Title: IEA TASK XIII: Demand Response Resources 1st Meeting Economic Working Group Meeting
1IEA TASK XIIIDemand Response Resources1st
Meeting -- Economic Working Group Meeting
- Host
- Mikael TogebyElkraft System, Denmark
- Daniel Violette, Ph.D. Mr. Pete ScarpelliSummit
Blue Consulting RETX, Inc.Boulder,
Colorado Chicago, Illinois - Ph. 720-564-1130 Ph 312-559-0756
- E-mail dviolette_at_summitblue.com pscarpelli_at_retx.
com - August 17-18, 2004
2AgendaDay 1
- --MORNING--
- 1. Introductions
- 2. Background on overall IEA Annex
- 3. Review goals and objectives for economic
working group - 4. Defining Benefits and Costs
- 5. DR benefit-cost analysis frameworks
- 6. DRR in forward-looking planning analyses
- -- AFTERNOON --
- 7. Critical success factors for DR assessments
- 8. Discussion (Methods, applications, models,
estimates, institutions)
3AgendaDay 2
- 1. Summarize results from day 1
- 2. DRR cost-benefit and planning methods
- Questions that need to be addressed
- Gap analysis, i.e., where does new work need to
be done - 3. Develop research and action agenda
- 4. Outline of Final Report
- 5. Action Agenda
4Demand Response Definition
Demand response is the ability of electricity
demand to respond to variations in electricity
prices in 'markets' or in 'real' time.
Inclusion of DRR in energy markets can take the
form of reduced energy costs, direct payments for
energy not consumed, and/or a reservation
payment for being available to reduce consumption
upon request.
5IEA TASK XIII DRR
- Define and build turnkey DRR infrastructure model
including Business Model, Business Rules,
Enabling Technology, Standards and Implementation
Plan. - Deliver DRR into Any emerging or existing
liberalized electricity market.
6 Project Participants
- Australia
- Canada
- Denmark
- Finland
- Italy
- Japan
- Korea
- Netherlands
- Norway
- Spain
- Sweden
- USA
Pending Mexico, India, New Zealand
7IEA Task XIII Chronology
- February 2003 PLMA invited to present at IEA
Demand Response workshop - March 2003 IEA Secretariat attends Spring PLMA
Meeting in Washington D.C. - April 2003 DOE agrees to have USA sponsor DRR
project if approved by IEA DSM ExCo - April 2003 IEA DSM ExCo approves DRR Project in
Concept - May 2003 DRR Project Working Group formed
8Task XIII Chronology (cont)
- June 2003 IEA/PLMA Press Releases announcing
project and September meetings - July 2003 PLMA asked to participate in DOE
Planning for demand response - September 2003 IEA/PLMA International
Seminar/Experts Workshop - April 2004 DRR Project Approved by ExCo
- May 2004 DRR Project work begins
9Activities Timeline
10Task 2 Market Comparisons
- Goals
- Identify how DR is being used
- Highlight common utilizations and unique efforts
- Report on State of the Practice
- Methodology
- Marketplace Overview
- Independent Research
- Data Request of Experts (released soon)
- Establish State of Practice Work Group
(technology usage customer marketing efforts) - Work Products
- Country Comparison Charts
- Program Benchmarking Charts
- State of Practice Case Studies
11Additional Efforts
- Task XIII Project Portal
- www.demandresponseresources.com
- Project Information
- Work group workplace
- DR Research Library
- Operational Issues Work Group
- Initiated at September Experts Meeting
- Focused on DR market design, data management,
operations, etc. - Project Communication
- Articles
- Conferences
- Canada Power Conference, Toronto, Canada
- Metering Europe, Berlin, Germany
- Critical Infrastructure, Grenoble, France
- NARUC, United States
12Economic Working Group
- The initial draft memo indicated four areas were
targeted for work by the Economics Working Group - 1. Appropriate Benefit/Cost Frameworks for DRR.
- 2. Valuation of DRR in Markets and Incorporating
DRR in Resource Planning. - 3. Conducting DRR Economic Potential Studies
- 4. Ex-post Evaluation of DRR Programs and/or
Policies. - Recognize that we are near the beginning -- your
input now influences the entire project. - OBJECTIVES FOR THIS MEETING
- 1. ARE WE ASKING THE RIGHT QUESTIONS?
- 2. ARE WE FOCUSED ON THE RIGHT END-PRODUCTS?
