WBS 2 - Hadron Calorimeter - PowerPoint PPT Presentation

1 / 29
About This Presentation
Title:

WBS 2 - Hadron Calorimeter

Description:

Complete QIE ASIC submitted March 5. Due back June 15 ... Bugs being fixed in HPDs. Front End ASICs: Complete QIE submitted to fabrication. ... – PowerPoint PPT presentation

Number of Views:22
Avg rating:3.0/5.0
Slides: 30
Provided by: dang5
Category:

less

Transcript and Presenter's Notes

Title: WBS 2 - Hadron Calorimeter


1
WBS 2 - Hadron Calorimeter
  • Jim Freeman
  • DOE/NSF Review
  • May 8, 2001

2
Outline
  • System Overview
  • Status and Technical Progress
  • Schedule and Cost Performance
  • Committee Concerns and Issues
  • Plans for the Next Six Months
  • Summary and Conclusions

3
System Overview

4
US HCAL Scope
  • HB Absorber, assembly and installation tooling
  • Scintillator production for HB
  • Scintillators and fibers acquisition for HE
  • Fraction of fibers acquisition for HF
  • Readout boxes, HPDs, and PMTs for HB, HE, HO,
    HF
  • Front end and higher level electronics for HB,
    HE, HO, HF
  • Power, calibration, controls for HB, HE, HO,HF
  • Fraction of HE brass acquisition
  • HF Mechanical Engineering

5
HCAL Status and Progress
  • Absorber and Tooling
  • Scintillator Factory
  • HPDs
  • Front End Electronics
  • Readout Electronics
  • HF

6
Absorber Factory
  • HB- Complete and delivered to CERN
  • HB- tooling completed and at CERN
  • HB
  • 12 wedges (out of 18) complete
  • Expect completion in July 01
  • HB should arrive at CERN in fall 01
  • HB tooling complete and in Spain
  • Entire absorber task 90 complete.

7
Barrel HCAL

8
HB- Absorber
HB- absorber is complete. It passed all QC tests
and has been disassembled and shipped to CERN.
9
HB- at CERN
HB- wedges and scintillator crates in Bldg 186 at
CERN. Scintillators will be installed into wedges
in June.
10
HB
12 of 18 HB Wedges are complete
Cradle and tooling ready
HB will be complete by end of July, ahead of
schedule
11
Optics Factory
  • Builds optical system for HB
  • Full staffing at 14 ftes
  • Rate 1.3 megatiles/day
  • 473 out of 612 total Megatiles complete
  • Completed HB- optics July 2000
  • Complete HB optics Sept 2001
  • Will finish ahead of schedule

12
HCAL Optics 80 complete
Completed Megatiles
13
HPD Status
  • Had large electrical cross talk at high frequency
    due to resistance between bias supply and diode.
  • Solution was to aluminize diode.
  • Unfortunately, solution revealed and worsened
    existing problem, optical cross talk.
  • Have found solution to optical cross talk,
    anti-reflective coating.
  • Expect to have preproduction HPDs in fall 01.
  • Plan to start production in December 01. Delivery
    complete by Oct 2003. Defines critical path.
  • Possible to double production rate (to gain
    schedule contingency) but at substantial cost
    (200K). Need to make this decision this fall.

14
HPD

Diode Structure
Bias Voltage
15
HPD Anti-reflective coating

Aluminum with no anti-reflective coating
Reflectivity vs wavelength for diode with
antireflective coating
16
Readout Box Progress
  • Redesign to modularize components (readout
    modules plug into crate)
  • Results in better electrical, thermal, and
    maintenance properties
  • Passed Production Readiness Review in February
    01. CMS Sign-off on integration, safety, other
    issues.
  • Starting production (optical components in
    production, contract in place for crates)

17
RBX Readout Module
  • The readout module (RM) integrates the HPD, front
    end electronics, and digital optical drivers.

18
Front End ASICs QIE and CCA
  • QIE
  • QIE is pipelined charge(Q) Integrator and
    Encoder Digitizer chip
  • Complete QIE ASIC submitted March 5. Due back
    June 15
  • Production scheduled to complete July 28, 2002
  • One fabrication cycle contingency
  • CCA
  • CCA is the Channel Control ASIC clock and
    control chip
  • Channel Control ASIC will be submitted in May
  • Production scheduled to complete August 16, 2002

19
Readout Electronics
  • Four generations of cards
  • Demonstrator 2000 (show concept)
  • Prototype 2001 (basic building blocks)
  • Preproduction 2002
  • Production 2003
  • Production scheduled for completion Spring 2003
  • Major upcoming tasks
  • Radioactive source calibration demonstration
    Summer 01, FNAL
  • Test Beam DAQ Summer 02, CERN

20
HF
  • Progress since last review
  • Mechanical Engineering about finished. EDR in
    August 01.
  • Specifications for phototubes and quartz fiber
    defined.
  • Passed PRR for phototubes and fibers in March 01
  • RFQs for phototubes and fibers ready to be sent
    out.

21
Installation Planning
HB Installation Plan. HB, HE, and HO will be
covered in detail in break-out session
22
US HCAL Schedule
HPD delivery determines schedule
V27 milestones


Installing HE readout modules critical path.
Driven by availability of HPDs.
23
HCAL Cost Performance
24
HCAL Cost Comparison
2000 Lehman 2001 Lehman
EAC 37.0M 38.3M
Complete 47 58
ETC EAC - BCWP 19.2M 16.0M
BCWS 19.7M 25.9M
BCWP 17.4M 22.3M
BCWS-BCWP -2.4M -3.6M
Contingency Use 2.3M 3.6M
Schedule variance largely due to delayed purchase
of phototubes and HPDs (2.4M) Contingency use
during the last year (1.3M) was 50 HPD-related
costs
25
US CMS HCAL L2 Milestone Performance
26
Progress Since Last Review
  • HB absorber, tooling almost complete. First HB at
    CERN, second complete July 2001.
  • Optics Production about 80 complete. Finish in
    September 2001.
  • Redesign, PRR for Readout Box. Starting
    production
  • Bugs being fixed in HPDs.
  • Front End ASICs Complete QIE submitted to
    fabrication. CCA to be submitted soon.
  • Readout Electronics Demonstrators complete,
    moving into prototype phase.
  • HF Mechanical Design close to complete. EDR in
    August.
  • HF PRR for fibers and phototubes. Ready to place
    RFQs
  • Revised installation plan at CERN

27
Concerns from last review
  • Front End Electronics ASIC QIE is on schedule,
    CCA two months behind. Not on critical path
  • Bottoms-up Rebaseline of Readout Box Done.
    Passed Production Readiness Review. Have started
    production.
  • HPDs Still a problem, critical path. Hope for
    final fix by fall 01.
  • Installation Plan Revised plan

28
What we plan for the next 6 months
  • HB completed and delivered to CERN
  • Optics complete for HB- and HB
  • Receive first complete QIEs and test
  • Place order for HPDs
  • Place order for HF phototubes and fiber

29
Summary
  • Absorber and Optics factories finishing on cost
    and schedule.
  • Front End ASICs progressing. Schedule is OK.
  • RBX is in production phase. Not on Critical Path.
  • HPDs remain an issue. Schedule recovery is
    possible.
Write a Comment
User Comments (0)
About PowerShow.com