Title: Chapter%208%20Operations%20Scheduling
1Chapter 8Operations Scheduling
2Scheduling Problems in Operations
- Job Shop Scheduling
- Personnel Scheduling
- Facilities Scheduling
- Vehicle Scheduling and Routing
- Project Management
- Dynamic versus Static Scheduling
3The Hierarchy of Production Decisions
4Characteristics of the Job Shop Scheduling
Problem
- Job Arrival Pattern
- Number and Variety of Machines
- Number and Skill Level of Workers
- Flow Patterns
- Evaluation of Alternative Rules
-
5Objectives in Job Shop Scheduling
- Meet due dates
- Minimize work-in-process (WIP) inventory
- Minimize average flow time
- Maximize machine/worker utilization
- Reduce set-up times for changeovers
- Minimize direct production and labor costs
- (note that these objectives can be conflicting)
6Terminology
- Flow shop shop design in which machines are
arranged in series - A Pure Flow Shop
- In general flow shop a job may skip a particular
machine
7Terminology
- Job shop the sequencing of jobs through machines
- A job shop does not have the same restriction on
workflow as a flow shop. In a job shop, jobs can
be processed on machines in any order - Usual job shop contains m machines and n jobs to
be processed - Each job requires m operations (one on each
machine) in a specific order, but the order can
be different for each job - Real job shops might not require to use all m
machines and yet may have to visit some machines
more than once - Workflow is not unidirectional in a job shop
- One Machine in a Job Shop
8Terminology
- Parallel processing vs. sequential processing
parallel processing means that the machines are
identical - In practice, there are often multiple copies of
the same machine - A job arriving at a work center can be scheduled
on any one of a number machines ? more
flexibility, complicating the scheduling problem
further - A factory might have multiple identical
machines, purchased from the same manufacturer,
that produce parts with higher quality on one
machine than on any other - Schedule provides the order in which jobs are to
be executed, and projects start time for each job
at each work center - Sequence lists the order in which jobs are to be
done
9Terminology Performance Measures
- Average WIP level .(is exactly what it sounds
like) - Flowtime The amount of time a job spends from
the moment it is ready for processing until its
completion, and includes any waiting time prior
to processing - Average WIP level is directly related to the time
jobs spend in the shop (flowtime) - Makespan The total time for all jobs to finish
processing - For a single machine problem, the makespan is the
same regardless of the schedule, assuming we do
not allow any idle time between jobs
10Terminology Performance Measures
- Performances that have to do with each jobs due
date - Lateness The amount of time a job is past its
due date - Lateness is a negative number if a job is early
- Earliness The amount of time a job a early
- Tardiness Equals to zero if job is on time or
early, and equals to lateness if the job is late - Measures of the cost of production
- Machine utilization and labor utilization are
primary measures of shop utilization
11Deterministic Scheduling of a Single Machine
Priority Sequencing Rules
- Random Choose the next job at random. Do not use
it! - FCFS First Come First Served. Jobs processed in
the order they arrive to the shop. Viewed as a
fair rule. - SPT Shortest Processing Time. Jobs with the
shortest processing time are scheduled first.
Popular method to determine the next homework
assignment by many students.