13Work Area 1 -- B/C Analyses
- Work Area 1 Benefit/Cost Framework -- Develop
the Benefit-Cost Framework that appropriately
supports the economic case for DRR as part of a
resource plan. - Product This work effort will produce
- A listing of benefits that appropriately credit
DRR for the value it provides, and a list of
costs that fully account for the costs of DRR
programs and - For each identified benefit and cost, methods and
guidelines (as practicable) will be identified
that can be used to estimate each that benefit
and cost. - Note The view is that, by doing this
Benefit/Cost effort first, we are providing a
framework for the other work areas.
14 Work Area 2 DRR in Planning
- Work Area 2 Valuation and Planning -- Develop
"approaches" (not specific models) to incorporate
DRR in forward planning short-term (1 to 2
years), medium-term (3 to 6 years), and long-term
plans (10 years). - Goal Develop planning structures and approaches
that identify and explain the tools for
incorporating DRR in longer-term market and
resource planning. - Product Report on approaches and guidelines for
assessing DRR in resource planning. - Identify existing tools and models that are
available in member countries (e.g., capacity
expansion planning models, resource planning
models, and other useful tools/models, e.g.,
distributed generation planning tools). - Develop guidelines for DRR valuation and
planning. - Develop examples and case-studies as practicable.
15Work Area 3 -- DRR Potential
- Work Area 3 DRR Potential -- estimation of DRR
potential in a market. - Focus on structuring approaches and developing
appropriate guidelines for their application. - Should we begin with work on economic potential
of energy efficiency programs and for estimating
the economic potential of distributed generation
will serve as useful starting points. - This effort will be linked with the DRR program
design efforts and "lessons learned" from Task 2. - Product Produce templates for assessing the
potential contribution of DRR in different
markets and for different types of DRR programs.
16Work Area 4 -- Evaluation of DRR
- Work Area 4 Ex-Post Evaluation of DRR Discuss
and develop approaches and requirements for
evaluating and verifying the benefits and costs
of DRR for specific programs that are in place. - Focus on assessing the economic value attributed
to DRR as part of these ex post evaluations - Do we need to take into account the longer-term
impacts from DRR that might represent important
components of the total benefits (i.e., develop
an annual average). - Product Produce guidelines to approaches for
the ex-post evaluation of DRR for different types
of DRR and different market circumstances.
17Overview Issues with DR Valuation
- 1. Appropriately capturing all the values
associated with a DRR. - Many values associated with DRR are difficult to
quantify, - But, they are growing in importance as
supply-side resources become more constrained
(e.g., transmission congestion, and natural gas
prices) - 2. Need to dimension uncertainty around future
outcomes. - Simple planning paradigms such as 1 in 10 year
events are not very useful in assessing option
and hedge values as they only represent one
point. - Different approaches are needed for dimensioning
uncertainty if new tools are to be useful. - 3. Categorization -- There are many types of DRR
programs -- how to classify them such that the
guidelines are appropriate.
18- -- Section 1 --
- Identification of Benefits and Costs
- What should be addressed?
19DRR -- Market Benefits?
- 1. Reliability -- Increased system reliability
through investments at load centers, i.e., the
locational value of the resource. - 2. Market Power -- Demand reductions curb market
power and supply-side reliance - 3. Market Price Reductions -- Reduced regional
prices (part private and/or market?) - 4. Efficient markets -- Better pricing and the
interaction of demand and supply can produce
technology and overall productivity gains (e.g.,
1 per year). - 5. Insurance Value -- Creates the ability to
lower/minimize costs of low probability high
consequence events given current infrastructure
(looking 1 to 2 years out). - 6. Option Value -- Creates more future planning
options, e.g., lower demand growth allows for
more time to assess new infrastructure options
and adapt to new or changed circumstances (makes
gradual changes more economic).
20DRR -- Market Benefits?
- 7. Reduced hedging costs -- Lowered average
prices and price volatility creates a forward
price curve that lowers the costs of hedging. - 8. Risk management benefits -- By allowing
customers to manage part of the price and
commodity risks according to their risk
preferences. - 9. Portfolio benefits -- DRR provides for
increased diversity resources over time (are we
double counting with other benefits?) - 10. Environmental benefits -- By promoting
efficient use of resources. - 11. Customer services -- Through increased
comfort, customer choice and reward for energy
management -- Non-Energy Benefits. - 12. Other -- What is being missed? Where does
the avoided costs of a combustion turbine fit in?
Assumes competitive market in generation so no
need to specify avoid turbine costs?
