IEA TASK XIII: Demand Response Resources 1st Meeting Economic Working Group Meeting - PowerPoint PPT Presentation

1 / 77
About This Presentation
Title:

IEA TASK XIII: Demand Response Resources 1st Meeting Economic Working Group Meeting

Description:

Looks at how DRR has affected the probability of an outage. ... Under the most conservative assumptions -- Outage costs at $1000/MWh; and a ... – PowerPoint PPT presentation

Number of Views:272
Avg rating:3.0/5.0
Slides: 78
Provided by: randy203
Category:

less

Transcript and Presenter's Notes

Title: IEA TASK XIII: Demand Response Resources 1st Meeting Economic Working Group Meeting


1
IEA TASK XIIIDemand Response Resources1st
Meeting -- Economic Working Group Meeting
  • Host
  • Mikael TogebyElkraft System, Denmark
  • Daniel Violette, Ph.D. Mr. Pete ScarpelliSummit
    Blue Consulting RETX, Inc.Boulder,
    Colorado Chicago, Illinois
  • Ph. 720-564-1130 Ph 312-559-0756
  • E-mail dviolette_at_summitblue.com pscarpelli_at_retx.
    com
  • August 17-18, 2004

2
AgendaDay 1
  • --MORNING--
  • 1. Introductions
  • 2. Background on overall IEA Annex
  • 3. Review goals and objectives for economic
    working group
  • 4. Defining Benefits and Costs
  • 5. DR benefit-cost analysis frameworks
  • 6. DRR in forward-looking planning analyses
  • -- AFTERNOON --
  • 7. Critical success factors for DR assessments
  • 8. Discussion (Methods, applications, models,
    estimates, institutions)

3
AgendaDay 2
  • 1. Summarize results from day 1
  • 2. DRR cost-benefit and planning methods
  • Questions that need to be addressed
  • Gap analysis, i.e., where does new work need to
    be done
  • 3. Develop research and action agenda
  • 4. Outline of Final Report
  • 5. Action Agenda

4
Demand Response Definition
Demand response is the ability of electricity
demand to respond to variations in electricity
prices in 'markets' or in 'real' time.
Inclusion of DRR in energy markets can take the
form of reduced energy costs, direct payments for
energy not consumed, and/or a reservation
payment for being available to reduce consumption
upon request.
5
IEA TASK XIII DRR
  • Define and build turnkey DRR infrastructure model
    including Business Model, Business Rules,
    Enabling Technology, Standards and Implementation
    Plan.
  • Deliver DRR into Any emerging or existing
    liberalized electricity market.

6
Project Participants
  • Australia
  • Canada
  • Denmark
  • Finland
  • Italy
  • Japan
  • Korea
  • Netherlands
  • Norway
  • Spain
  • Sweden
  • USA

Pending Mexico, India, New Zealand
7
IEA Task XIII Chronology
  • February 2003 PLMA invited to present at IEA
    Demand Response workshop
  • March 2003 IEA Secretariat attends Spring PLMA
    Meeting in Washington D.C.
  • April 2003 DOE agrees to have USA sponsor DRR
    project if approved by IEA DSM ExCo
  • April 2003 IEA DSM ExCo approves DRR Project in
    Concept
  • May 2003 DRR Project Working Group formed

8
Task XIII Chronology (cont)
  • June 2003 IEA/PLMA Press Releases announcing
    project and September meetings
  • July 2003 PLMA asked to participate in DOE
    Planning for demand response
  • September 2003 IEA/PLMA International
    Seminar/Experts Workshop
  • April 2004 DRR Project Approved by ExCo
  • May 2004 DRR Project work begins

9
Activities Timeline
10
Task 2 Market Comparisons
  • Goals
  • Identify how DR is being used
  • Highlight common utilizations and unique efforts
  • Report on State of the Practice
  • Methodology
  • Marketplace Overview
  • Independent Research
  • Data Request of Experts (released soon)
  • Establish State of Practice Work Group
    (technology usage customer marketing efforts)
  • Work Products
  • Country Comparison Charts
  • Program Benchmarking Charts
  • State of Practice Case Studies

11
Additional Efforts
  • Task XIII Project Portal
  • www.demandresponseresources.com
  • Project Information
  • Work group workplace
  • DR Research Library
  • Operational Issues Work Group
  • Initiated at September Experts Meeting
  • Focused on DR market design, data management,
    operations, etc.
  • Project Communication
  • Articles
  • Conferences
  • Canada Power Conference, Toronto, Canada
  • Metering Europe, Berlin, Germany
  • Critical Infrastructure, Grenoble, France
  • NARUC, United States

12
Economic Working Group
  • The initial draft memo indicated four areas were
    targeted for work by the Economics Working Group
  • 1. Appropriate Benefit/Cost Frameworks for DRR.
  • 2. Valuation of DRR in Markets and Incorporating
    DRR in Resource Planning.
  • 3. Conducting DRR Economic Potential Studies
  • 4. Ex-post Evaluation of DRR Programs and/or
    Policies.
  • Recognize that we are near the beginning -- your
    input now influences the entire project.
  • OBJECTIVES FOR THIS MEETING
  • 1. ARE WE ASKING THE RIGHT QUESTIONS?
  • 2. ARE WE FOCUSED ON THE RIGHT END-PRODUCTS?

