Title: GLAST Proposal Review
1GLAST Large Area Telescope LAT Project
Management William E. Althouse Stanford Linear
Accelerator Center Stanford University LAT
Instrument Project Manager wea_at_slac.stanford.edu
2LAT Project Management
- Outline
- LAT Project overview scope, schedule
- Participants, WBS, organization, relationships
- Funding
- System engineering, configuration management
- Project management control system description,
status - Risk management contingency management
- Major milestones, issues mitigations,
conclusions
3Overview
4LAT Project Scope
- Develop deliver the LAT flight instrument in
accordance with Collaboration proposal (Nov. 99)
GLAST Mission level II specs - Ground support equipment
- Balloon flight test
- Support integration into GLAST observatory
- Support launch, post-launch mission operations
- Develop provide Instrument Operations Center
- Develop provide ground software necessary to
support the above - Develop ground software for science data analysis
- Provide management, system engineering, and
performance safety assurance as required - Provide E/PO services for GLAST Mission
- Support participate in Mission Operations
Data Analysis
5Schedule Overview
Calendar Years
2003
2010
2000
2002
2004
2005
2001
I-CDR (Joint DOE/NASA Review)
Inst. Delivery
Launch
M-CDR
SRR
NAR
PDR
Implementation
Ops.
Formulation
Inst. IT
Build Test Engineering Models
Build Test Flight Units
Inst.-S/C IT
Schedule Reserve
1st Joint DOE/NASA of GLAST LAT
Baseline Review
6Organization
7LAT Development Organizations
- California State University at Sonoma (SSU)
- University of California at Santa Cruz - Santa
Cruz Institute of Particle Physics (UCSC/SCIPP) - Centre National de la Recherche Scientifique /
Institut National de Physique Nucléaire et de
Physique des Particules (CNRS/IN2P3)1 - Commissariat à l'Energie Atomique / Direction des
Sciences de la Matière/ Département
d'Astrophysique, de physique des Particules, de
physique Nucléaire et de l'Instrumentation
Associée (CEA/DSM/DAPNIA)1 - Goddard Space Flight Center Laboratory for High
Energy Astrophysics (NASA/GSFC/LHEA) - Hiroshima University2
- Institute for Space and Astronautical Science
(ISAS)2 - Istituto Nazionale di Fisica Nucleare (INFN)
- Naval Research Laboratory (NRL)
- RIKEN2
- Royal Institute of Technology (KTH)3
- Stanford University Hanson Experimental Physics
Laboratory (SU-HEPL) - Stanford University - Stanford Linear Accelerator
Center (SU-SLAC) - Stockholm University3
- Texas AM University Kingsville
- University of Washington 1French Team
- 2Japanese GLAST Collaboration (JGC)
- 3Swedish GLAST Collaboration (SGC)
8Work Breakdown Structure
9GLAST LAT Organization
Collaboration Science Team
E/PO L. Cominsky, SSU
Principal Investigator P. Michelson, SU
SSAC N. Gehrels, GSFC
Instrument Scientist S. Ritz, GSFC
Project Manager W. Althouse, SU-SLAC
Instrument Design Team T. Kamae, SU-SLAC
IPO
Project Controls T. Boysen, SU-SLAC
Integration Test M. Nordby, SU-SLAC
Mech. Systems M. Nordby, SU-SLAC
10Relations between LAT Organizations Technical
direction (deliverables flow oppositely)
DOE/NASA JOG
Relationships established by MoAs IAs
Level I Documents
Level II Documents
NASA/GSFC GLAST Project Office
SU-SLAC IPO
Level III Documents
SU-HEPL IOC Mgr.
SU-SLAC IT Mgr.
UCSC Tkr Mgr.
GSFC/LHEA ACD Mgr.
NRL Cal Mgr.
SU-SLAC SAS Mgr.
SU-SLAC Chief Elec. Engr.
SU-SLAC Mech. Sys. Engr.
KTH Stockholm Univ.
CEA/DAPNIA French Proj. Mgr IN2P3
SU-SLAC Tkr Engr.
JGC Si Det. Mgr. (Hiroshima)
Collaboration Institutions
INFN Labs Italian Proj. Mgr. (Pisa)
UCSC
SU-HEPL
NRL
CEA/DAPNIA (Power Sys)
GSFC/LHEA
SU-SLAC
11Funding
12Relations between LAT Organizations Funding
Japan
Sweden
Italy
France
U.S.A.
