Status Report: Resource Adequacy RA and Long Term Procurement Planning LTPP - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

Status Report: Resource Adequacy RA and Long Term Procurement Planning LTPP

Description:

Adopted procurement policy framework (Jan-2004) Adopted RAR Framework (Oct-2004) Approved first 10-year of Long-Term ... 1/27 - CAISO resubmitted 2006 LCR study ... – PowerPoint PPT presentation

Number of Views:21
Avg rating:3.0/5.0
Slides: 13
Provided by: docsC
Category:

less

Transcript and Presenter's Notes

Title: Status Report: Resource Adequacy RA and Long Term Procurement Planning LTPP


1
Status ReportResource Adequacy (RA) and Long
Term Procurement Planning (LTPP)
  • CPUC Energy Division
  • Molly Tirpak Sterkel
  • Email mts _at_ cpuc.ca.gov Tel 415-703-1873
  • Power Association of Northern California
  • April 11, 2006

2
Key Milestones in RA and LTPP
  • 2004
  • Adopted procurement policy framework (Jan-2004)
  • Adopted RAR Framework (Oct-2004)
  • Approved first 10-year of Long-Term Plans
    (Dec-2004)
  • 2005
  • Established rules for System RAR program (Oct-04)
  • 2006
  • First round of System RAR compliance process
    underway
  • Two New Proceedings for RA and LTPP
  • RA Local RAR program rules under development
  • LTPP Next round of 10 year plans (2007-2016)
    will be reviewed

3
System RAR Program In Place for 2006
  • Applicable to all LSEs under CPUC jurisdiction,
    including 3 IOUs 12 ESPs
  • LSEs must meet 15-17 planning reserve margin
    based on monthly peaks
  • Based on a top down approach to monthly peaks
  • Must acquire qualifying capacity that meets
    availability requirements
  • Year-Ahead showing is for 90 of 115 of peak
    for a 5 month summer period
  • Month-Ahead is for 100 of 115 of peak
  • Sanctions/Penalties for LSE non-compliance

4
October 2005 RA Decision onLiquidated Damages
(LD) Contracts
  • LD Contracts phased out for RA Counting Purposes
  • No LD contracts starting after 10-29-05 count
  • Except DWR Contracts, LDs are limited to
  • 75 of an LSEs portfolio for 2006
  • 50 for 2007
  • 25 for 2008,
  • and 0 thereafter
  • For 2006, there are 6300 MW of LDs
  • LD contracts (not inc. DWR) are about 14 of
    filed RA Capacity
  • By 2007, most LD contracts expire
  • By 2008, only 2300 MW of non-DWR LD contracts

5
System RAR Compliance for 2006/2007
  • LSEs filed first year-ahead filings in Feb.
    2006
  • Showing at least 90 of the RA requirement (115
    of forecast load) is covered for 5 peak months of
    2006
  • Preliminary analysis shows 92 covered in
    aggregate
  • CPUC investigating possible compliance issues
  • LSEs will file first monthly filings in May
    2006
  • Due May 1st for June month
  • Monthly thereater
  • All LSEs will file year ahead 2007 showings
    October 2, 2006 (1st business day after 9/30)

6
New RA Proceeding R.05-12-013
  • Phase 1 Issues
  • Adoption of Local RA Requirement based on
    consideration of CAISOs LCR Study
  • Other Issues as-needed related to
  • Implementation
  • Compliance
  • Tradable Capacity Product
  • Phase 2 Issues
  • Capacity Markets tradable capacity product
  • Multi-year forward RA Requirement
  • Zonal RA Requirement
  • Other Implementation Issues/ General Order

7

Local RAR Consideration Underway
  • CAISO 2006 Local Capacity Report (LCR) - Sep-05
  • New Proceeding Opened - Dec-05
  • Parties filed Local RAR Proposals - Jan 24-06
  • CAISO filed supporting info on 2006 LCR -
    Jan-31-2006
  • CAISO Hosted Meet and Confer on 2007 LCR -
    Feb-17-06
  • Purpose was to lock in assumptions for 2007 study
  • Workshops Held
  • 2007 Local RAR Feb 8-9/Mar-15-06 re LCR study
    program
  • RE Tradable Capacity Product - Mar-27-06
  • CPUC Staff Report Issued on Local RAR - Apr-10-06
  • 2007 LCR expected from CAISO - Apr-21-2006
  • Expect CPUC decision to adopt Local RAR -
    Jun-2006

8
Milestones for Local RAR
4/21 - CAISO submits 2007 LCR study
5/15 - Draft Dec issued
1/24 - Local RAR proposals submitted 1/27 -
CAISO resubmitted 2006 LCR study
6/15 - CPUC vote on dec
10/2 - LSE submit RA filings for both 2007 System
RAR (year ahead) and 2007 Local RAR
4/18 - Opening Comments due
2/17 - CAISO started 2007 LCR study after the
meet confer session
5/3 - Close of CPUC Proceediing Record
4/28 - Reply Comments due
9
New Long Term Procurement Plan Proceeding
R.06-02-013
  • Phase 1 Issue
  • Need for Additional Policies to Support New
    Generation
  • Proposals were due on March 7, 2006
  • Workshop on March 14, 2006
  • Comments on 4/7 and 4/14
  • Planning for a June 2006 Decision
  • Phase 2 Issues
  • New Long Term Procurement Plans to be filed in
    Summer, decision by end of year.
  • No additional schedule details yet on plan
    filings

10
Proposals to Support New Generation
  • Commission received 18 responses on 3/2
  • Blink We must intervene to ensure new
    generation gets built
  • Dont Blink Give RA and LTPP policies a chance
    to work (with numerous other fixes)
  • Proposals that support other issues
  • Workshop - 3/14
  • Discuss proposals and need numbers
  • Intermediary Concept Presented
  • Comments Received on 4/7
  • Replies due on 4/14

11
Upcoming Milestones in Procurement
  • April 06 PGE Expected to file new Power Plant
    Application
  • May 06 Additional Schedule Details to be
    determined on LTPP Cycle
  • June 06 CPUC will consider Local RA Decision
  • CPUC will consider New Generation Decision
  • Summer 06 Long Term Procurement Plans Filed
  • Oct. 2 06 LSEs file 2007 Local RAR
    Demonstrations
  • LSEs file Year Ahead Summer 2007 RAR
  • December 06 CPUC Decision on LTPP
  • Spring 07 CPUC Decision on RA Phase 2 Issues
  • Capacity markets
  • RA General Order

12
CPUC Procurement and RA Website
  • Links to LTPP and RA key documents proposals
  • www.cpuc.ca.gov/static/hottopics/1energy/r0404003.