12Deterministic Scheduling of a Single Machine
Priority Sequencing Rules
- SWPT Shortest Weighted Processing Time. A weight
is assigned to each job based on the jobs value
(holding cost) or on its cost of delay - EDD Earliest Due Date. Jobs are sequenced
according to their due dates. - CR Critical Ratio. Compute the ratio of
processing time of the job and remaining time
until the due date. Schedule the job with the
largest CR value next, however, if the job is
late, the ration will be negative, or the
denominator will be zero, and this job should be
given highest priority -
- (Processing time remaining until completion) /
(Due Date Current Time)
13FCFS Example
Flowtime The amount of time a job spends from
the moment it is ready for processing until its
completion, and includes any waiting time prior
to processing Earliness The amount of time a job
a early
Job j pj Dj Cj Fj Lj Ej Tj
1 7 8 7 7 -1 1 0
2 1 12 8 8 -4 4 0
3 5 6 13 13 7 0 7
4 2 4 15 15 11 0 11
5 6 18 21 21 3 0 3
Average 12.8 3.2 1 4.2
Max 21 11 4 11
14SPT Example
Shortest Processing Time
- is optimal for minimizing
- Average and Total flowtime
- Average waiting time
- Average and Total lateness
Job j pj Dj Cj Fj Lj Ej Tj
2 1 12 1 1 -11 11 0
4 2 4 3 3 -1 1 0
3 5 6 8 8 2 0 2
5 6 18 14 14 -4 4 0
1 7 8 21 21 13 0 13
Average 9.4 -0.2 3.2 3
Max 21 13 11 13
15SWPT Example
Shortest Weighted Processing Time -total weighted
down time -sequencing
Job j Pj Dj wj pj//wj Cj Fj wjFj Lj Ej Tj
4 2 4 5 0.4 2 2 10 -2 2 0
2 1 12 2 0.5 3 3 6 -9 9 0
5 6 18 4 1.5 9 9 36 -9 9 0
3 5 6 3 1.67 14 14 42 8 0 8
1 7 8 2 3.5 21 21 42 13 0 13
Ave 9.8 27.2 0.2 4 4.2
Max 21 42 13 9 13
16EDD Example
Job j pj Dj Cj Fj Lj Ej Tj
4 2 4 2 2 -2 2 0
3 5 6 7 7 1 0 1
1 7 8 14 14 6 0 6
2 1 12 15 15 3 0 3
5 6 18 21 21 3 0 3
Average 11.8 2.2 0.4 2.6
Max 21 6 2 6
17CR Example
Subtract Current Time
Job j pj Dj CRj
1 7 8 0.875
2 1 12 0.083
3 5 6 0.833
4 2 4 0.500
5 6 18 0.333
Job j pj Dj Dj-CT CRj
2 1 12 5 0.200
3 5 6 -1 -5.000
4 2 4 -3 -0.667
5 6 18 11 0.545
Schedule jobs 1 ?4 ? 3 ? 2 ? 5
18CR Example (cont)
Job j pj Dj Cj Fj Lj Ej Tj
1 7 8 7 7 -1 1 0
4 2 4 9 9 5 0 5
3 5 6 14 14 8 0 8
2 1 12 15 15 3 0 3
5 6 18 21 21 3 0 3
Average 13.2 3.6 0.2 3.8
Max 21 8 1 8
19Comparing Methods
Method Fj Lj Ej Tj
FCFS Ave 12.8 3.2 1 4.2
Max 21 11 4 11
SPT Ave 9.4 -0.2 3.2 3
Max 21 13 11 13
SWPT Ave 9.8 0.2 4 4.2
Max 21 13 9 13
EDD Ave 11.8 2.2 0.4 2.6
Max 21 6 2 6
CR Ave 13.2 3.6 0.2 3.8
Max 21 8 1 8
20Results for Single Machine Sequencing
- The rule that minimizes the mean flow time of all
jobs is SPT. - The following criteria are equivalent
- Mean flow time
- Mean waiting time.
- Mean lateness
- Moores algorithm minimizes number of tardy jobs
- Lawlers algorithm minimizes the maximum flow
time subject to precedence constraints.
21EDD Example
Job j pj Dj Cj Fj Lj Ej Tj
4 2 4 2 2 -2 2 0
3 5 6 7 7 1 0 1
1 7 8 14 14 6 0 6
2 1 12 15 15 3 0 3
5 6 18 21 21 3 0 3
Average 11.8 2.2 0.4 2.6
Max 21 6 2 6
22Minimizing the Number of Tardy Jobs
- Morre Algorithm - minimizes number of tardy jobs
- Step 1 Sequence the jobs according to EDD rule
and initially put all jobs in set V - Step 2 Find the first tardy job in set V say it
is job k in the sequence. If there are no
tardy jobs in the set V, stop the sequence is
optimal - Step 3 Select the job with largest processing
time among first k jobs. Place this job in set U.
Go to step 2 - Comments
- 1. Placing a job in set U means that it will be
tardy and will occupy a position in sequence
after all non-tardy jobs - 2. Tardy jobs may be schedules in any order
because the performance measure is the number of
tardy jobs
23Example Moore Algorithm
Alt. solution 1 4 2 5 3
Job j pj Dj Cj Fj Lj Ej Tj
4 2 4 2 2 -2 2 0
3 5 6 7 7 1 0 1
1 7 8 14 14 6 0 6
2 1 12 15 15 3 0 3
5 6 18 21 21 3 0 3
Average 11.8 2.2 0.4 2.6
Max 21 6 2 6
Iteration 1
Iteration 2
4 2 4 2 2 -2 2 0
1 7 8 9 9 1 0 1
2 1 12 10 10 -2 2 0
5 6 18 16 16 -2 2 0
3 5 6 21 21 15 0 15
Iteration 3
4 2 4 2 2 -2 2 0
2 1 12 3 3 -9 9 0
5 6 18 9 9 -9 9 0
3 5 6 14 14 8 0 8
1 7 8 21 21 13 0 13
Average 9.8 0.2 4 4.2
Max 21 13 9 13
24Lawlers Algorithm minimizes the maximum flow
time subject to precedence constraints.
