Calais, MESt' Stephen,NB Border Crossing Project A Case Study - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Calais, MESt' Stephen,NB Border Crossing Project A Case Study

Description:

New crossing discussed for about 30 years. 8th busiest commercial crossing ... Annual traffic 2.9 million vehicles. 7,500 AADT including 550 heavy trucks ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 25
Provided by: williamp5
Category:

less

Transcript and Presenter's Notes

Title: Calais, MESt' Stephen,NB Border Crossing Project A Case Study


1
Calais, ME-St. Stephen,NB Border Crossing
Project A Case Study
2
Agenda
  • Introduction
  • Planning, coordination, and permitting
  • Considerations during Design
  • Considerations during Construction
  • Lessons learned

3
(No Transcript)
4
Introduction
  • New crossing discussed for about 30 years
  • 8th busiest commercial crossing along the U.S. /
    Canadian border
  • Annual traffic 2.9 million vehicles
  • 7,500 AADT including 550 heavy trucks
  • Delays inbound to the U.S. can be up to 2 hours
  • Truck traffic entering Maine has doubled since
    NAFTA implementation (70,000 to 140,000 annually)

5
(No Transcript)
6
(No Transcript)
7
Project Management
  • Maine and New Brunswick DOTs share the costs of
    bridge design/construction on a 50/50 basis
  • MaineDOT Bridge design lead
  • MaineDOT Project Manager for the bridge
    construction portion

8
Agencies U.S.
  • FHWA lead federal agency
  • MaineDOT
  • GSA cooperating agency
  • U.S. Department of Homeland Security
  • Customs and Border Protection
  • U.S. Border Patrol
  • U.S. Department of State

9
Agencies Canada
  • New Brunswick Department of Transportation
  • Transport Canada
  • Canada Border Services Agency
  • Canada Revenue Agency
  • Citizenship Immigration Canada
  • Foreign Affairs Canada
  • Royal Canadian Mounted Police

10
  • Four Alternatives including no action considered
  • Alternatives 2A and 3 deemed viable
  • Chosen Alternative 3 Calais Industrial Park

11
Timeline
  • Preliminary design and NEPA compliance started
    1999
  • FHWA issued FONSI in July 2002
  • Final design and permittingJuly 2002 September
    2006
  • Construction Begins
  • NBDOT - Spring 2006
  • MaineDOT Spring 2007
  • GSA and CBSA - 2007
  • Open to traffic - Fall 2008

12
This Last Year
  • January 2006 Reevaluation of 2001 Environmental
    Assessment
  • May 2006 Army Corps of Engineers request for
    details
  • June 2006 Maine DOT replies
  • June 2006 - US Coast Guard Approval
  • Sept 2006 Army Corps of Engineers approval
  • Project tendered September 27, 2006

13
Planning
  • Maine and New Brunswick circulated studies at
    same time
  • Changes in process (New Brunswick was very
    flexible)
  • Public Involvement
  • 9 PAC meetings, 2 public meetings, and 1 formal
    public hearing
  • MaineDOT GSA enter into a cost reimbursement
    agreement for NEPA

14
International Coordination
  • Partnership, respect for others process,
    flexibility
  • International Stakeholders workshops
  • Every 6 months to 1 year throughout the process
  • International partnering agreement
  • Master schedule discussed and developed
  • Good forum for troubleshooting problems like
    labor issues
  • Communication between workshops
  • Find ways to maintain national focus for future
    funding purposes
  • TBWG, BSPC, etc.

15
Permitting Coast Guard Bridge Permit
  • Required for an international bridge
  • Cooperating agency under NEPA
  • Bridge permit
  • 40 plans required
  • Approved Presidential Permit is also required
  • Long lead time is necessary

16
Permitting Presidential Permit
  • U.S. Department of State 2003-2005
  • No precedent for the northern border
  • First one in at least 30 years
  • Guidelines for complete application
  • State Dept. distributes application to at least
    55 agencies for comment and determinations
  • Prepared and circulated own EA and FONSI as part
    of their process as well

17
Treaties and Approvals
  • Transport Canada New Brunswick agreement
  • This project spurred a new Canadian equivalent of
    the U.S. Presidential Permit process
  • International Boundary Commission approval
  • International Joint Commission or exchange of
    diplomatic notes required between Foreign Affairs
    Canada and U.S. State Department
  • MaineDOT - New Brunswick agreement to construct
    and reimburse

18
Design Considerations U.S.
  • Inspection facility increased in size from 20
    to 50 acres. (Post 911)
  • MaineDOT GSA cost reimbursement agreements
  • Advance notice for materials and people crossing
    the border
  • Buy America clause for steel
  • MaineDOT NBDOT funding and management agreement
  • Bridge contractor fact sheet and
    prequalification
  • Coordination between GSA and MaineDOT of design
    issues staging issues, exchange of plans, etc.

19
Considerations During Construction - Labor
  • Labor and requirements for foreign workers
  • Human Resources Development Canada-Canadian Labor
    Market Opinion
  • CBSA immigration
  • Maine Dept of Labor
  • Security and background check
  • Ideal worker dual citizenship, no criminal
    record

20
Considerations During Construction - Security
  • Security during construction
  • U.S. Border Patrol
  • RCMP
  • Movement of workers must be able to cross
    border within project limits
  • No precedent on this issue

21
Considerations During Construction - Taxes
22
Lessons Learned
  • Partnerships among agencies on both sides of the
    border that are built to last
  • Respect for others and stay flexible
  • Communicate and communicate some more
  • Combine NEPA/Presidential Permit Process as much
    as possible
  • Maximize the use of the cooperating agencies
  • Taxation issues for international bridge projects
    are complex

23
Project Status
  • International Bridge Construction (11.58 Million)
  • March 2007 Summer 2008
  • U.S. Inspection Facility
  • Summer 2007 Fall 2008
  • US Route 1 (9.33 Million)
  • April 2007 Summer 2008
  • NB Route 1
  • Spring 2007
  • Canadian Inspection Facility
  • Summer 2007 Fall 2008

24
Calais, ME-St. Stephen,NB Border Crossing
Project
Write a Comment
User Comments (0)
About PowerShow.com