13
Work Area 1 -- B/C Analyses
  • Work Area 1 Benefit/Cost Framework -- Develop
    the Benefit-Cost Framework that appropriately
    supports the economic case for DRR as part of a
    resource plan.
  • Product This work effort will produce
  • A listing of benefits that appropriately credit
    DRR for the value it provides, and a list of
    costs that fully account for the costs of DRR
    programs and
  • For each identified benefit and cost, methods and
    guidelines (as practicable) will be identified
    that can be used to estimate each that benefit
    and cost.
  • Note The view is that, by doing this
    Benefit/Cost effort first, we are providing a
    framework for the other work areas.

14
Work Area 2 DRR in Planning
  • Work Area 2 Valuation and Planning -- Develop
    "approaches" (not specific models) to incorporate
    DRR in forward planning short-term (1 to 2
    years), medium-term (3 to 6 years), and long-term
    plans (10 years).
  • Goal Develop planning structures and approaches
    that identify and explain the tools for
    incorporating DRR in longer-term market and
    resource planning.
  • Product Report on approaches and guidelines for
    assessing DRR in resource planning.
  • Identify existing tools and models that are
    available in member countries (e.g., capacity
    expansion planning models, resource planning
    models, and other useful tools/models, e.g.,
    distributed generation planning tools).
  • Develop guidelines for DRR valuation and
    planning.
  • Develop examples and case-studies as practicable.

15
Work Area 3 -- DRR Potential
  • Work Area 3 DRR Potential -- estimation of DRR
    potential in a market.
  • Focus on structuring approaches and developing
    appropriate guidelines for their application.
  • Should we begin with work on economic potential
    of energy efficiency programs and for estimating
    the economic potential of distributed generation
    will serve as useful starting points.
  • This effort will be linked with the DRR program
    design efforts and "lessons learned" from Task 2.
  • Product Produce templates for assessing the
    potential contribution of DRR in different
    markets and for different types of DRR programs.

16
Work Area 4 -- Evaluation of DRR
  • Work Area 4 Ex-Post Evaluation of DRR Discuss
    and develop approaches and requirements for
    evaluating and verifying the benefits and costs
    of DRR for specific programs that are in place.
  • Focus on assessing the economic value attributed
    to DRR as part of these ex post evaluations
  • Do we need to take into account the longer-term
    impacts from DRR that might represent important
    components of the total benefits (i.e., develop
    an annual average).
  • Product Produce guidelines to approaches for
    the ex-post evaluation of DRR for different types
    of DRR and different market circumstances.

17
Overview Issues with DR Valuation
  • 1. Appropriately capturing all the values
    associated with a DRR.
  • Many values associated with DRR are difficult to
    quantify,
  • But, they are growing in importance as
    supply-side resources become more constrained
    (e.g., transmission congestion, and natural gas
    prices)
  • 2. Need to dimension uncertainty around future
    outcomes.
  • Simple planning paradigms such as 1 in 10 year
    events are not very useful in assessing option
    and hedge values as they only represent one
    point.
  • Different approaches are needed for dimensioning
    uncertainty if new tools are to be useful.
  • 3. Categorization -- There are many types of DRR
    programs -- how to classify them such that the
    guidelines are appropriate.

18
  • -- Section 1 --
  • Identification of Benefits and Costs
  • What should be addressed?

19
DRR -- Market Benefits?
  • 1. Reliability -- Increased system reliability
    through investments at load centers, i.e., the
    locational value of the resource.
  • 2. Market Power -- Demand reductions curb market
    power and supply-side reliance
  • 3. Market Price Reductions -- Reduced regional
    prices (part private and/or market?)
  • 4. Efficient markets -- Better pricing and the
    interaction of demand and supply can produce
    technology and overall productivity gains (e.g.,
    1 per year).
  • 5. Insurance Value -- Creates the ability to
    lower/minimize costs of low probability high
    consequence events given current infrastructure
    (looking 1 to 2 years out).
  • 6. Option Value -- Creates more future planning
    options, e.g., lower demand growth allows for
    more time to assess new infrastructure options
    and adapt to new or changed circumstances (makes
    gradual changes more economic).

