findings using EVM
analysis Airborne Laser (GAO-04-643R)
  • Background From 1996 to 2001, the ABL program
    was an Air Force major defense acquisition
    program.
  • In October 2001, the DOD transferred
    responsibility for the program to the Ballistic
    Missile Defense Organization (now MDA) where ABL
    became one element of the Ballistic Missile
    Defense System (BMDS).
  • ABL's mission is to destroy enemy ballistic
    missiles in the boost phase as part of the
    layered defense strategy.
  • ABL is being developed incrementally in a series
    of 2-year blocks.

1 Airborne Laser
12
Airborne Laser (GAO-04-643R) (cont) Website
www.gao.gov/new.items/d04643.pdf
  • Prime contractors cost for developing ABL1 had
    nearly doubled from Air Force original estimate
    and additional cost growth expected
  • Costs increased from 1B in 1996 to 2B in 2003
  • Unrealistic PMB at contract award prompted
    numerous rebaselines
  • GAO forecasted an overrun between 431M - 943M
    for first ABL demo
  • Cumulative Cost Variance at that time was -242M
    with a schedule variance of -28M
  • Contractor reported no variance at completion
  • The cost growth occurred because the program did
    not adequately anticipate the complexities
    involved in developing the system.
  • MDA continues to face significant challenges in
    developing the ABL's revolutionary technologies
    and in achieving cost and schedule stability.

1 Airborne Laser
13
ABL Cost and Schedule Variance in FY 2003 ( in
Millions)
14
ABL Actual Performance Vs. Projected Performance
15
Airborne Laser (GAO-04-643R) (cont)
  • Conclusions Program did not adequately plan for
    or anticipate complexities involved in developing
    ABLs revolutionary technologies
  • Rapid prototyping forced program to integrate
    components before they were fully tested causing
    unexpected rework
  • Fabrication of ABLs unique components and
    developing its complex software proved more
    costly and time consuming than anticipated
  • Bow wave of uncompleted work from prior years
    competed for current resources despite an
    increase in staff and additional work shifts
  • Recommendations GAO recommended that MDA
  • complete an uncertainty analysis on the
    contractors new cost estimate to quantify level
    of confidence
  • Result DOD concurred.

1 Airborne Laser
16
Summary of GAO Report Findings using EVM
analysis NASA Cost Estimating Process
(GAO-04-642)
  • Background NASA's programs encompass a broad
    range of complex and technical activities--from
    investigating the composition and resources of
    Mars to providing satellite and aircraft
    observations of Earth for scientific and weather
    forecasting.
  • Our review focused on 27 of 68 NASA programs in
    the development phase as of April 2003 or that
    completed development in fiscal year 2001 or
    2002.
  • To assess NASA's cost-estimating processes and
    methodologies, we conducted a more in-depth
    review of 10 of the 27 programs
  • We chose programs using the following critieria
  • The highest development cost estimate within five
    of NASA's seven Enterprises.

17
NASA Cost Estimating Process (GAO-04-642) (cont)
Website www.gao.gov/new.items/d04642.pdf
  • We compared cost estimating documentation from 10
    programs against SEI cost estimate criteria to
    determine whether NASA followed good cost
    estimating practices.
  • We found that NASA cost estimates for 8 out of
    the 10 programs we reviewed in detail increased
    over time
  • NASA attributed cost growth to technical problems
    and funding shortages
  • Variability in cost estimates indicated that
    programs lacked sufficient knowledge needed to
  • Establish priorities,
  • Quantify risks,
  • Make informed decisions, and
  • Thus predict costs

18
NASA Cost Estimating Process (GAO-04-642)
(cont)Overview of 10 Selected Programs
19
NASA Cost Estimating Process (GAO-04-642) (cont)
  • Conclusion NASAs basic cost estimating
    processes lacked discipline needed to ensure that
    program estimates are reasonable
  • None of the 10 programs GAO reviewed met all of
    GAOs cost estimating criteria
  • Only 3 of the 10 programs provided a breakdown of
    the work to be performed
  • Only 2 programs used EVM for measuring cost and
    performance to identify risks
  • The other 8 programs compared planned versus
    actual obligations and expenditures
  • NASA had no data to determine ahead of time
    whether these 8 programs were at risk of cost and
    schedule overruns
  • Recommendations GAO recommended that NASA
  • develop rebaselining guidance to ensure
    consistency among programs,
  • implement EVM as a tool for bringing cost to the
    forefront,
  • and ensure EVM policies are enforced
  • Result NASA concurred.