- Goal Scheduling a set of simultaneously
arriving tasks on one machine with precedence
constraints to minimize maximum lateness
(tardiness). - Precedence constraints occur when certain jobs
must be completed before other jobs can begin. - Algorithm
- Tasks are scheduled in reverse order job to be
completed last is scheduled first. - At each step selection is made from the jobs
that are not required to precede any other
unscheduled job. - Select a job that achieves
25Lawlers Example
Processing for all jobs is 1 day
- One machine ? Ffinal 111111 6
- Select from jobs 4,5,6 such that gives
- min6-3, 6-5, 6-60 ? job 6 is a last job
2) Recalculate F F 6-1 5 Select
from jobs 3,4,5 such that gives min5-4,
5-3, 5-50 ? order x-x-x-x-5-6
3) Recalculate F F 5-1 4 Select
from jobs 3,4 such that gives min4-4,
4-30 ? order x-x-x-3-5-6
4) Recalculate F F 4-1 3 Select
from jobs set 4 ? order x-x-4-3-5-6
5) Recalculate F F 3-1 2 Select
from jobs set 2 ? order x-2-4-3-5-6
6) Recalculate F F 2-1 1 Select
from jobs set 1 ? order 1-2-4-3-5-6
26Lawlers Example
Production is done in next order 1 2 4 3
5 6
Lawlers algorithm minimizes the maximum flow
time subject to precedence constraints
Processing for all jobs is 1 day
Job j pj Dj Cj Fj Lj Ej Tj
1 1 2 1 1 -1 1 0
2 1 5 2 2 -3 3 0
4 1 3 3 3 0 0 0
3 1 4 4 4 0 0 0
5 1 5 5 5 0 0 0
6 1 6 6 6 0 0 0
Average 3.5 -0.67 0.67 0
Max 6 0 3 0
27Gantt Charts
- Pictorial representation of a schedule is called
Gantt Chart - The purpose of the chart is to graphically
display the state of each machine at all times - Horizontal axis time
- Vertical axis machines 1, 2, , m
Processing Job 1 Job 2
Machine 1 3 5
Machine 2 2 1
Processing Job 1 Job 2
Machine 1 3/1 5/2
Machine 2 2/2 1/1
Question Is it an optimal schedule? Are there
any precedence constrains?
28Gantt Charts
Processing Job 1 Job 2
Machine 1 3 5
Machine 2 2 1
Processing Job 1 Job 2
Machine 1 3/1 5/2
Machine 2 2/2 1/1
Question How to determine THE optimal
solution? What makes scheduling problem more
difficult?
29Example
Processing time / machine number Processing time / machine number Processing time / machine number
Job Operation 1 Operation 2 Operation 3 Release date Due date
1 4/1 3/2 2/3 0 16
2 1/2 4/1 4/3 0 14
3 3/3 2/2 3/1 0 10
4 3/2 3/3 1/1 0 8
Completed by 14 11 13 (late) 10 (late)
Find a solution!
30Deterministic Scheduling with Multiple Machines
- For the case of m machines and n jobs, there are
n! distinct sequenced on each machine
(permutations), so (n!)m is the total number of
possible schedules - For m 3 and n 4, total number of possible
schedules is 24313,824 - Assume that each job must be processed in the
order - First on machine 1, then machine 2.
- The optimal solution for scheduling n jobs on two
machines to minimize the total flow time is
always a permutation schedule - Assume flow shop in each job operations have to
be done on both machines - Permutation schedule is when jobs are done in the
same order on both machines - This is the basis for Johnsons algorithm
31Example
MetalFrame makes 4 different types of metal door
frames. Preparing the hinge upright is a two-step
operation. Natural schedule
Jobs Jobs Jobs Jobs
Machines 1 2 3 4 Total time
1 5 4 3 2 14
2 2 5 2 6 15
Is it optimal?
