Title: Use of Moveable Barrier Walls on I275 in Northern Kentucky
1Use of Moveable Barrier Walls onI-275 in
Northern Kentucky
- Presented By
- Paul Looney, P.E.
- KYTC Division of Highway Design
- James Napier, P.E., P.L.S.
- WMB, Inc.
2Begin Project
End Project
3The Project
- 4-lane Interstate Pavement Rehabilitation
- Existing Concrete Pavement
- 6 PCC Shoulders
- 4 Inside
- 10 Outside
4(No Transcript)
5Can 2-Lanes Be Maintained?
- Bridge over Ohio River
- Twin bridges at Ky 8
- Reduced structure and width on existing mainline
shoulders
6(No Transcript)
7(No Transcript)
8(No Transcript)
9(No Transcript)
10Preliminary Decisions
- Maintain 1 lane in each direction
- Cross traffic over and construct one side
- Necessary due to constraints at each end of
project - Traffic should be analyzed to determine potential
problems
11Traffic Issues
- Peak-hour traffic exceeded single lane capacity
during weekdays
12Hourly Traffic I-275 EB (MP 12.6)April 11-13,
2006
13Hourly Traffic I-275 WB (MP 12.6)April 11-13,
2006
14I-275 EB (MP 12.7)Sept 11-16, 2006
15I-275 WB (MP 12.4)Sept 11-16, 2006
16Single Lane Traffic Impacts
- Maximum Backup EB- 0.5 mile
- Maximum Backup WB-5.3 miles
17(No Transcript)
18Administrative Direction
- Maintain 2 lanes in both directions
- Allow only off-peak single lane closures
19Is there another way?
- Nighttime work only?
- There are directional AM/PM peaks
- What if we could reverse the lanes to only keep 2
lanes in the peak direction?
20First KTC Project to Use Movable Concrete Traffic
Barrier (MCTB)
- I-275 Pavement Rehab ProjectBoone CountyItem
No. 6-2028.00
21TCP Alternates Considered
- Original Plan to Maintain One Lane in Each
Direction Separated by a 9T Wall - Did Not Meet Requirement to Keep Two Lanes Open
During Peak Traffic Hours (11.1 Million) - Part-Width Paving at Night and On Weekends
- Not Safe Would Lengthen Time to Complete
Project per District construction Personnel
(12.5 Million)
22TCP Alternates Considered
- Temporary Widening in The Median to Maintain Two
Lanes In Each Direction - Would Require Extensive Temporary Pavement and
Construction of a Temporary Bridge in the Median
at Exit 11 (16.0 Million) - Same as 3 Above Except Widening is Made Permanent
and Striped As Shoulder - Most Expensive Alternate and Same Reasons As For
3 Above (18.0 Million)
23Reversible Lane Scheme Selected
- Requires the Use of a Moveable Concrete Traffic
Barrier (MCTB) and a Barrier Transfer Machine
(BTM) - Barrier Moved Twice a Day
- Median Crossovers and Slip Ramps Used to Shift
Traffic to One Roadway
24Moveable Barrier Wall Transfer Machine
25Specific Wall Design Criteria
- MCTB size is 32 high x 24 wide at base
- Each MCTB section is 37 long with pin to pin
length of 39 - MCTB has New Jersey shape with T-Head
- BTM size is 12 high x 14 wide x 46 long
- BTM can move wall laterally from 4 to 18 feet
- Speeds up to 5 miles per hour
- Minimum Horizontal Radius 300 feet
- Grades up to 6 (10 With Special Design)
- BTM can lift wall up to 18 inches
26I-70 Project Indianapolis, In
FOR THIS APPLICATION THE BARRIER TRANSFER
MACHINE ALWAYS MOVES BARRIER FROM LEFT TO RIGHT
AS IT ADVANCES
27Design of PlansFor Reversible Lane
- Develop Reversible Lane Typical
- Required Paved Roadway Width
- 1.5 11.5 14 11.5 1.5 40