Ministry of Education, Culture, Sports, Science,
Technology
DOE
KEK (US-Japan)
SU
SLAC
IPO
JGC
ISAS
Hiroshima University
RIKEN Institute
UCSC
HEPL
SSU
13LAT WBS 4.1 Funding
Total 158.2M
14LAT WBS 4.1 Funding
15System Engineering
16System Engineering
- System trade studies
- Decomposition and validation of requirements
- LAT System and Subsystem Requirements
- Subsystem Interface Control Documents (ICDs)
- Technical risk assessment
- Parts and materials planning, qualification,
listing - FMECA, fault tree analysis
- Design integration and verification
- Support Instrument/Observatory ICD development
- Coordination with spacecraft contractor
- Supported by IDT
17LAT Trade Studies
- Many studies complete prior to Nov. 99 proposal
(S. Ritz presentation) - Studies completed since selection
- Tracker SSD size, pitch ? instrument footprint,
mass - SSD spec finalized, prototypes made and evaluated
- Tracker radiator thickness distribution
- Grid material Al vs. CFC
- Aluminum selected
- To be resolved
- ACD segmentation
- Optimize number of on-board processors
- Optimize science during intense solar flares
- Optimize IT, calibration and verification
testing plans - System Engineer supports subsystem internal trade
studies
18LAT Specification Tree
- Level II(b) specsderived from II(a)
- LAT Performance Specs collect all applicable
Level IIrequirements into one place
19Configuration Management
- All project documentation stored in central
database, with individual controlled access via
WWW - Configuration Item List maintained by LAT
Document Librarian - Single Document Change Notice (DCN) form for
initial release to configuration control
(technical baseline), and to record changes
includes provision for red-line markups - Subsystem managers approve majority of changes
(detailed specifications, drawings) - LAT CCB approves changes to level III
documents/baselines
20Integrated PMCS
DOE/NASA funded elements only
- Copy of SLAC systems for PEP II, BaBar, SPEAR
III
21PMCS A Work in Progress
- Developing WBS and WBS dictionary
- Developing bottoms-up cost estimate
- Performing systematic contingency analysis
- Primavera P3
- Developing resource loaded schedules
- Identifying key milestones, external links (held
in PM WBS) - Developing accounting interfaces
- Development toward baseline
- All inputs due in March
- First process cycle in April
- Stability by June
- Budget and schedule baselines ready in July
22Status of PMCS Inputs
234.1 GLAST LAT PROJECT
244.1 GLAST LAT PROJECT
INCOMPLETE
25Risk Management
26Risk Management
- Risk management tools
- Risk identification management risk reduction
planning - Performance metrics
- Contingency (reserve/margin) management
- Single interface at DOE, NASA, IPO for all
requirements - Weekly telecon meetings
- Thorough validation verification processes
27Risk Reduction Planning
- Use of engineering models to minimize activities
in series with instrument integration, test and
delivery schedule - Grid engineering model and instrument thermal
model permit independent testing of flight
radiators - Electronics EMs to permit early flight software
verification, support beam test calibration
activities - Tracker, Calorimeter and ACD EMs to support early
flight software verification, support equipment
and test software/procedure verification - ACD EM to support beam test calibration
- SSD trade study balanced margins for
- Science requirements
- Mass ? instrument footprint ? SSD size
- Power ? number of signal channels ? SSD strip
pitch - Considering construction of thermal vacuum test
facility at SLAC to reduce risk of dependence on
off-site facilities - Study team to develop calibration plan, IT
strategies
28Technical Performance Metrics
29Instrument Mass
30Instrument Power
31LAT DOE NASA Cost
32Major Milestones, Issues, Conclusions
33LAT Project Milestones
- Instrument System Requirements Review (SRR)
9/28/00 (C) - LAT Preliminary Design Review (PDR)
8/6/01 - LAT Critical Design Review (CDR) 8/5/02
- Subsystems deliveries for beam test calibrations
5/15/03-8/1/03 - Calibration unit ready for beam tests 9/1/03
- Subsystem deliveries for instrument IT
10/1/03-12/24/03 - Calibration activities complete
1/26/04 - Flight hardware delivered to LAT integration
- LAT ready for environmental testing 4/9/04
- LAT Pre-Ship Review (PSR) 10/7/04
- LAT ready for integration with Observatory
12/22/04 - GLAST launch 9/05
34Project Issues and Mitigations
- International commitments
- Aggressively working to get signed MoAs and
International Agreements - DOE/NASA Implementing Arrangement
- Working to facilitate agreement
- Flight software development
- Aggressively recruiting additional manpower
- Balloon flight schedule
- Working to reduce conflicting demands on shared
personnel - Lack of SLAC on-site space experienced EEE parts
engineer - Seeking local contractor help
- Use of off-site environmental test facilities
- Proposed on-site thermal vacuum test facility
- Inadequate reserves to deal with significant
budget/schedule hiccups by any major sponsor
35Project Managers Conclusions
- We have developed the organization to do the job
- We have identified and are strengthening weak
spots - Technical design was very mature at start of
Formulation Phase - We are focusing on developing a sound project
basis - Project is schedule driven, compressed between
availability of funding and launch - After assuring performance and safety, tracking
and controlling schedule progress is paramount - Combined DOE, NASA and other domestic and foreign
partner resources make the ambitious LAT goals
possible - Dont go to launch pad with our fingers crossed
- Do the necessary planning, finish design and fab
as early as prudent, to leave maximum time for
testing - Test thoroughly to develop confidence