Title: Market Readiness Scorecard: Summary Findings


1
Market Readiness Scorecard Summary Findings
Cheryl Moseley Business Rules and Contracts
Manager April 6, 2001
2
Readiness Scorecards
  • Readiness Scorecards are issued on a weekly basis
  • Scorecards issued to MP project managers
  • Scorecard areas for todays report
  • Registration Agreements (All)..
  • Data Conversion (TDSPs)
  • Generation Asset Data Forms (Resources)
  • ERCOT-Polled Metering Proposals (TDSPs)
  • NOIE meter point Registration (TDSPs)...
  • EDI Testing (CRs and TDSPs)..
  • EDI Systems (TDSPs).
  • TDSP as LSE issues (IOU TDSPs)
  • Private WAN Connection (QSEs and TSPs).
  • Market Operations Interface, API (QSEs).
  • Market Operations Interface, Portal (QSEs).
  • Real Time Communications RTU/ICCP

3
Registration and Agreements
  • 319 Market Participation Applications Received
  • 36 QSEs (30 expect to be in pilot)
  • 102 LSEs (12 REPs expect to be in pilot)
  • 120 TDSPs
  • 61 Resource entities

4
Registration and Agreements
  • Issues
  • TDSPs 9 Munis and Coops have not registered
  • LSEs 6 of 102 applications pending
    identification of a QSE
  • All CRs participating in pilot have QSEs
    designated
  • Resources 7 of 61 applications pending
    identification of a QSE
  • Action Plan
  • ERCOT contacting all unregistered Munis and Coops
  • LSEs and Resources understand the need to
    identify QSE under negotiations
  • Requested PUCT serves approved Protocols to all
    affected parties

5
Generation Asset Data Forms
550 Units connected to ERCOT Grid
286
264
Action Items ERCOT contacting Resource
Entities ERCOT validating forms received
6
Metering Design Proposal Status
ERCOTs network model contains 443 active units
As of 04-05-2001
124
109
86
124
Action Items ERCOT contacting TDSPs ERCOT
working with TDSPs to approve pending proposals
7
NOIE Meter Point Registration Status
110 Munis and Coops Identified
As of 04-05-2001
NOIE Registration
No NOIE Registration
101
9
Received
8
92
Action Items ERCOT contacting missing
NOIEs ERCOT validating forms received
8
EDI Testing
  • Issues
  • End to End testing was delayed from 3/26 to 4/2
  • ERCOT and MPs are having difficulty completing
    testing frames within the 3 day turnaround.
    Currently frames are taking 5 days
  • NOIE meter data submission test plan completed.
    Testing for meter data submission will begin on
    4/16
  • Action Plan
  • TTPT ITPTA will review timeline and may move to
    7 days a week rather than 5

9
EDI Systems (TDSPs)
  • Issues
  • TDSPs have informed ERCOT that they would not
    build systems to interface via EDI for the 95 of
    non-pilot accounts
  • TDSPs did not build EDI systems to respond as
    old CR for the 5
  • Action Plan
  • ERCOT and TDSPs have agreed upon a workaround
  • ERCOT has prepared a system change request to be
    implemented on July 31st
  • Workaround will perform data repair on true-up
    systems and reconcileUFE created from April (end
    of data conversion) until July

10
Private WAN Connection
  • Issues
  • Frame Relay
  • QSEs 16 of 21 QSEs that need frame relay
    circuits have completed installation and testing
  • ERCOT completed installation at 3 of the
    remaining 5. QSEs need to complete construction
    at their site
  • The remaining 2 may not need WAN for beginning of
    pilot
  • Point to Point
  • 10 of 24 QSEs that need point to point circuits
    have completed installation and testing
  • ERCOT completed installation on 9 of the
    remaining 14 QSEs
  • TDSPs ERCOT completed frame relay circuit
    installations at all TSPs. 5 TSPs need to
    complete their site installations for
    connectivity tests to proceed
  • Action Plan
  • Client site installation issues have been
    escalated to project managers

11
Market Operations Interface (API)
  • Issues
  • Connectivity Tests
  • All 21 QSEs (out of 21 who are qualifying using
    programmatic interface) have completed XML
    connectivity tests
  • Functional Tests
  • All 21 QSEs have completed XML functional tests
  • This was a critical mock market entry criteria
  • Last QSE has passed majority of test
  • Last phase of functional qualification will
    continue into the mock market
  • Action Plan
  • Will monitor performance during the first two
    weeks of mock market to complete qualification

12
Market Operations Interface (Portal)
  • Issues
  • Functional test on the portal was unable to be
    performed due to connectivity issues with test
    environment
  • 8 QSEs will use portal only during mock market
    and beginning of pilot (none will represent
    generation)
  • Action Plan
  • Functional qualification will be performed in
    parallel with first two weeks of mock market
  • ERCOT has made a training environment available
    for participants

13
Real Time Communications (ICCP/RTU)
  • Issues
  • Technical Testing with QSE systems for RTU and
    ICCP has started
  • Resource specific testing will require data
    submission from all generation units for each QSE
  • Data from many generation units in network model
    is missing as QSEs finalize relationships with
    resource owners who need to submit data forms
  • Action Plan
  • ERCOT is working with resource owners to expedite
    submission of data forms

14
Questions?