21DRR -- Private Entity Benefits
- 1. Specialty DRR providers (in the U.S., they are
called "aggregators" or "curtailment service
providers") - Payments received for providing DRR.
- 2. Distribution Companies
- Lowered distribution OM.
- Lowered capital costs for distribution.
- Payments from others for implementing DRR
- 3. Transmission Company Benefits
- Lowered TD OM costs
- Deferred capital costs
22DRR -- Private Entity Benefits
- 4. Commodity providers (i.e., electricity
suppliers to retail customers or retail
aggregators) - Lowered costs of purchasing wholesale electricity
(but what is the impact on margins -- i.e., do
they really benefit?) - 5. Reliability Entities (i.e., ISOs or power
pools) - They are non-profit, so how do they benefit --
are they just facilitators? - 6. End-use Customers
- Lower retail prices for electricity
- Increased reliability
- Payments for providing DRR
- 7. What private benefits are being missed?
23DRR -- Dimensioning the Costs
- Private Costs (for anyone who runs a DRR
program) - Costs of DRR set-up (one-time expenditures)
- Marketing and program design
- Equipment and software
- On-going operating costs
- Payments to participants (capacity and/or energy)
- Overhead management
- Market Costs
- Are there any?
- Miss-allocation of resources?
- Lost profits to generators? (We don't make up
lost profits to firms when a more efficient
option comes along so, why do it here?)
24- -- Section 2 --
- Examples of Benefit Cost Studies
25Side Line -- Dimensioning Uncertainty in DR
Valuation
- Expressing and dimensioning uncertainty for use
in analyses. - Uncertainty is what makes hedges and options
valuable. - If we could use point estimates and were certain
about their values, there is no need for options
or hedges since the optimal solution would simply
be picked. - Industry has used few tools to express
uncertainty - Key problem -- How to dimension uncertainty for
use in planning analyses (simplest to more
complex) - 1. Scenario analyses
- 2. Range estimates -- construct confidence
intervals based on key inputs. - 3. Range estimates with the range filled in with
likelihood estimates to provide a rough-cut
probability distribution.
26Scenarios Versus Distributions
- An assessment about likelihoods of the different
scenarios can provide additional, useful
information. - Individuals familiar with the market can supply
the best available information on
probabilities. - Derived from judgment, expert opinion and
augmented by secondary research. - End-result A distribution is a better
representation of the scenarios being assessed
27DRR Benefit/Costs based on Energy Efficiency (EE)
Frameworks
- A common US DSM framework is from the California
(CA) Standard Practice Manual for Economic
Analysis of DSM or EE Programs. - The CA approach defines five stakeholder
benefit-cost tests - 1. Participant test,
- 2. Utility test
- 3. Rate impact (or non-participant) test,
- 4. Total Resource Cost (TRC) which is most
commonly used and - 5. Societal test (includes externalities).
- BUT, and approach suitable for EE may not be
appropriate for DRR. - However, it is widely used in the US in states
with active DSM programs and that also have DRR
programs. - Possible Justification -- Could this set a lower
bound? If DRR passes the TRC test then, it
would certainly pass a more appropriate market
test designed for DRR?
28CA Standard Practice Manual
- Widely adopted in the US for DSM benefit cost
analysis. - First published in 1983, revised in 1988, and
again in 2001. - Manual covers conservation, load management, fuel
switching, and load building programs. - But all are permanent reductions programs and are
not dispatchable in response to market factors or
events. - QUESTION -- Can we really compare benefits of
dispatchable programs in this static benefit-cost
framework? Initial answer is no. - All stakeholder tests focus on net present
values (NPVs) over the lifetime of DSM measures.
29Participant Test
- Evaluates whether a DSM program/measure is cost
effective to program participants. - Compares the DSM measure cost after utility
rebates to the net present value benefits of the
energy savings over the life of the measure. - This is one of the most important tests in the
US, since regulators would not want to encourage
customers to install DSM measures that are not
cost effective to them. - Test results often have B/C ratios gt 2.
30Utility Test
- Evaluates whether a DSM measure/program is cost
effective to the utility. - This test compares the present value of the
avoided cost benefits over the DSM measures
lifetimes to the total DSM program costs. - This test result is usually very positive, with
B/C ratios gt 3, and often above 10.