If idle time for machine 2 is equal to zero,
then we have found an optimal solution
32Deterministic Scheduling with Multiple Machines
Johnsons Rule
- Name Machine 1 A, Machine 2 B,
- then ai processing time for job i on A
- and bi processing time for job i on B
- Johnsons Rule says that job i precedes job j in
the optimal sequence if - Algorithm
- Step 1 Record the values of ai and bj in two
columns - Step 2 Find the smallest remaining value in two
columns. If this value in column a, schedule this
job in the first open position in the sequence
if this value in column b, schedule this job in
the last open position in the sequence Cross off
each job as it is scheduled
33Example (cont)
Jobs Jobs Jobs Jobs
Machines 1 2 3 4 Total time
1 5 4 3 2 14
2 2 5 2 6 15
Johnsons schedule 4 x x x
4 x x 3
job A B
1 5 2
2 4 5
3 3 2
4 2 6
4 x 1 3
4 2 1 3
Natural schedule
Johnsons schedule
Is it optimal?
34Results for Multiple Machines
- For three machines, a permutation schedule is
still optimal if we restrict attention to total
flow time only (not necessarily the case for
average flow time). - Under some circumstances, the two machine
algorithm can be used to solve the three machine
case - Label the machines A, B and C
- or
- Redefine Ai Ai Bi and Bi Bi Ci
- When scheduling two jobs on m machines, the
problem can be solved by graphical means.
35Sequencing Theory The Two-Job Flow Shop Problem
- Assume that two jobs are to be processed through
m machines. Each job must be processed by the
machines in a particular order, but the sequences
for the two jobs need not be the same - Graphical procedure developed by Akers (1956)
- Draw a Cartesian coordinate system with the
processing times corresponding to the first job
on the horizontal axis and the processing times
corresponding to the second job on the vertical
axis (keeping order) - Block out areas corresponding to each machine at
the intersection of the intervals marked for that
machine on the two axes - Determine a path from the origin to the end of
the final block that does not intersect any of
the blocks and that minimizes the vertical
movement. Movement is allowed only in three
directions horizontal, vertical, and 45-degree
diagonal. The path with minimum vertical distance
corresponds to the optimal solution
36Example 8.7 (in the book) A regional
manufacturing firm produces a variety of
household products. One is a wooden desk lamp.
Prior to packing, the lamps must be sanded,
lacquered, and polished. Each operation requires
a different machine. There are currently
shipments of two models awaiting processing. The
times required for the three operations for each
of the two shipments are The order of
operations is the same for both jobs A ? B ? C ?
Job 1 Job 1 Job2 Job2
Operation Time Operation Time
Sanding (A) 3 A 2
Lacquering (B) 4 B 5
Polishing (C) 5 C 3
37Minimizing the flow time is equivalent to finding
the path from the origin to the upper right point
F (for this problem it is art the end of block C)
that maximizes the diagonal movement and
therefore minimizes either the horizontal or the
vertical movement.
Job 1 Job 1 Job2 Job2
Time Time
A 3 A 2
B 4 B 5
C 5 C 3
10 (6)16
12 (3)15
38Example
142218
14418
Job 1 Job 1 Job2 Job2
Order Operation Time Order Operation Time
B 3 A 2
D 4 D 5
C 2 B 4
A 5 C 3
39Schematic of a Typical Assembly Line
- The problem of balancing an assembly line is a
classic engineering problem - A set of n distinct tasks that must be
completed on each item - The time required to complete task i is a known
constant ti - The goal is to organize the tasks into groups,
with each group of tasks being performed at a
single workstation - The amount of time allotted to each workstation
is determined in advance - (C cycle time), based on the desired rate
of production of the assembly line
40Assembly Line Balancing
- Assembly line balancing is traditionally thought
of as a facilities design and layout problem - There are a variety of factors that contribute to
the difficulty of the problem - Precedence constrains some tasks may have to be
completed in a particular sequence - Zoning restriction Some tasks cannot be
performed at the same workstation - Let t1, t2, , tn be the time required to
complete the respective tasks
41Assembly Line Balancing
- The total work content (time) associated with the
production of an item, say T, is given by
- For a cycle time of C, the minimum number of
workstations possible is T/C, where the
brackets indicate that the value of T/C is to be
rounded to the next larger integer - Ranked positional weight technique the method
places a weight on each task based on the total
time required by all of the succeeding tasks.
Tasks are assigned sequentially to stations based
on these weights
42Assembly Line Balancing
- Example 8.11
- The Final assembly of Noname personal
computers, a generic mail-order PC clone,
requires a total of 12 tasks. The assembly is
done at the Lubbock, Texas, plant using various
components imported from the Far East. The
network representation of this particular problem
is given in the following figure.
