Title: APGC4ISR BRAC UPDATE


1
APG/C4ISR BRAC UPDATE
  • SAME-Regional Event
  • LTC Thomas Tickner
  • CPT BJ Kraemer

2
C4ISR Phase 2 C2/CNT East
Location Aberdeen Scope 650,000 SF of new
high-tech, electronics-communications RD
facility Delivery Method DBB AE Ewing Cole
C2/CNT East CWE 150-200M Advertise 26 Jan
09 Bid Opening 7 Apr 09 Award 21 Apr 09 Status
Advertised. Building turnover 31 Dec 10, site
work complete Aug 11. Early Site Package awarded
3 Feb 09 for 2M and Magazine Road awarded 27 Feb
09 for 0.4M to clear C2/CNT East footprint.
3
Consolidated North
Location Aberdeen Scope 140,000 SF of new
integration, fabrication and research and
development facility Delivery Method DBB AE
Jacobs Consolidated North CWE 40-60M Advertise
11 Jun 09 Bid Opening 24 Jul 09 Award 7 Aug
09 Status 95 Design due 30 Apr 09. Building
turnover 31 Dec 10.
4
Building 5100
Location Aberdeen Scope 109,000 SF of
adaptive re-use space for integration,
fabrication and research and development facility
Delivery Method DBB AE Jacobs Bldg 5100 CWE
15-30M Advertise 18 Jun 09 Bid Opening 31 Jul
09 Award 14 Aug 09 Status 95 Design due 7 May
09. OCS footprint clears 30 Sep 09. Building
turnover 31 Dec 10.
5
JSEC (Joint Satellite Engineering Center)
Location Aberdeen Scope 98,000 SF of
satellite engineering and research and
development facility Delivery Method DBB AE
USACE JSEC CWE 30-50M Advertise 2 Jul 09 Bid
Opening 14 Aug 09 Award 28 Aug 09 Status 95
Design due 21 May 09. Building turnover 31 Dec 10.
6
Integration Facility
Location Aberdeen Scope 85,000 SF of new
integration and fabrication facility Delivery
Method DBB AE Jacobs Integration Facility CWE
5-15M Advertise 15 Dec 09 Bid Opening 15 Feb
10 Award 15 Apr 10 Status 35 Design received
25 Mar 09. OCS footprint clears 30 Sep 10.
Building turnover 30 Jun 11.
7
C4ISR Phase 2 Site/Utilities
Location Aberdeen Scope Electrical
Distribution Substation, Water Sewer and
Roadway/Intersection Improvements within the
Phase 2 footprint Delivery Method DBB AE
Jacobs Site/Utilities CWE 15-30M Status
Multiple solicitation packages. Electrical
Substation Distribution 95 Design due 1 Jun
09. Water Sewer 95 Design due 24 Apr 09.
Roadway improvements within Phase 2 project area
95 design due 25 May 09.