31Rate Impact Test
- Measures programs impacts on electric or gas
rates. Used to be called the non-participant
test. - It compares the avoided cost benefits from a DSM
program to the sum of the program costs and lost
revenues. - This is similar to economics Pareto efficiency
test a policy which makes everyone better off. - This test is often slightly negative for
conservation programs, with B/C ratios of
0.8-0.9, - And slightly positive for DR programs, with B/C
ratios of 1-2.
32Total Resource Cost (TRC) Test
- Evaluates whether the benefits from the DSM
resource are greater than the costs of such the
sum of the program costs and the DSM measure
costs. - Also evaluates whether a program is cost
effective to the utilitys ratepayers as a total
group. - This test varies depending on the costs and
benefits of the programs. - Usually positive for conservation programs, with
B/C ratios over 1 even taking into account net
benefits (i.e., net of free-riders) - For DR programs, with B/C ratios depend on the
avoided supply costs and can be less than 1 or
greater than 1 accordingly. - Key is how the avoided costs for meeting peak
demand from other alternatives (usually a
combustion turbine) are calculated (Is there an
opportunity to develop guidelines for calculating
avoided costs?)
33Societal Test
- Very similar to TRC test.
- Main difference is adding avoided environmental
externalities (avoided pollution costs) as a
program benefit. - CA also uses "other" DSM benefits in the societal
test such as non-energy benefits, reliability
benefits, fuel diversity. - This is similar to the Kaldor-Hicks compensation
principal in economics - Winners from a DSM set of programs could
compensate the losers with some of their benefits
so that everyone would be better off. - In the US, the societal test results are often
very similar to the TRC test results but it all
depends upon the externality values that are
added to the TRC test.
34Case Study 1 -- Xcel Energy's use of B/C Tests
(Utility in Minnesota, U.S.)
- Mass-Market Program Xcel Energy cycles
participant customers central air conditioners
and electric water heaters - 15 minutes on/off during peak periods.
- Uses radio signals and pagers for cycling.
- Offers customers a 15 summer rate discount for
participating in program. - Program has been operating for 14 years, and over
20 of residential customers participate.
Program impacts are about 0.7 kW per residential
customer.
35Xcel ProgramBenefit-Cost Results
- Analysis done for 15 year periodlifetime of a
cycling device. - Key benefits and costs are
- Total Program Costs -- 5,453,902
- Number of Participants -- 35,100
- Energy Savings at the Generator -- 510,060 kWh
- Demand Savings at the Generator -- 25,105 kW
- Avoided costs
- Per KW 217.20
- Per kWh 0.713
36Benefit-Cost Results (cont.)
- Participant test B/C ratio is infinite
- customers have no direct costs to participate in
program. - Customer surveys show they experience some minor
discomfort during control periods, but costs for
that are not estimated. - Utility B/C ratio is 5.5avoided generation, TD,
and energy costs much larger than program costs.
Rate discounts not included in this B/C ratio. - Rate impact B/C ratio is 0.86rate discounts
about equal avoided costs, and program costs push
ratio below 1. - TRC and societal B/C ratios are also 5.5, i.e.,
the same as the utility test ratios, since there
are no DSM measure costs that customers have to
pay directly.
37Uncertainties in Xcel Energys DSM Benefit Cost
Analysis
- Retrospective evaluation where actual program
impacts are compared to estimated program
impacts. - Total energy and demand savings per program.
- Load shapes of actual savings.
- Free ridership/free drivership
- Avoided costs and lost revenues 20 year
forecasts are inherently uncertain. - These forecasts do not include low probability
but high cost events. - Environmental externalities and other non-energy
benefits. Methods are not well agreed upon.
38Benefit-Cost based on LOLP
- LOLP stands for loss of load probability and is
the focus of most reliability-based
organizations. - This approach has been used by the NY ISO, and
the ISO NE. - Looks at how DRR has affected the probability of
an outage. - To date, these evaluations have been
retrospective and focused on whether benefits
attained to date exceed the program costs to
date.
39CASE STUDY 2 -- NY ISO Emergency Demand Response
Program (EDRP)
- Assess the benefits of EDRP by looking at how an
increase in reserves would reduce the loss of
load probability (LOLP) - A measure of the benefits of EDRP can be defined
by the change in the Value of Expected Un-served
Energy (VEUE) as follows - ?VEUE (Change in LOLP) (Outage Cost/MW)
(Un-Served Load in MW) - By calling EDRP, the load reduction works to
restore reserve margins - The extent to which reserve margins are
completely restored is a function of the amount
of load reduction of onsite generation provided
by EDRP participants
40NY ISO Emergency Demand Response Program (EDRP)
(cont.)
