Title: The ATLAS Hadronic Endcap Calorimeter


1
The ATLAS Hadronic Endcap Calorimeter
James L. Pinfold For the ATLAS Hadronic Endcap
Calorimeter Group
2
Hadronic Endcap CalorimeterLAr-Cu sampling
calorimeter covering 1.5 lt h lt 3.2
  • GOOD HE JET RESOLUTION (10 l of active
    cover.)
  • FULL HECFCAL h COVER (1-5-gt 4.8) for good
    Etmiss determination.
  • PUNCHTHROUGH TO m SYSTEM REDUCED by 11l
    thickness of HECsupport.

3
Hadronic Endcap Calorimeter Construction
Responsibilities
  • Absorber plate production
  • Alberta
  • Dubna
  • Protvino
  • Readout foils
  • Mainz
  • TRIUMF
  • EST boards
  • Lebedev
  • Module stacking centres
  • Dubna
  • MPI Munich
  • TRIUMF
  • Protvino
  • Cold electronics (preamps) cabling harness
  • MPI Munich
  • Calibration system
  • KOSICE
  • Mainz

4
Hadronic Endcap Segmentation
Front mod. 25 plates, rear mod. 17 plates
  • Composed of two wheels per end, 32 modules per
    wheel
  • Front wheel 67 tonnes 25 mm Cu plates
  • Rear wheel 90 tonnes 50 mm Cu plates
  • Channel count for both endcaps, 4416

5
HEC MODULE
PAD boards
EST boards
Honeycomb
Copper plates
Tie Rods
Connecting Bars
Cold Electronics
6
HEC Readout
  • Electrostatic Trans- former readout
  • Distance between
    Cu plates 8.5 mm
  • LAr gaps 1.954 mm
  • Robust against HV shorts

7
Cu Absorber Plate Production
  • Three sites Alberta, Dubna, Protvino
  • Roughly one sector(1/32nd) per month can be
    machined at Dubna Protvino. Since June 1st 1999
    2-gt3 per month can be machined at Alberta
  • Estimate machining finished by early 2002.
  • Eg Cu machining _at_ Alberta, using the CSR
    advanced machining facility

See the machining in realtime moving images
http//129.128.162.80/webcam/JavaCam.html
8
Series Production of Modules
  • 1st module completed in Munich on 4/16/ 99.

Module under HV test at TRIUMF
9
Quality Control
  • Quality control procedures defined in October
    1997, updated in November 1998.
  • 2000 testbeam QC database started at CERN
  • 2001-gt merging of QC databases from CERN
    institutes into LAr QC database.

Go-NoGo jigs
Cu density check
Template check
10
Cold Electronics
3 PSBs on back of each front module 2 PSBs on the
back of each rear module
11
Cold Testing
(7 out of 8 modules will be cold tested)
4 modules in cold test cryostat
Modules prepared for a cold test
12
Test Beam Setup
(1 in 8 modules will be beam tested)
Rotating to vertical
Mating the modules
Modules in the cryostat
13
Stacking Insertion of HEC wheels into the
Cryostat
Stacking
Crane
Wheel
Rotator
Air Pads
T6 Cryostat
14
Recent Future Testbeam
Test-beam summer 2000 involving 6 series modules
in the H6 beamline. Analysis of results recently
accepted by NIM Summer 2001 2
successful test-beam periods . H6 Joint
EMEC-HEC test planned for the August of 2002.
Using H1 cryostat deploy 1) EMEC 2) HEC FRONT
3) HEC REAR (HALF DEPTH)
15
Test Beam Results (1)Energy resolution for
electrons
  • Reported here are key results from the test of 6
    series production HEC modules
  • Results obtained in the summer of 2000

16
Test Beam Results (2)
  • Spatial uniformity of response to electrons as a
    variation of EM calib. Const. variation

Non-uniformity lt 1
17
Test Beam Results (3)Energy resolution for pions
18
Testbeam Results(4) Muon Detection
  • Using 150 GeV muons (most prob. muon signal

19
Testbeam Results(5) e/h Ratio
Ratio of response to electrons and hadrons
CMC is an energy dep. leakage correction
20
Final Remarks
  • Series production well underway 57 (76/134)
    modules stacked on schedule
  • 42 (57/134) modules Cold Tested.
  • All HEC only beam tests finished this summer!
  • Joint EMEC-HEC test beam next summer.
  • Joint EMEC-HEC-FCAL test in 2003
  • Stand/Table/Rotator for installation ordered and
    due December 2001.
  • Assembly area and clean rooms in Bat.180 ready.
  • Assembly of the HEC will start in March 2003 in
    Bat. 180 at CERN.