Use of Moveable Barrier Walls on I275 in Northern Kentucky - PowerPoint PPT Presentation

1 / 53
About This Presentation
Title:

Use of Moveable Barrier Walls on I275 in Northern Kentucky

Description:

Use of Moveable Barrier Walls on I275 in Northern Kentucky – PowerPoint PPT presentation

Number of Views:251
Avg rating:3.0/5.0
Slides: 54
Provided by: KYT81
Category:

less

Transcript and Presenter's Notes

Title: Use of Moveable Barrier Walls on I275 in Northern Kentucky


1
Use of Moveable Barrier Walls onI-275 in
Northern Kentucky
  • Presented By
  • Paul Looney, P.E.
  • KYTC Division of Highway Design
  • James Napier, P.E., P.L.S.
  • WMB, Inc.

2
Begin Project
End Project
3
The Project
  • 4-lane Interstate Pavement Rehabilitation
  • Existing Concrete Pavement
  • 6 PCC Shoulders
  • 4 Inside
  • 10 Outside

4
(No Transcript)
5
Can 2-Lanes Be Maintained?
  • Bridge over Ohio River
  • Twin bridges at Ky 8
  • Reduced structure and width on existing mainline
    shoulders

6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
(No Transcript)
10
Preliminary Decisions
  • Maintain 1 lane in each direction
  • Cross traffic over and construct one side
  • Necessary due to constraints at each end of
    project
  • Traffic should be analyzed to determine potential
    problems

11
Traffic Issues
  • Peak-hour traffic exceeded single lane capacity
    during weekdays

12
Hourly Traffic I-275 EB (MP 12.6)April 11-13,
2006
13
Hourly Traffic I-275 WB (MP 12.6)April 11-13,
2006
14
I-275 EB (MP 12.7)Sept 11-16, 2006
15
I-275 WB (MP 12.4)Sept 11-16, 2006
16
Single Lane Traffic Impacts
  • Maximum Backup EB- 0.5 mile
  • Maximum Backup WB-5.3 miles

17
(No Transcript)
18
Administrative Direction
  • Maintain 2 lanes in both directions
  • Allow only off-peak single lane closures

19
Is there another way?
  • Nighttime work only?
  • There are directional AM/PM peaks
  • What if we could reverse the lanes to only keep 2
    lanes in the peak direction?

20
First KTC Project to Use Movable Concrete Traffic
Barrier (MCTB)
  • I-275 Pavement Rehab ProjectBoone CountyItem
    No. 6-2028.00

21
TCP Alternates Considered
  • Original Plan to Maintain One Lane in Each
    Direction Separated by a 9T Wall
  • Did Not Meet Requirement to Keep Two Lanes Open
    During Peak Traffic Hours (11.1 Million)
  • Part-Width Paving at Night and On Weekends
  • Not Safe Would Lengthen Time to Complete
    Project per District construction Personnel
    (12.5 Million)

22
TCP Alternates Considered
  • Temporary Widening in The Median to Maintain Two
    Lanes In Each Direction
  • Would Require Extensive Temporary Pavement and
    Construction of a Temporary Bridge in the Median
    at Exit 11 (16.0 Million)
  • Same as 3 Above Except Widening is Made Permanent
    and Striped As Shoulder
  • Most Expensive Alternate and Same Reasons As For
    3 Above (18.0 Million)

23
Reversible Lane Scheme Selected
  • Requires the Use of a Moveable Concrete Traffic
    Barrier (MCTB) and a Barrier Transfer Machine
    (BTM)
  • Barrier Moved Twice a Day
  • Median Crossovers and Slip Ramps Used to Shift
    Traffic to One Roadway

24
Moveable Barrier Wall Transfer Machine
25
Specific Wall Design Criteria
  • MCTB size is 32 high x 24 wide at base
  • Each MCTB section is 37 long with pin to pin
    length of 39
  • MCTB has New Jersey shape with T-Head
  • BTM size is 12 high x 14 wide x 46 long
  • BTM can move wall laterally from 4 to 18 feet
  • Speeds up to 5 miles per hour
  • Minimum Horizontal Radius 300 feet
  • Grades up to 6 (10 With Special Design)
  • BTM can lift wall up to 18 inches