20
Summary of GAO Report Findings using EVM
analysis Polar-Orbiting Environment Satellite
(GAO-04-1054)
  • Background The United States operates
    polar-orbiting meteorological satellite systems
    to
  • Provide graphical weather images and specialized
    weather products that are inputs into weather
    prediction.
  • These images, products, and models are all used
    by weather forecasters, the military, and the
    public for both weather forecasting and climate
    monitoring.
  • NPOESS1 is being developed to combine two current
    satellite systems into a single state-of-the-art
    environment monitoring satellite system.
  • NPOESS is a tri-agency endeavor involving DOD,
    NASA, and the National Organic and Atmospheric
    Administration

1 National Polar-Orbiting Environmental
Satellites
21
Polar-Orbiting Environment Satellite
(GAO-04-1054) (cont) Website www.gao.gov/new.ite
ms/d041054.pdf
  • Recently the NPOESS program office developed a
    new cost and schedule baseline.
  • Congress asked us to identify any cost or
    schedule changes as a result of the revised
    baseline and determine what factors contributed
    to these changes.
  • We found that the program office increased
    NPOESS1 cost estimate by 1.2B and delayed the
    availability of the first NPOESS satellite by 20
    months.
  • Funding cuts stretched out NPOESS program causing
    an increase in cost
  • Other cost increases were due to problems with
    sensor development and additional program office
    costs to mitigate risks after program rebaseline.
  • Lack of schedule slack increased risk for
    managing development issues.

1 National Polar-Orbiting Environmental
Satellites
22
Polar-Orbiting Environment Satellite
(GAO-04-1054) (cont)
  • Conclusion NPOESS could experience further cost
    and schedule increases
  • Contractors continued schedule slippage in both
    cost and schedule targets indicated the NPOESS
    contract would likely overrun by 500M
  • Program risks with developing critical sensors
    could also add costs
  • Since contract rebaseline, cost overruns have
    more than doubled and the schedule was slipping
    again
  • We estimated an overrun between 372M and 891M
    at completion compared to the contractor which
    estimated an overrun of only 130M
  • Cumulative cost variance at that time was 55M at
    only 20 percent complete
  • Recommendations We concluded that continued
    oversight is more critical than ever.
    Accordingly, GAO plans to continue the review of
    this program.
  • Result DOD, NASA, and NOAA officials generally
    agreed with the report

1 National Polar-Orbiting Environmental
Satellites
23
Summary of GAO Report Findings using EVM
analysis Navy Shipbuilding (GAO-05-183)
  • Background The U.S. Navy invests billions of
    dollars each year to maintain technological
    superiority of its warships.
  • Our study reviewed the top four ship classes
    involved in new ship construction to determine
    the reasons behind significant cost overruns.

24
Navy Shipbuilding (GAO-05-183) (cont)website
www.gao.gov/new.items/d05183.pdf
  • For the 8 ships assessed (2 ships in 4 classes),
    we found that Congress had appropriated 2.1
    billion in additional funding to cover in cost
    increases through 2004
  • GAO EVM analysis indicated cost increases of
    3.1B or more for all 8 ships could be expected
  • Cost increases for CVN 77 and LPD 17 were the
    most pronounced
  • Virginia Class submarine was expected to also
    require additional costs
  • Increases in labor hour and material costs
    together account for 77 percent of the cost
    growth on the eight ships. Shipbuilders cited the
    following as key causes
  • Design modifications
  • Additional and more costly materials
  • Changes in employee pay and benefits

25
Navy Shipbuilding (GAO-05-183) (cont)
  • Conclusion Navy practices for estimating costs,
    contracting, and budgeting for ships resulted in
    unrealistic funding of programs
  • PMB costs for CVN, SSN, and LPD 17 were all
    unrealistic increasing the likelihood of
    increased costs
  • Navy does not account for probability of cost
    growth when estimating costs
  • No uncertainty analysis
  • No management reserve
  • 3 out of 4 ship classes received CPRs on a
    quarterly basis
  • LPD 17 switched to monthly CPRs after
    unprecedented cost growth
  • CVN 77 is switching to monthly CPRs within the
    year
  • SSN 774 class is staying with quarterly CPRs
    despite expected cost growth
  • Recommendation GAO recommended the Navy
  • perform uncertainty analysis,
  • establish realistic budgets for measuring
    performance,
  • and include more timely and complete reporting on
    program costs.
  • Results Navy partially concurred.

26
Next steps for GAO and EVM
  • Select members of GAO have been extensively
    trained to use EVM for audits
  • These members delivered in-house training to
    various GAO teams to get the word out about the
    benefits of using EVM
  • Ability to quantify historical cost and schedule
    performance
  • Provide a means for forecasting future costs and
    schedules
  • Identify areas of poor performance and technical
    concern
  • Ability to forecast potential problem areas and
    report to Congress
  • GAO has ordered Winsight software and will be
    trained in the next few months
  • Next area of focus includes scheduling techniques
    and tools, with an emphasis on the critical path
    method
Write a Comment
User Comments (0)
About PowerShow.com