1Market Readiness Scorecard Summary Findings
April 13, 2001
2Readiness Scorecards
- Readiness Scorecards are issued on a weekly basis
- Scorecards issued to MP project managers
- Data Conversion (TDSPs)
- One TDSP having minor conversion problems
- TDSP as LSE issues (IOU TDSPs)
- Market Operations Interface, API (QSEs).
- On Track
- At Risk
- Problem
3Readiness Scorecards (contd)
- Registration and Agreements
- Generation Asset Data Forms (Resources)
- ERCOT-Polled Metering Proposals (TDSPs).
- NOIE meter point Registration (TDSPs)..
- EDI Testing (CRs and TDSPs).
- TDSP as LSE issues (IOU TDSPs)
- Private WAN Connection (QSEs and TSPs)
- Market Operations Interface, Portal (QSEs).
- Real Time Communications RTU/ICCP
4Registration and Agreements
- 325 Market Participation Applications Received
- 36 QSEs (30 expect to be in pilot)
- 102 LSEs (12 REPs expect to be in pilot)
- 122 TDSPs
- 65 Resource entities
5Registration and Agreements
- Issues
- TDSPs 7 Munis and Coops have not registered
- LSEs 6 of 102 applications pending
identification of a QSE - All CRs participating in pilot have QSEs
designated - Resources 8 of 65 applications pending
identification of a QSE - Action Plan
- ERCOT contacting all unregistered Munis and Coops
- LSEs and Resources understand the need to
identify QSE under negotiations - Requested PUCT serves approved Protocols to all
affected parties
6Generation Asset Data Forms
546 Units connected to ERCOT Grid
286
264
Action Items ERCOT contacting Resource
Entities ERCOT validating forms received
7Metering Design Proposal Status
Network Model EPS Proposals Identify 462
Active Units
137
115
As of 04-12-2001
124
86
Action Items ERCOT contacting TDSPs for
missing proposals ERCOT working with TDSPs to
approve pending proposals.
8NOIE Meter Point Registration Status
122 Munis and Coops Identified
As of 04-12-2001
No Meter Form Received
NOIE Meter Form
20
102
Received
16
84
Action Items ERCOT contacting missing
NOIEs ERCOT validating forms received
9EDI Testing
- Issues
- Start of End to End testing was delayed one week
- ERCOT received test transactions from CRs
starting on 4/2 (originally scheduled to receive
them on 3/26 ) - As of 4/12, ERCOT systems have been unable to
send all required responses - Action Plan
- Parties have agreed to implement some
contingencies to make up the time - ERCOT continues to work with all parties on
additional contingency measures to enable
switches by 5/31
10Private WAN Connection
- Issues
- Frame Relay
- QSEs 16 of 21 QSEs that need frame relay
circuits have completed installation and testing - Point to Point
- 10 of 24 QSEs that need point to point circuits
have completed installation and testing - TDSPs ERCOT completed frame relay circuit
installations at all TSPs. - Action Plan
- Client site installation issues have been
escalated to project managers
11Market Operations Interface (API)
- Issues
- Connectivity Tests
- All 21 QSEs that will use the programmatic
interface have completed XML connectivity tests - Functional Tests
- All 21 QSEs that will use the programmatic
interface have completed XML functional tests - Mock Market Functional Tests
- All 21 have passed the initial secure transfer
connectivity test on the operational system - Functional qualification will continue into
subsequent weeks of the mock market - Action Plan
- Will monitor performance during the next two
weeks of mock market to complete qualification
12Market Operations Interface (Portal)
- Issues
- The ERCOT portal has experienced various problems
which has not allowed proper qualification
testing on the portal - 8 QSEs will use portal only during mock market
and beginning of pilot (none will represent
generation) - Action Plan
- Functional qualification will be performed in
parallel with subsequent weeks of mock market - ERCOT is working with vendor on system fixes
identified during the mock market test
13Real Time Communications (ICCP/RTU)
- Issues
- Completed technical testing of RTU with 8 out of
18 QSEs - Resource specific testing will require data
submission from all generation units for each QSE
(start 4/16/01) - Data from many generation units in network model
is missing as QSEs finalize relationships with
resource owners who need to submit data forms - Action Plan
- ERCOT is working with resource owners to expedite
submission of data forms