Failure Case Study of Construction at a Solid Waste Site - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Failure Case Study of Construction at a Solid Waste Site

Description:

Failure Case Study of Construction at a Solid Waste Site K. Madhavan, Ph.D., P.E., Dept. of Civil & Env. Engineering Christian Brothers University – PowerPoint PPT presentation

Number of Views:491
Avg rating:3.0/5.0
Slides: 20
Provided by: maescOrgm
Category:

less

Transcript and Presenter's Notes

Title: Failure Case Study of Construction at a Solid Waste Site


1
Failure Case Study of Construction at a Solid
Waste Site
  • K. Madhavan, Ph.D., P.E.,
  • Dept. of Civil Env. Engineering
  • Christian Brothers University
  • Memphis, TN, 38104

2
Geotechnical Courses
  • Required Courses
  • - CE 322 Geotechnical Engineering
  • - CE 322L Geotech Lab
  • - CE 340 Design of Foundations
  • Elective Course
  • - CE 418 Advanced Design of Foundations

3
Motivation
  • Technical Issues Brings together all principles
    applications including from other
    required/elective courses
  • Opportunities to discuss professional and ethical
    issues
  • Perhaps students understand materials better
    (connecting concepts with applications)

4
Project Data
  • Site was an old sand gravel dredging area
    around 1900s
  • A clay cap was in place
  • 23 acre site
  • Four buildings (one two storey-140,000 sq. ft.)
    on pile foundations
  • Buildings were on monotube piles

5
Construction at a Landfill Site
  • Geotechnical investigations and report were done
    in 1977-78
  • - Not to build at the site and find another site
  • - The client chose to build at the site (1979)
  • - The cost of construction about 6M
  • - After several years of use, buildings
  • were not usable and were vacated
  • - A remedial work was done for about 10M
  • - Litigation between parties and was
  • settled out of court

6
Construction Details
  • A gas collection system was installed in a sand
    layer above the waste
  • Numerous obstructions were encountered while
    driving the piles
  • Utilities were grade supported
  • Monotube piles were filled with concrete

7
Structural Details
  • All buildings had structural floor slabs
  • Floor beams supported by piles and one-way slabs
  • Superstructures were of steel frames with
    exterior metal sheathing

8
Performance of Buildings, Pavement, and other
construction
  • Cracks on floors and walls, floor sloped
  • Methane gas inflow in buildings
  • Buildings Differential settlements up to 18
    inches
  • Parking area settled as much as 3 ft
  • Buried utilities were affected
  • Large amount of asphalt added to pavement

9
Geotechnical Investigations
  • About 100 boreholes
  • Soil Layers
  • Clay cap
  • Landfill material 30 to 60 ft (materials
    including car bodies, concrete slabs, etc)
  • Beneath landfill loose sand layer (left from
    previous dredging operations)
  • Bottom strata (100 ft below) dense sand
    suitable to receive pile foundations

10
Remediation
  • Use of minipiles to underpin and relevel the
    buildings
  • Use of driven piles to support the outside
    structures (lamp posts, access ramps)
  • Use of design-build contract
  • Use of best value concept in awarding the
    contract

11
Analysis of Failure
  • Possible reasons
  • Pile Foundation System
  • - Pile installation monitoring
  • - use of proper pile wall thickness
  • - depth of piles (obstructions)
  • - Negative skin friction (excessive )
  • - No provision to minimize it
  • - The negative skin friction may have
  • added to the load applied at bearing

12
Analysis Contd
  • Gas Collection System
  • - at a landfill site was a poor choice
    Construction of the gas collection system on
    grade
  • - water main breaking and washing out part of
    the sand layer gas collection system

13
Geotechnical Concepts
  • Problems in building at landfill sites
  • Total and differential settlements
  • Negative skin friction (means of reducing)
  • Providing proper gas collection system
  • Construction control monitoring
  • Design-build concept
  • Performance oriented specifications

14
References
  • ASCEs Journal of Performance of Constructed
    Facilities
  • ASCEs Journal of Professional Issues in
    Engineering Education and Practice
  • J. Feld K.L. Cooper, Construction Failure,
    Second Edition, 1997, John Wiley Sons.

15
Questions?
  • Comments?

16
Installation of Minipiles
  • From the floor surface, holes (7dia) were
    drilled through the beams up to the desired depth
  • 4 diameter pipes were inserted
  • The smaller pipe was twisted and pulled out for a
    short distance
  • and concrete grout was injected

17
Installation Contd
  • The smaller pipe was withdrawn and high strength
    steel casing was inserted
  • For piles at locations other than through the
    existing monotube piles, 12 diameter monotube
    pile was driven and similar minipile was
    constructed

18
Installation Contd
  • After the pile has reached its design strength,
    the floor was lifted using the pile as a reaction
    pile
  • The piles were connected to the beams and the
    original monotube piles were cut off.

19
Pile Testing
  • Four monotube piles were load tested and the
    ultimate capacity was 150 Tons
  • Two other 12 diameter pipe piles were tested and
    the ultimate capacity was 200 Tons.
Write a Comment
User Comments (0)
About PowerShow.com