- If deployment of EDRP resources results in a
positive change in VEUE, then that benefit
qualifies as a contribution to system security - Under the most conservative assumptions -- Outage
costs at 1000/MWh and a reduction in LOLP of
0.05 - THEN, only 3.6 of the load would have had to be
at risk in order for the benefits in terms of
VEUE to exceed program costs as implemented by
the NY ISO. - At the other extreme (5000/MWh and 0.50 LOLP),
only 0.1 of the load would have to be at risk
for the program benefits to equal program costs - This B/C approach sets boundary conditions which
must be true for the program to be cost
effective, even though those conditions are very
uncertain.
41- -- Section 3 --Retrospective Evaluations versus
Forward-looking Planning Studies - Case studies 1 and 2 were retrospective
evaluations designed to determine if a DRR
program's benefits exceeded its costs for the
past year. - Economic planning analyses are needed to
determine future investment in DRR versus
supply-side investments. - How should we do future planning?
42DISCO Utility Assessment of DRR
- Reference -- Report filed with Massachusetts
State Regulators. - Two DISCO utility programs with both focused on
reliability. - 1. A large customer call-option program for 160
MW (in year 1) - 2. A mass market AC load control program that
provides 10 MW increment per year for five years
resulting in a total of 50 MW in year 5. - Reliability was the focus since the DISCO wanted
to see if these programs could be justified based
on DISCO cost reductions. - To defer OM and capital expenses, the utility
believed it would have to make reductions
mandatory. - As a result, pricing options were not considered.
43Conceptual Issue Overview
- Should the DISCO take a more proactive approach
to DR in the future and seek to acquire 170 to
210 MW of DR? - ISSUE There is a belief that DR market benefits
are large, but when DISCO benefits are examined
they are found to be much smaller than the
perceived market benefits. - The Discussion Scenario -- An NSTAR DR investment
producing 210 MW from a CI call program and a
mass-market DLC program - Initial estimate of 80M in market-wide benefits
over 5-year horizon with market-wide B/C ratio of
3.4. - But, from an DISCO perspective, this investment
provides 7.7M in benefits and 23.8M in costs
over 5-year horizon with NSTAR B/C ratio of only
0.3. - DISCO customer perspective -- Customers receive
at least 20 of the market benefits or 16.4M
plus incentive payments of 16M from program
participation NPV discounted over five years for
a customer B/C of 1.4.
44 Setting the Stage Views on Market Benefits of
DR
- Overall, there is a basic belief among many
organizations that market benefits from DR are
sizeable - ISO-NE Regional Transmission Expansion Plan
states that DR can have significant benefits in
terms of reliability and savings in congestion
costs. - New England Demand Response Initiatives Final
Draft Report states that a small amount of DR can
enhance system reliability and substantially
reduce market-clearing prices, producing
significant benefits to consumers. - ISO-NE 2002 DR Program Evaluation states that
magnitudes of DR sufficient to clear the market
at lower bid prices (ECP), will reduce the price
of energy for all purchasers in the spot market. - The NYISO states that it has had a successful DR
program in operation through two summers which
has delivered benefits to the grid in terms of
reduced market price and improved system
reliability.
45Setting the Stage (cont.)
- FERC SMD and White Paper
- Demand response is essential in competitive
markets to assure the efficient interaction of
supply and demand. - Demand response options should be available so
that end users can respond to price signals. - California PUC -- Demand Response is a vital
resource to enhance electric system reliability,
reduce power purchase cost and individual
consumer costs R. 02-06-001, Order Instituting
Rule making, June 6, 2002. - California Energy Commission 2002 2012
Electricity Outlook Report estimates that an
increased level of DR could have saved California
2.5 billion in year 2000. - FINALLY -- California Energy Commission Order
Instituting Rulemaking (June 17, 2003) states
that the CEC will consider the acquisition of
2,500 MW of DR (approx. 5 of peak demand) to
moderate price increases and improve system
reliability.
46Setting the Stage (cont.)
August 14 2002 Hour 15 Supply Curve (ISO-NE)
Peak load reduced by 5
- A 5 reduction in peak load can generate a 50
reduction in ECP. - DR can reduce the price of energy for all
purchasers in the spot market. - DR can play a significant role in price spike
mitigation in lieu of price caps. - Source ISO-NE 2002 DR Program Evaluation.