- Available Paved Roadway Width
- 4 24 10 38
- Decided to Widen Inside Shoulder 2
- Existing Shoulder Eastbound
- Permanent JPC Pavement Westbound
281
2
1
2
29Reversible Lane Configuration
30Design of PlansFor Reversible Lane
- Developing Reversible Lane Typical
- Fit Reversible Lane Typical to Existing I-275
Roadways
31Reversible Lane Plan
32Design Considerations
- Reduced Shoulder Widths at Ohio River Bridge (30
Roadway Gutter to Gutter)
33I-275 Westbound Approach toOhio River Bridge
34I-275 Westbound atOhio River Bridge
35Limited Time Disincentive
- 16 Calendar Days Per Roadway to Complete All Work
- Disincentive of 10,000 Per Day After 16 Days
36(No Transcript)
37(No Transcript)
38BTM Moving Wall atOhio River Bridge
39Design ConsiderationsContinued
- Reduced Shoulder Widths at Ohio River Bridge (30
Roadway Gutter to Gutter) - Reduced Roadway Width on Eastbound I-275 Bridge
at KY 8 Interchange (38 Gutter to Gutter)
40I-275 EastboundBridge over Ky 8
41Design ConsiderationsContinued
- Reduced Shoulder Widths at Ohio River Bridge (30
Roadway Gutter to Gutter) - Reduced Roadway Width on Eastbound I-275 Bridge
at KY 8 Interchange (38 Gutter to Gutter) - Where Is BTM Located When Not Moving Wall?
42BTM at Crossover(On-Site Storage Location)
43Other Time Restrictions(Placed on Contractor)
- Work Through Phase 2 by November 15, 2007
- Completion of Work by July 1, 2008
- Disincentive of 5,000 per day
44Construction Contract
- Let to Contract on July 27, 2007
- Winning Bid was 14,033,994
- W. L. Harper Company
- 2.67 Under Engineers Estimate
45Moveable Concrete Traffic Barrier Bid Items
- Moveable Concrete Traffic Barrier bid at 91.20
per LF for 13,440 LF - Temporary Impact Attenuator bid at 12,576.54
Each for 2 Attenuators - Total Cost 1,250,881
46MOVEABLE BARRIER WALL COSTS VS.PAVEMENT WIDENING
IN MEDIAN COSTS
47Not Included in Estimates
- Road User Costs
- Construction Time Saved Constructing Temporary
Pavement in Median - Construction Time Saved Removing Temporary
Pavement from Median
48PROBLEMS DURING CONSTRUCTION
49Mike Shayeson - PresidentThe Harper Co.
Contractors
50When To Use
- Need to Close Roadways or Lanes During
Construction - High ADTs
- Peaks in Traffic Volumes in Opposite Directions
- Peaks Exceed Maximum Traffic Volumes Available in
Lanes to Remain Open
51Other Uses
- For Shoulder Work to Create Additional Working
Room During Off Peak Hours - To Separate Work in the Median From Traffic and
Expand Work Area Along Median During Non-Peak
Hours - To Create Contra-Flow Lanes
- In Permanent Applications for Managed Lane
Applications
52One Source Item
- Currently the Moveable Concrete Traffic Barrier
and Transfer Machine are One Source Items - Both Are Produced by Barrier Systems, Inc., 180
River Road, Rio Vista, California 94571 Toll
Free Ph. 888-800-3691 - The Federal Highway Administration has Approved
the Use of This One Source Item for Use On All
Federal Projects - Ron Vititoe Midwest Regional Manager Phone
1-209-482-3020
53Use of Moveable Barrier Walls onI-275 in
Northern Kentucky
- Contact Info
- Paul Looney, P.E.
- KYTC Division of Highway Design
- Paul.Looney_at_ky.gov
- James Napier, PE, PLS
- WMB, Inc.
- 1950 Haggard Court
- Lexington, KY 40505
- Ph. 859-299-5226
- E-mail james_at_wmbinc.com