20
DRR -- Market Benefits?
  • 7. Reduced hedging costs -- Lowered average
    prices and price volatility creates a forward
    price curve that lowers the costs of hedging.
  • 8. Risk management benefits -- By allowing
    customers to manage part of the price and
    commodity risks according to their risk
    preferences.
  • 9. Portfolio benefits -- DRR provides for
    increased diversity resources over time (are we
    double counting with other benefits?)
  • 10. Environmental benefits -- By promoting
    efficient use of resources.
  • 11. Customer services -- Through increased
    comfort, customer choice and reward for energy
    management -- Non-Energy Benefits.
  • 12. Other -- What is being missed? Where does
    the avoided costs of a combustion turbine fit in?
    Assumes competitive market in generation so no
    need to specify avoid turbine costs?

21
DRR -- Private Entity Benefits
  • 1. Specialty DRR providers (in the U.S., they are
    called "aggregators" or "curtailment service
    providers")
  • Payments received for providing DRR.
  • 2. Distribution Companies
  • Lowered distribution OM.
  • Lowered capital costs for distribution.
  • Payments from others for implementing DRR
  • 3. Transmission Company Benefits
  • Lowered TD OM costs
  • Deferred capital costs

22
DRR -- Private Entity Benefits
  • 4. Commodity providers (i.e., electricity
    suppliers to retail customers or retail
    aggregators)
  • Lowered costs of purchasing wholesale electricity
    (but what is the impact on margins -- i.e., do
    they really benefit?)
  • 5. Reliability Entities (i.e., ISOs or power
    pools)
  • They are non-profit, so how do they benefit --
    are they just facilitators?
  • 6. End-use Customers
  • Lower retail prices for electricity
  • Increased reliability
  • Payments for providing DRR
  • 7. What private benefits are being missed?

23
DRR -- Dimensioning the Costs
  • Private Costs (for anyone who runs a DRR
    program)
  • Costs of DRR set-up (one-time expenditures)
  • Marketing and program design
  • Equipment and software
  • On-going operating costs
  • Payments to participants (capacity and/or energy)
  • Overhead management
  • Market Costs
  • Are there any?
  • Miss-allocation of resources?
  • Lost profits to generators? (We don't make up
    lost profits to firms when a more efficient
    option comes along so, why do it here?)

24
  • -- Section 2 --
  • Examples of Benefit Cost Studies

25
Side Line -- Dimensioning Uncertainty in DR
Valuation
  • Expressing and dimensioning uncertainty for use
    in analyses.
  • Uncertainty is what makes hedges and options
    valuable.
  • If we could use point estimates and were certain
    about their values, there is no need for options
    or hedges since the optimal solution would simply
    be picked.
  • Industry has used few tools to express
    uncertainty
  • Key problem -- How to dimension uncertainty for
    use in planning analyses (simplest to more
    complex)
  • 1. Scenario analyses
  • 2. Range estimates -- construct confidence
    intervals based on key inputs.
  • 3. Range estimates with the range filled in with
    likelihood estimates to provide a rough-cut
    probability distribution.

26
Scenarios Versus Distributions
  • An assessment about likelihoods of the different
    scenarios can provide additional, useful
    information.
  • Individuals familiar with the market can supply
    the best available information on
    probabilities.
  • Derived from judgment, expert opinion and
    augmented by secondary research.
  • End-result A distribution is a better
    representation of the scenarios being assessed

27
DRR Benefit/Costs based on Energy Efficiency (EE)
Frameworks
  • A common US DSM framework is from the California
    (CA) Standard Practice Manual for Economic
    Analysis of DSM or EE Programs.
  • The CA approach defines five stakeholder
    benefit-cost tests
  • 1. Participant test,
  • 2. Utility test
  • 3. Rate impact (or non-participant) test,
  • 4. Total Resource Cost (TRC) which is most
    commonly used and
  • 5. Societal test (includes externalities).
  • BUT, and approach suitable for EE may not be
    appropriate for DRR.
  • However, it is widely used in the US in states
    with active DSM programs and that also have DRR
    programs.
  • Possible Justification -- Could this set a lower
    bound? If DRR passes the TRC test then, it
    would certainly pass a more appropriate market
    test designed for DRR?

28
CA Standard Practice Manual
  • Widely adopted in the US for DSM benefit cost
    analysis.
  • First published in 1983, revised in 1988, and
    again in 2001.
  • Manual covers conservation, load management, fuel
    switching, and load building programs.
  • But all are permanent reductions programs and are
    not dispatchable in response to market factors or
    events.
  • QUESTION -- Can we really compare benefits of
    dispatchable programs in this static benefit-cost
    framework? Initial answer is no.
  • All stakeholder tests focus on net present
    values (NPVs) over the lifetime of DSM measures.

29
Participant Test
  • Evaluates whether a DSM program/measure is cost
    effective to program participants.
  • Compares the DSM measure cost after utility
    rebates to the net present value benefits of the
    energy savings over the life of the measure.
  • This is one of the most important tests in the
    US, since regulators would not want to encourage
    customers to install DSM measures that are not
    cost effective to them.
  • Test results often have B/C ratios gt 2.