47DISCO Benefits
- Defer or eliminate TD capital expenditures
- Provide (n-1) reserve
- Standby generation
- Curtailable load
- Emergency Response Resource
- Hedge against questionable forecasts
- Extreme weather events
- Unforeseen load growth
- Rapid development
- Assist during contingency/emergency events
- Revenues from ISO-NE DRR capacity and energy
payments to any DRR provider.
48NSTAR DR Program Costs
- Proposed Program Cost Categories
- Staff time (development, marketing,
implementation) - Software systems
- Physical infrastructure
- Incentive payments
- Financial assistance to participants
- Revenue differentials due to rate impacts
49DISCO Benefits Costs
- An interactive process involving NSTAR staff and
enabling technology manufacturers and vendors was
used to calculate the benefits and costs - Distribution System Planning
- Regulatory Policy and Rates
- ISO-NE Liaison
- The calculations were based upon estimates of
achievable DR by key rate classes - Geographic and demographic analyses of customer
characteristics in relation to key distribution
system nodes - Rate analyses were also performed to estimate DR
impacts on billing determinants
50DRs Impact on DISCO Revenues
- Monthly peak demand determines billing kW.
- Analyses assume a 10 reduction in billing
determinants. - For programs examined, revenue differentials
minimal (under .1) as only participants are
impacted and other high consumption hours make up
for the reduced demand charge for these
participants in hours with load control.
51NSTAR BCR
NSTAR BCR 0.32
Deferred TD Expenditures Revenue from ISO-NE
NSTAR Benefits 7.7M
Market Benefits 80.1M
Benefits
Costs
- NSTAR Expanded DR
- Program costs
- Lost revenues
NSTAR Investment 23.8M
- - Calculations assume 160 MW enrolled in CI call
option program and 10 MW enrolled in mass-mkt
program in 2004 increasing by 10 MW per year
until 50 MW are enrolled in 2008. - Values are NPV over 5 years at 7.72 discount
rate.
52Market-Wide Benefits
- A pivot factor in assessing NSTAR options
- Simple analyses used to justify assumed large
benefits in terms of - 1. Hedges against price spikes in spot markets,
- 2. Reduced price volatility influencing all MW
transactions through lowered forward price curve,
and - 3. Increased reliability (TD system and
generation adequacy) - 4. Portfolio value due to resource diversity --
DR supply costs not correlated with fuel prices,
plant outages, and transmission congestion. - 5. Reduced market power -- Mkt power exists on
peak days when transmission constraints do not
all for the import of power into zones. - Methods for estimating benefits have not been
standardized and are still being developed. - Existing studies are retrospective and show low
price effects from DR -- BUT what might occur in
the next five years?
53Market Extended Market Benefits
- Market Benefits
- Transfer/Collateral Benefits
- Reduction in long-term hedging costs
- System reliability improvement
- Extended Market Benefits
- Transmission Real Options Value
- Increased incentive for innovation
- Increased resource portfolio diversity
- Reduction in market power
- Operating reserves demand curve
54Market Benefits Definitions
- Collateral Savings Reduction in market-clearing
prices in spot markets impacted by DR. Also
referred to as Benefits to Non-participant
Buyers. - Hedging Benefits Savings due to reduced average
prices and price variability in the market.
Results lowered forward price curve for all MW
transactions. - Reliability Benefits Enhanced grid reliability
and reduced probability of customer outages
(reduced ISO-NE calculated LOLP). - Transmission Real Options Value Hedge against
low probability, high consequence events Only
counted in Extended Market Benefits Analysis.
55Rationale for including Market Benefits
- DR has positive impacts beyond those captured by
traditional benefit/cost tests. - DR has potential to ameliorate generation,
transmission, and distribution issues in specific
situations. - FERC estimated that a 5 reduction in peak demand
could have reduced recent California price spikes
by 50. - NSTAR has received societal benefits funds to
assess a small-scale demand response program for
commercial customers.
56Market BCR for DISCO Program
Market BCR 3.36 Extended Market BCR 5.34Based
on an Options Value of 25 million (best guess)
-
-
- Generation Reliability
- - Reserves
- - Outage costs
- Reduced Energy Costs
- - MWh prices
- - Hedging costs
-
Market Benefits 80.1M
Benefits
Costs
- NSTAR Expanded DR
- Program costs
- Resource costs
NSTAR Investment 23.8M
- Best practices used to estimate market benefits.
- Much debate about the magnitude of the benefits.
- Calculations assume 160 MW enrolled in CI call
option program and 10 MW enrolled in mass-mkt
program in 2004 increasing by 10 MW per year
until 50 MW are enrolled in 2008. - Values are NPV over 5 years at 7.72 discount
rate.