26
I-70 Project Indianapolis, In
FOR THIS APPLICATION THE BARRIER TRANSFER
MACHINE ALWAYS MOVES BARRIER FROM LEFT TO RIGHT
AS IT ADVANCES
27
Design of PlansFor Reversible Lane
  • Develop Reversible Lane Typical
  • Required Paved Roadway Width
  • 1.5 11.5 14 11.5 1.5 40
  • Available Paved Roadway Width
  • 4 24 10 38
  • Decided to Widen Inside Shoulder 2
  • Existing Shoulder Eastbound
  • Permanent JPC Pavement Westbound

28
1
2
1
2
29
Reversible Lane Configuration
30
Design of PlansFor Reversible Lane
  • Developing Reversible Lane Typical
  • Fit Reversible Lane Typical to Existing I-275
    Roadways

31
Reversible Lane Plan
32
Design Considerations
  • Reduced Shoulder Widths at Ohio River Bridge (30
    Roadway Gutter to Gutter)

33
I-275 Westbound Approach toOhio River Bridge
34
I-275 Westbound atOhio River Bridge
35
Limited Time Disincentive
  • 16 Calendar Days Per Roadway to Complete All Work
  • Disincentive of 10,000 Per Day After 16 Days

36
(No Transcript)
37
(No Transcript)
38
BTM Moving Wall atOhio River Bridge
39
Design ConsiderationsContinued
  • Reduced Shoulder Widths at Ohio River Bridge (30
    Roadway Gutter to Gutter)
  • Reduced Roadway Width on Eastbound I-275 Bridge
    at KY 8 Interchange (38 Gutter to Gutter)

40
I-275 EastboundBridge over Ky 8
41
Design ConsiderationsContinued
  • Reduced Shoulder Widths at Ohio River Bridge (30
    Roadway Gutter to Gutter)
  • Reduced Roadway Width on Eastbound I-275 Bridge
    at KY 8 Interchange (38 Gutter to Gutter)
  • Where Is BTM Located When Not Moving Wall?

42
BTM at Crossover(On-Site Storage Location)
43
Other Time Restrictions(Placed on Contractor)
  • Work Through Phase 2 by November 15, 2007
  • Completion of Work by July 1, 2008
  • Disincentive of 5,000 per day

44
Construction Contract
  • Let to Contract on July 27, 2007
  • Winning Bid was 14,033,994
  • W. L. Harper Company
  • 2.67 Under Engineers Estimate

45
Moveable Concrete Traffic Barrier Bid Items
  • Moveable Concrete Traffic Barrier bid at 91.20
    per LF for 13,440 LF
  • Temporary Impact Attenuator bid at 12,576.54
    Each for 2 Attenuators
  • Total Cost 1,250,881

46
MOVEABLE BARRIER WALL COSTS VS.PAVEMENT WIDENING
IN MEDIAN COSTS
47
Not Included in Estimates
  • Road User Costs
  • Construction Time Saved Constructing Temporary
    Pavement in Median
  • Construction Time Saved Removing Temporary
    Pavement from Median

48
PROBLEMS DURING CONSTRUCTION
49
Mike Shayeson - PresidentThe Harper Co.
Contractors
50
When To Use
  • Need to Close Roadways or Lanes During
    Construction
  • High ADTs
  • Peaks in Traffic Volumes in Opposite Directions
  • Peaks Exceed Maximum Traffic Volumes Available in
    Lanes to Remain Open

51
Other Uses
  • For Shoulder Work to Create Additional Working
    Room During Off Peak Hours
  • To Separate Work in the Median From Traffic and
    Expand Work Area Along Median During Non-Peak
    Hours
  • To Create Contra-Flow Lanes
  • In Permanent Applications for Managed Lane
    Applications

52
One Source Item
  • Currently the Moveable Concrete Traffic Barrier
    and Transfer Machine are One Source Items
  • Both Are Produced by Barrier Systems, Inc., 180
    River Road, Rio Vista, California 94571 Toll
    Free Ph. 888-800-3691
  • The Federal Highway Administration has Approved
    the Use of This One Source Item for Use On All
    Federal Projects
  • Ron Vititoe Midwest Regional Manager Phone
    1-209-482-3020

53
Use of Moveable Barrier Walls onI-275 in
Northern Kentucky
  • Contact Info
  • Paul Looney, P.E.
  • KYTC Division of Highway Design
  • Paul.Looney_at_ky.gov
  • James Napier, PE, PLS
  • WMB, Inc.
  • 1950 Haggard Court
  • Lexington, KY 40505
  • Ph. 859-299-5226
  • E-mail james_at_wmbinc.com
Write a Comment
User Comments (0)
About PowerShow.com