30
Utility Test
  • Evaluates whether a DSM measure/program is cost
    effective to the utility.
  • This test compares the present value of the
    avoided cost benefits over the DSM measures
    lifetimes to the total DSM program costs.
  • This test result is usually very positive, with
    B/C ratios gt 3, and often above 10.

31
Rate Impact Test
  • Measures programs impacts on electric or gas
    rates. Used to be called the non-participant
    test.
  • It compares the avoided cost benefits from a DSM
    program to the sum of the program costs and lost
    revenues.
  • This is similar to economics Pareto efficiency
    test a policy which makes everyone better off.
  • This test is often slightly negative for
    conservation programs, with B/C ratios of
    0.8-0.9,
  • And slightly positive for DR programs, with B/C
    ratios of 1-2.

32
Total Resource Cost (TRC) Test
  • Evaluates whether the benefits from the DSM
    resource are greater than the costs of such the
    sum of the program costs and the DSM measure
    costs.
  • Also evaluates whether a program is cost
    effective to the utilitys ratepayers as a total
    group.
  • This test varies depending on the costs and
    benefits of the programs.
  • Usually positive for conservation programs, with
    B/C ratios over 1 even taking into account net
    benefits (i.e., net of free-riders)
  • For DR programs, with B/C ratios depend on the
    avoided supply costs and can be less than 1 or
    greater than 1 accordingly.
  • Key is how the avoided costs for meeting peak
    demand from other alternatives (usually a
    combustion turbine) are calculated (Is there an
    opportunity to develop guidelines for calculating
    avoided costs?)

33
Societal Test
  • Very similar to TRC test.
  • Main difference is adding avoided environmental
    externalities (avoided pollution costs) as a
    program benefit.
  • CA also uses "other" DSM benefits in the societal
    test such as non-energy benefits, reliability
    benefits, fuel diversity.
  • This is similar to the Kaldor-Hicks compensation
    principal in economics
  • Winners from a DSM set of programs could
    compensate the losers with some of their benefits
    so that everyone would be better off.
  • In the US, the societal test results are often
    very similar to the TRC test results but it all
    depends upon the externality values that are
    added to the TRC test.

34
Case Study 1 -- Xcel Energy's use of B/C Tests
(Utility in Minnesota, U.S.)
  • Mass-Market Program Xcel Energy cycles
    participant customers central air conditioners
    and electric water heaters
  • 15 minutes on/off during peak periods.
  • Uses radio signals and pagers for cycling.
  • Offers customers a 15 summer rate discount for
    participating in program.
  • Program has been operating for 14 years, and over
    20 of residential customers participate.
    Program impacts are about 0.7 kW per residential
    customer.

35
Xcel ProgramBenefit-Cost Results
  • Analysis done for 15 year periodlifetime of a
    cycling device.
  • Key benefits and costs are
  • Total Program Costs -- 5,453,902
  • Number of Participants -- 35,100
  • Energy Savings at the Generator -- 510,060 kWh
  • Demand Savings at the Generator -- 25,105 kW
  • Avoided costs
  • Per KW 217.20
  • Per kWh 0.713

36
Benefit-Cost Results (cont.)
  • Participant test B/C ratio is infinite
  • customers have no direct costs to participate in
    program.
  • Customer surveys show they experience some minor
    discomfort during control periods, but costs for
    that are not estimated.
  • Utility B/C ratio is 5.5avoided generation, TD,
    and energy costs much larger than program costs.
    Rate discounts not included in this B/C ratio.
  • Rate impact B/C ratio is 0.86rate discounts
    about equal avoided costs, and program costs push
    ratio below 1.
  • TRC and societal B/C ratios are also 5.5, i.e.,
    the same as the utility test ratios, since there
    are no DSM measure costs that customers have to
    pay directly.

37
Uncertainties in Xcel Energys DSM Benefit Cost
Analysis
  • Retrospective evaluation where actual program
    impacts are compared to estimated program
    impacts.
  • Total energy and demand savings per program.
  • Load shapes of actual savings.
  • Free ridership/free drivership
  • Avoided costs and lost revenues 20 year
    forecasts are inherently uncertain.
  • These forecasts do not include low probability
    but high cost events.
  • Environmental externalities and other non-energy
    benefits. Methods are not well agreed upon.

38
Benefit-Cost based on LOLP
  • LOLP stands for loss of load probability and is
    the focus of most reliability-based
    organizations.
  • This approach has been used by the NY ISO, and
    the ISO NE.
  • Looks at how DRR has affected the probability of
    an outage.
  • To date, these evaluations have been
    retrospective and focused on whether benefits
    attained to date exceed the program costs to
    date.