57Go/No Go Factors for DRR
- Conditions favoring DR initiatives
- Escalating or volatile energy prices
- Plant outages and reduced generation availability
- Uncertainty in capital markets
- Unexpected growth in electric demand
- Wide availability of advanced metering technology
- Increased risk management costs
- Conditions hindering DR initiatives
- Bifurcation of incentives
- Supply/generation technology breakthroughs
- Low cost of capital for plant additions
- Stable or low growth in electric demand
- Status quo regulatory posture (e.g. no
innovative rates, etc.)
58Regulatory and Market Unknowns
- Regulatory environment
- Will regulators encourage distribution companies
to promote DR that serves dual purposes (DISCO
benefits and MARKET benefits) via rates or
incentives? - Depends upon perceived market-wide benefits.
- Market environment
- Will suppliers (load serving entities -- LSEs)
pay the DISCO for commodity price risk protection
via DR? - Will there be competitive curtailment service
providers (CSPs) that serve the market function? - Will outsourced DRR become an industry convention
(e.g., the purchase of a Texas Utility's DRR
program by a technology company, i.e., Comverge,
Inc.)?
59KEMA-XENERGY ExampleMethod 1 Black Scholes
- Value of options to buy or sell at fixed prices
- Call option to buy at X if market goes higher
- Put option to sell at X if market goes lower
- Other Inputs
- r risk-free rate of return
- s volatility
- DR as call option that reduces risk
- Avoided expected price base value
- Call option says I can buy at a fixed price
- Value of the call option is the value of avoided
exposure to prices above base
60KEMA-XENERGY Method 1 Black Scholes - Problems
- If market drops, could have paid too much for DR
- To protect against overpayment risk, could buy a
put option - Strike price cost of DR (/ MWh)
- Cost of overpayment risk value of the put
option, whether or not we actually buy it. - NOTE Black Scholes not typically assumed to
apply to electricity markets, but it is easily
applied as and example.
61KEMA-XENERGY Method 2 Portfolio Optimization
- Monte Carlo simulation compares cost and risk of
alternative portfolios (used instead of
closed-form Black-Scholes) - Can construct a supply portfolio to satisfy
reliability requirement - Balancing cost and risk
- Define cost-risk trade-off explicitly or
implicitly - In simple illustration,
- Price volatility is only source of risk
- Model interaction between native generation and
market
62KEMA-XENERGY Method 2 Portfolio Comparison
Generation Capacity
Demand and Market Prices
Market Price Volatility 28
63KEMA-XENERGY Method 2 Portfolio Comparison
NOTE This is only one piece of the puzzle, but
it is indicative of new thinking in approaching
these problems. From AESP/EPRI
Pricing Conference, May 18-19, 2004
64Alternative Portfolio Approach
- 1. Information needs for DRR planning
- Resource characterization and value analyses.
- Need to dimension uncertainty around key factors.
- 2. What is needed from the planning tools
- Ability to work with distributions as inputs.
- Address the value of information as uncertainty
is reduced over time. - Time steps are required in the analyses.
- 3. A simplified example
- 4. Conclusions
65Application of Portfolio Analyses
- Today's planning environment requires analyses
that - Uncertainty be incorporated in the analyses.
- Risk mitigation options must be identified and
valued. - Appropriately credit Demand Response (DR) and
Energy Efficiency (EE) for risk management and
other values. - Hedging values as expressed in reduced mean peak
period prices and price volatility -- both
influence forward price curves. - Direct price impacts in spot market transactions
(gas and electric). - Other values (market power, innovation, customer
values). - Address the value of information and learning
over time. - Assess the value of flexibility, i.e., creation
of real options to address future contingencies
(some may not yet be known). - Continue to appropriately analyze supply-side
economics.
66Application of New Tools
- Need to dimension uncertainty.
- Assess Value at Risk from different options.
- Fully address the portfolio of demand-side and
supply-side options. - Need to work with distributions of outcomes
- Closed form solutions and analytics.
- Monte Carlo methods.
- Decision-tree variants.
- Must incorporate time steps to address
flexibility. - New models such as _at_RISK and Crystal Ball allow
for analyses based on representations of market
uncertainties. - Supply-side models also incorporate Monte Carlo
solutions, e.g., General Electric's MAPS model
and Global Energy Decision's MIDAS model.
Adaptations of these models may be useful.