39
CASE STUDY 2 -- NY ISO Emergency Demand Response
Program (EDRP)
  • Assess the benefits of EDRP by looking at how an
    increase in reserves would reduce the loss of
    load probability (LOLP)
  • A measure of the benefits of EDRP can be defined
    by the change in the Value of Expected Un-served
    Energy (VEUE) as follows
  • ?VEUE (Change in LOLP) (Outage Cost/MW)
    (Un-Served Load in MW)
  • By calling EDRP, the load reduction works to
    restore reserve margins
  • The extent to which reserve margins are
    completely restored is a function of the amount
    of load reduction of onsite generation provided
    by EDRP participants

40
NY ISO Emergency Demand Response Program (EDRP)
(cont.)
  • If deployment of EDRP resources results in a
    positive change in VEUE, then that benefit
    qualifies as a contribution to system security
  • Under the most conservative assumptions -- Outage
    costs at 1000/MWh and a reduction in LOLP of
    0.05
  • THEN, only 3.6 of the load would have had to be
    at risk in order for the benefits in terms of
    VEUE to exceed program costs as implemented by
    the NY ISO.
  • At the other extreme (5000/MWh and 0.50 LOLP),
    only 0.1 of the load would have to be at risk
    for the program benefits to equal program costs
  • This B/C approach sets boundary conditions which
    must be true for the program to be cost
    effective, even though those conditions are very
    uncertain.

41
  • -- Section 3 --Retrospective Evaluations versus
    Forward-looking Planning Studies
  • Case studies 1 and 2 were retrospective
    evaluations designed to determine if a DRR
    program's benefits exceeded its costs for the
    past year.
  • Economic planning analyses are needed to
    determine future investment in DRR versus
    supply-side investments.
  • How should we do future planning?

42
DISCO Utility Assessment of DRR
  • Reference -- Report filed with Massachusetts
    State Regulators.
  • Two DISCO utility programs with both focused on
    reliability.
  • 1. A large customer call-option program for 160
    MW (in year 1)
  • 2. A mass market AC load control program that
    provides 10 MW increment per year for five years
    resulting in a total of 50 MW in year 5.
  • Reliability was the focus since the DISCO wanted
    to see if these programs could be justified based
    on DISCO cost reductions.
  • To defer OM and capital expenses, the utility
    believed it would have to make reductions
    mandatory.
  • As a result, pricing options were not considered.

43
Conceptual Issue Overview
  • Should the DISCO take a more proactive approach
    to DR in the future and seek to acquire 170 to
    210 MW of DR?
  • ISSUE There is a belief that DR market benefits
    are large, but when DISCO benefits are examined
    they are found to be much smaller than the
    perceived market benefits.
  • The Discussion Scenario -- An NSTAR DR investment
    producing 210 MW from a CI call program and a
    mass-market DLC program
  • Initial estimate of 80M in market-wide benefits
    over 5-year horizon with market-wide B/C ratio of
    3.4.
  • But, from an DISCO perspective, this investment
    provides 7.7M in benefits and 23.8M in costs
    over 5-year horizon with NSTAR B/C ratio of only
    0.3.
  • DISCO customer perspective -- Customers receive
    at least 20 of the market benefits or 16.4M
    plus incentive payments of 16M from program
    participation NPV discounted over five years for
    a customer B/C of 1.4.

44
Setting the Stage Views on Market Benefits of
DR
  • Overall, there is a basic belief among many
    organizations that market benefits from DR are
    sizeable
  • ISO-NE Regional Transmission Expansion Plan
    states that DR can have significant benefits in
    terms of reliability and savings in congestion
    costs.
  • New England Demand Response Initiatives Final
    Draft Report states that a small amount of DR can
    enhance system reliability and substantially
    reduce market-clearing prices, producing
    significant benefits to consumers.
  • ISO-NE 2002 DR Program Evaluation states that
    magnitudes of DR sufficient to clear the market
    at lower bid prices (ECP), will reduce the price
    of energy for all purchasers in the spot market.
  • The NYISO states that it has had a successful DR
    program in operation through two summers which
    has delivered benefits to the grid in terms of
    reduced market price and improved system
    reliability.

45
Setting the Stage (cont.)
  • FERC SMD and White Paper
  • Demand response is essential in competitive
    markets to assure the efficient interaction of
    supply and demand.
  • Demand response options should be available so
    that end users can respond to price signals.
  • California PUC -- Demand Response is a vital
    resource to enhance electric system reliability,
    reduce power purchase cost and individual
    consumer costs R. 02-06-001, Order Instituting
    Rule making, June 6, 2002.
  • California Energy Commission 2002 2012
    Electricity Outlook Report estimates that an
    increased level of DR could have saved California
    2.5 billion in year 2000.
  • FINALLY -- California Energy Commission Order
    Instituting Rulemaking (June 17, 2003) states
    that the CEC will consider the acquisition of
    2,500 MW of DR (approx. 5 of peak demand) to
    moderate price increases and improve system
    reliability.

46
Setting the Stage (cont.)
August 14 2002 Hour 15 Supply Curve (ISO-NE)
Peak load reduced by 5
  • A 5 reduction in peak load can generate a 50
    reduction in ECP.
  • DR can reduce the price of energy for all
    purchasers in the spot market.
  • DR can play a significant role in price spike
    mitigation in lieu of price caps.
  • Source ISO-NE 2002 DR Program Evaluation.

47
DISCO Benefits
  • Defer or eliminate TD capital expenditures
  • Provide (n-1) reserve
  • Standby generation
  • Curtailable load
  • Emergency Response Resource
  • Hedge against questionable forecasts
  • Extreme weather events
  • Unforeseen load growth
  • Rapid development
  • Assist during contingency/emergency events
  • Revenues from ISO-NE DRR capacity and energy
    payments to any DRR provider.

48
NSTAR DR Program Costs
  • Proposed Program Cost Categories
  • Staff time (development, marketing,
    implementation)
  • Software systems
  • Physical infrastructure
  • Incentive payments
  • Financial assistance to participants
  • Revenue differentials due to rate impacts

49
DISCO Benefits Costs
  • An interactive process involving NSTAR staff and
    enabling technology manufacturers and vendors was
    used to calculate the benefits and costs
  • Distribution System Planning
  • Regulatory Policy and Rates
  • ISO-NE Liaison
  • The calculations were based upon estimates of
    achievable DR by key rate classes
  • Geographic and demographic analyses of customer
    characteristics in relation to key distribution
    system nodes
  • Rate analyses were also performed to estimate DR
    impacts on billing determinants

50
DRs Impact on DISCO Revenues
  • Monthly peak demand determines billing kW.
  • Analyses assume a 10 reduction in billing
    determinants.
  • For programs examined, revenue differentials
    minimal (under .1) as only participants are
    impacted and other high consumption hours make up
    for the reduced demand charge for these
    participants in hours with load control.

51
NSTAR BCR
NSTAR BCR 0.32

Deferred TD Expenditures Revenue from ISO-NE
NSTAR Benefits 7.7M
Market Benefits 80.1M
Benefits
Costs
  • NSTAR Expanded DR
  • Program costs
  • Lost revenues

NSTAR Investment 23.8M
  • - Calculations assume 160 MW enrolled in CI call
    option program and 10 MW enrolled in mass-mkt
    program in 2004 increasing by 10 MW per year
    until 50 MW are enrolled in 2008.
  • Values are NPV over 5 years at 7.72 discount
    rate.

52
Market-Wide Benefits
  • A pivot factor in assessing NSTAR options
  • Simple analyses used to justify assumed large
    benefits in terms of
  • 1. Hedges against price spikes in spot markets,
  • 2. Reduced price volatility influencing all MW
    transactions through lowered forward price curve,
    and
  • 3. Increased reliability (TD system and
    generation adequacy)
  • 4. Portfolio value due to resource diversity --
    DR supply costs not correlated with fuel prices,
    plant outages, and transmission congestion.
  • 5. Reduced market power -- Mkt power exists on
    peak days when transmission constraints do not
    all for the import of power into zones.
  • Methods for estimating benefits have not been
    standardized and are still being developed.
  • Existing studies are retrospective and show low
    price effects from DR -- BUT what might occur in
    the next five years?

53
Market Extended Market Benefits
  • Market Benefits
  • Transfer/Collateral Benefits
  • Reduction in long-term hedging costs
  • System reliability improvement
  • Extended Market Benefits
  • Transmission Real Options Value
  • Increased incentive for innovation
  • Increased resource portfolio diversity
  • Reduction in market power
  • Operating reserves demand curve

54
Market Benefits Definitions
  • Collateral Savings Reduction in market-clearing
    prices in spot markets impacted by DR. Also
    referred to as Benefits to Non-participant
    Buyers.
  • Hedging Benefits Savings due to reduced average
    prices and price variability in the market.
    Results lowered forward price curve for all MW
    transactions.
  • Reliability Benefits Enhanced grid reliability
    and reduced probability of customer outages
    (reduced ISO-NE calculated LOLP).
  • Transmission Real Options Value Hedge against
    low probability, high consequence events Only
    counted in Extended Market Benefits Analysis.

55
Rationale for including Market Benefits
  • DR has positive impacts beyond those captured by
    traditional benefit/cost tests.
  • DR has potential to ameliorate generation,
    transmission, and distribution issues in specific
    situations.
  • FERC estimated that a 5 reduction in peak demand
    could have reduced recent California price spikes
    by 50.
  • NSTAR has received societal benefits funds to
    assess a small-scale demand response program for
    commercial customers.

56
Market BCR for DISCO Program
Market BCR 3.36 Extended Market BCR 5.34Based
on an Options Value of 25 million (best guess)
  • Generation Reliability
  • - Reserves
  • - Outage costs
  • Reduced Energy Costs
  • - MWh prices
  • - Hedging costs

Market Benefits 80.1M
Benefits
Costs
  • NSTAR Expanded DR
  • Program costs
  • Resource costs

NSTAR Investment 23.8M
  • Best practices used to estimate market benefits.
  • Much debate about the magnitude of the benefits.
  • Calculations assume 160 MW enrolled in CI call
    option program and 10 MW enrolled in mass-mkt
    program in 2004 increasing by 10 MW per year
    until 50 MW are enrolled in 2008.
  • Values are NPV over 5 years at 7.72 discount
    rate.