67Information Needs for Portfolio Analyses
- 1. Appropriately capturing all the value
associated with a resource option. - Many values associated with demand-side options
are difficult to quantify, but are growing in
importance as supply-side resources become more
constrained (e.g., transmission congestion, and
natural gas availability and prices) - 2. Need to dimension uncertainty around future
outcomes. - Simple planning paradigms such as 1 in 10 year
events are not very useful in assessing option
and hedge values as they only represent one
point. - Different approaches are needed for dimensioning
uncertainty if new tools are to be useful.
682. Dimensioning Uncertainty
- Expressing and dimensioning uncertainty for use
in analyses. - Uncertainty is what makes hedges and options
valuable. - If we could use point estimates and were certain
about their values, there is no need for options
or hedges since the optimal solution would simply
be picked. - Industry has used few tools to express
uncertainty - Key problem -- How to dimension uncertainty for
use in planning analyses (simplest to more
complex) - 1. Scenario analyses
- 2. Range estimates -- construct confidence
intervals based on key inputs. - 3. Range estimates with the range filled in with
likelihood estimates to provide a rough cut
probability distribution.
69Scenarios Versus Distributions
70Application of New Tools
- Need to dimension uncertainty.
- Assess Value at Risk from different options.
- Fully address the portfolio of demand-side and
supply-side options. - Need to work with distributions of outcomes
- Closed form solutions and analytics.
- Monte Carlo methods
- Decisions tree variants
- Must incorporate time steps to address
flexibility. - New models such as _at_RISK and Crystal Ball allow
for analyses based on representations of market
uncertainties.
71Simplified Example -- Decision Tree
Time Period T 1
Objective MinimizeRevenue Requirementsover 10
years. Time Step One-year steps overa 10-year
period. Proxy Example Real applicationwould
includedistributions insteadof single
probabilitynodes.
SupplyPortfolio2
SupplyPortfolio3
Other Time Steps
SupplyPortfolio1
GasPrices
SeasonalEnergyDemandMetrics
PeakDemandMetrics
High .6
Low .4
High .7
High .5
Low .3
High .5
Low .5
High .5
Low .5
Low .5
High .5
High .4
Low .5
Low .6
NPVVAR
NPVVAR
NPVVAR
72Example DistributionStochastic Price Forecasts
73Example DistributionForecasted Bill Changes
74Conclusions (Agree/Disagree?)
- The tools exist to assess portfolio of
supply-side and demand-side options. - This requires
- 1. Appropriate resource characterization.
- 2. Representations of the uncertainty around key
factors in the analysis. - The challenge is to change perspectives and to
get planners to move out of their comfort zone to
develop better (i.e., more accurate)
representations of uncertainty. - Representing uncertainty and the value of
information over time is the key challenge as
both contribute to the value of options and
hedges. - This is new to planners, but it is necessary --
the good news is we have the tools and processes
that will allow these analyses.
75Conclusions -- Unique DRR Valuation Problems
- Values accrue to different entities
- Distribution companies in terms of deferred
maintenance and new facilities, plus contingency
avoidance. - Transmission owners through reduced capacity and
maintenance. - Reliability managers through lowered costs of
better Loss of Load Probabilities (LOLPs). - Customers who now are able to receive payment for
their ability to use electricity flexibility. - A key attribute of consumption is now given a
value. - SO -- Values accrue to many and to the market at
large, but costs are concentrated at the program
level. - Value is segmented with no one group is willing
to provide full value for DR, but generators can
be consolidated opponents.
76Day 2 Topics
- Suggestions for additional topics
- 1. Final report outline just to see if one view
of the project deliverable fits with the needs of
most IEA participants. - 2. What tools might we want to include in our
review and try to build on - Supply-side production cost models (probabilistic
and non-probabilistic) - Load shaping tools
- Monte Carlo and decision analysis tools (_at_RISK
and Crystal Ball) - Others?
- 3. Can we use information used to assess
distributed generation to help address
curtailable load options? - 4. Other topics
77- Meeting Moderators
- Dan Violette Pete ScarpelliSummit Blue
Consulting RETX, Inc.1722 14th Street,
230Boulder, Colorado 80302 Chicago,
IllinoisPh 720-564-1130 Ph312-953-4642E-Mai
l dviolette_at_summitblue.com E-Mail
pscarpelli_at_retx.com - Meeting Host
- Mikael TogebyElkraft SystemLautruphøj 72750
BallerupPh 44 87 36 16www.elkraft-system.dk