57
Go/No Go Factors for DRR
  • Conditions favoring DR initiatives
  • Escalating or volatile energy prices
  • Plant outages and reduced generation availability
  • Uncertainty in capital markets
  • Unexpected growth in electric demand
  • Wide availability of advanced metering technology
  • Increased risk management costs
  • Conditions hindering DR initiatives
  • Bifurcation of incentives
  • Supply/generation technology breakthroughs
  • Low cost of capital for plant additions
  • Stable or low growth in electric demand
  • Status quo regulatory posture (e.g. no
    innovative rates, etc.)

58
Regulatory and Market Unknowns
  • Regulatory environment
  • Will regulators encourage distribution companies
    to promote DR that serves dual purposes (DISCO
    benefits and MARKET benefits) via rates or
    incentives?
  • Depends upon perceived market-wide benefits.
  • Market environment
  • Will suppliers (load serving entities -- LSEs)
    pay the DISCO for commodity price risk protection
    via DR?
  • Will there be competitive curtailment service
    providers (CSPs) that serve the market function?
  • Will outsourced DRR become an industry convention
    (e.g., the purchase of a Texas Utility's DRR
    program by a technology company, i.e., Comverge,
    Inc.)?

59
KEMA-XENERGY ExampleMethod 1 Black Scholes
  • Value of options to buy or sell at fixed prices
  • Call option to buy at X if market goes higher
  • Put option to sell at X if market goes lower
  • Other Inputs
  • r risk-free rate of return
  • s volatility
  • DR as call option that reduces risk
  • Avoided expected price base value
  • Call option says I can buy at a fixed price
  • Value of the call option is the value of avoided
    exposure to prices above base

60
KEMA-XENERGY Method 1 Black Scholes - Problems
  • If market drops, could have paid too much for DR
  • To protect against overpayment risk, could buy a
    put option
  • Strike price cost of DR (/ MWh)
  • Cost of overpayment risk value of the put
    option, whether or not we actually buy it.
  • NOTE Black Scholes not typically assumed to
    apply to electricity markets, but it is easily
    applied as and example.

61
KEMA-XENERGY Method 2 Portfolio Optimization
  • Monte Carlo simulation compares cost and risk of
    alternative portfolios (used instead of
    closed-form Black-Scholes)
  • Can construct a supply portfolio to satisfy
    reliability requirement
  • Balancing cost and risk
  • Define cost-risk trade-off explicitly or
    implicitly
  • In simple illustration,
  • Price volatility is only source of risk
  • Model interaction between native generation and
    market

62
KEMA-XENERGY Method 2 Portfolio Comparison
Generation Capacity

Demand and Market Prices
Market Price Volatility 28
63
KEMA-XENERGY Method 2 Portfolio Comparison

NOTE This is only one piece of the puzzle, but
it is indicative of new thinking in approaching
these problems. From AESP/EPRI
Pricing Conference, May 18-19, 2004
64
Alternative Portfolio Approach
  • 1. Information needs for DRR planning
  • Resource characterization and value analyses.
  • Need to dimension uncertainty around key factors.
  • 2. What is needed from the planning tools
  • Ability to work with distributions as inputs.
  • Address the value of information as uncertainty
    is reduced over time.
  • Time steps are required in the analyses.
  • 3. A simplified example
  • 4. Conclusions

65
Application of Portfolio Analyses
  • Today's planning environment requires analyses
    that
  • Uncertainty be incorporated in the analyses.
  • Risk mitigation options must be identified and
    valued.
  • Appropriately credit Demand Response (DR) and
    Energy Efficiency (EE) for risk management and
    other values.
  • Hedging values as expressed in reduced mean peak
    period prices and price volatility -- both
    influence forward price curves.
  • Direct price impacts in spot market transactions
    (gas and electric).
  • Other values (market power, innovation, customer
    values).
  • Address the value of information and learning
    over time.
  • Assess the value of flexibility, i.e., creation
    of real options to address future contingencies
    (some may not yet be known).
  • Continue to appropriately analyze supply-side
    economics.

66
Application of New Tools
  • Need to dimension uncertainty.
  • Assess Value at Risk from different options.
  • Fully address the portfolio of demand-side and
    supply-side options.
  • Need to work with distributions of outcomes
  • Closed form solutions and analytics.
  • Monte Carlo methods.
  • Decision-tree variants.
  • Must incorporate time steps to address
    flexibility.
  • New models such as _at_RISK and Crystal Ball allow
    for analyses based on representations of market
    uncertainties.
  • Supply-side models also incorporate Monte Carlo
    solutions, e.g., General Electric's MAPS model
    and Global Energy Decision's MIDAS model.
    Adaptations of these models may be useful.

67
Information Needs for Portfolio Analyses
  • 1. Appropriately capturing all the value
    associated with a resource option.
  • Many values associated with demand-side options
    are difficult to quantify, but are growing in
    importance as supply-side resources become more
    constrained (e.g., transmission congestion, and
    natural gas availability and prices)
  • 2. Need to dimension uncertainty around future
    outcomes.
  • Simple planning paradigms such as 1 in 10 year
    events are not very useful in assessing option
    and hedge values as they only represent one
    point.
  • Different approaches are needed for dimensioning
    uncertainty if new tools are to be useful.

68
2. Dimensioning Uncertainty
  • Expressing and dimensioning uncertainty for use
    in analyses.
  • Uncertainty is what makes hedges and options
    valuable.
  • If we could use point estimates and were certain
    about their values, there is no need for options
    or hedges since the optimal solution would simply
    be picked.
  • Industry has used few tools to express
    uncertainty
  • Key problem -- How to dimension uncertainty for
    use in planning analyses (simplest to more
    complex)
  • 1. Scenario analyses
  • 2. Range estimates -- construct confidence
    intervals based on key inputs.
  • 3. Range estimates with the range filled in with
    likelihood estimates to provide a rough cut
    probability distribution.

69
Scenarios Versus Distributions
70
Application of New Tools
  • Need to dimension uncertainty.
  • Assess Value at Risk from different options.
  • Fully address the portfolio of demand-side and
    supply-side options.
  • Need to work with distributions of outcomes
  • Closed form solutions and analytics.
  • Monte Carlo methods
  • Decisions tree variants
  • Must incorporate time steps to address
    flexibility.
  • New models such as _at_RISK and Crystal Ball allow
    for analyses based on representations of market
    uncertainties.

71
Simplified Example -- Decision Tree
Time Period T 1
Objective MinimizeRevenue Requirementsover 10
years. Time Step One-year steps overa 10-year
period. Proxy Example Real applicationwould
includedistributions insteadof single
probabilitynodes.
SupplyPortfolio2
SupplyPortfolio3
Other Time Steps
SupplyPortfolio1
GasPrices
SeasonalEnergyDemandMetrics
PeakDemandMetrics



High .6
Low .4
High .7



High .5
Low .3



High .5
Low .5



High .5
Low .5



Low .5
High .5



High .4



Low .5
Low .6



NPVVAR
NPVVAR
NPVVAR
72
Example DistributionStochastic Price Forecasts
73
Example DistributionForecasted Bill Changes
74
Conclusions (Agree/Disagree?)
  • The tools exist to assess portfolio of
    supply-side and demand-side options.
  • This requires
  • 1. Appropriate resource characterization.
  • 2. Representations of the uncertainty around key
    factors in the analysis.
  • The challenge is to change perspectives and to
    get planners to move out of their comfort zone to
    develop better (i.e., more accurate)
    representations of uncertainty.
  • Representing uncertainty and the value of
    information over time is the key challenge as
    both contribute to the value of options and
    hedges.
  • This is new to planners, but it is necessary --
    the good news is we have the tools and processes
    that will allow these analyses.

75
Conclusions -- Unique DRR Valuation Problems
  • Values accrue to different entities
  • Distribution companies in terms of deferred
    maintenance and new facilities, plus contingency
    avoidance.
  • Transmission owners through reduced capacity and
    maintenance.
  • Reliability managers through lowered costs of
    better Loss of Load Probabilities (LOLPs).
  • Customers who now are able to receive payment for
    their ability to use electricity flexibility.
  • A key attribute of consumption is now given a
    value.
  • SO -- Values accrue to many and to the market at
    large, but costs are concentrated at the program
    level.
  • Value is segmented with no one group is willing
    to provide full value for DR, but generators can
    be consolidated opponents.

76
Day 2 Topics
  • Suggestions for additional topics
  • 1. Final report outline just to see if one view
    of the project deliverable fits with the needs of
    most IEA participants.
  • 2. What tools might we want to include in our
    review and try to build on
  • Supply-side production cost models (probabilistic
    and non-probabilistic)
  • Load shaping tools
  • Monte Carlo and decision analysis tools (_at_RISK
    and Crystal Ball)
  • Others?
  • 3. Can we use information used to assess
    distributed generation to help address
    curtailable load options?
  • 4. Other topics

77
  • Meeting Moderators
  • Dan Violette Pete ScarpelliSummit Blue
    Consulting RETX, Inc.1722 14th Street,
    230Boulder, Colorado 80302 Chicago,
    IllinoisPh 720-564-1130 Ph312-953-4642E-Mai
    l dviolette_at_summitblue.com E-Mail
    pscarpelli_at_retx.com
  • Meeting Host
  • Mikael TogebyElkraft SystemLautruphøj 72750
    BallerupPh 44 87 36 16www.elkraft-system.dk
Write a Comment
User Comments (0)
About PowerShow.com