43Assembly Line Balancing
- Precondition
- The job times and precedence relationships for
this problem are summarized in the table below.
Task Immediate Predecessors Time
1 _ 12
2 1 6
3 2 6
4 2 2
5 2 2
6 2 12
7 3, 4 7
8 7 5
9 5 1
10 9, 6 4
11 8, 10 6
12 11 7
44Assembly Line Balancing Helgeson and Birnie
Heuristic (1961)
- Ranked positional weight technique
- The solution precedence requires determining the
positional weight of each task. - The positional weight of task i is defined as the
time required
to perform task i plus the times
required to perform
all tasks having
task i as a predecessor.
Task Time Positional Weight
1 12 70
2 6 58
3 6 31
4 2 27
5 2 20
6 12 29
7 7 25
8 5 18
9 1 18
10 4 17
11 6 13
12 7 7
t3 t7 t8 t11 t12 31
The ranking 1, 2, 3, 6, 4, 7, 5, 8, 9, 10, 11, 12
? ti 70, and the production rate is a unit per
15 minutes The minimum number of workstations
70 / 15 5
45Assembly Line Balancing Helgeson and Birnie
Heuristic (1961)
Station 1 2 3 4 5 6
Tasks 1 2, 3, 4 5, 6, 9 7, 8 10, 11 12
Processing time 12 14 15 12 10 7
Idle time 3 1 0 3 5 8
Task Immediate Predecessors Time
1 _ 12
2 1 6
3 2 6
4 2 2
5 2 2
6 2 12
7 3, 4 7
8 7 5
9 5 1
10 9, 6 4
11 8, 10 6
12 11 7
The ranking 1, 2, 3, 6, 4, 7, 5, 8, 9, 10, 11, 12
46Helgeson and Birnie Heuristic (1961)
C15
Station 1 2 3 4 5 6
Tasks 1 2,3,4 5,6,9 7,8 10,11 12
Processing time 12 14 15 12 10 7
Idle time 3 1 0 3 5 8
Evaluate the balancing results by the efficiency
?ti/NC The efficiencies for C15 is 77.7,
C16 is 87.5, and C13 is 89.7 ?is the best one
Cycle Time15
T26
T112
T26
T36
T42
T52
T52
T612
T91
T85
T77
T104
T104
T116
T127
T127
47Helgeson and Birnie Heuristic (1961)
C15
Station 1 2 3 4 5 6
Tasks 1 2,3,4 5,6,9 7,8 10,11 12
Processing time 12 14 15 12 10 7
Idle time 3 1 0 3 5 8
C16
Increasing the cycle time from 15 to 16, the
total idle time has been cut down from 20
min/units to 10 ? improvement in balancing
rate. The production rate has to be reduced from
one unit/15 minutes to one unit/16minute
Station 1 2 3 4 5
Tasks 1 2,3,4,5 6,9 7,8,10 11,12
Idle time 4 0 3 0 3
C13
Station 1 2 3 4 5 6
Tasks 1 2,3 6 4,5,7,9 8,10 11,12
Idle time 1 1 1 1 4 0
48Helgeson and Birnie Heuristic (1961)
C15
Station 1 2 3 4 5 6
Tasks 1 2,3,4 5,6,9 7,8 10,11 12
Processing time 12 14 15 12 10 7
Idle time 3 1 0 3 5 8
C16
13 minutes appear to be the minimum cycle time
with six station balance. Increasing the number
of stations from 5 to 6 results in a great
improvement in production rate
Station 1 2 3 4 5
Tasks 1 2,3,4,5 6,9 7,8,10 11,12
Idle time 4 0 3 0 3
C13
Station 1 2 3 4 5 6
Tasks 1 2,3 6 4,5,7,9 8,10 11,12
Idle time 1 1 1 1 4 0
49Stochastic Scheduling Static Case
- Single machine case Suppose that processing
times are random variables. If the objective is
to minimize average weighted flow time, jobs are
sequenced according to expected weighted SPT.
That is, if job times are t1, t2, . . ., and the
respective weights are u1, u2, . . . then job i
precedes job i1 if - E(ti)/ui lt E(ti1)/ui1
- Multiple Machines Requires the assumption that
the distribution of job times is exponential,
(memoryless property). Assume parallel processing
of n jobs on two machines. Then the optimal
sequence is to to schedule the jobs according to
LEPT (longest expected processing time first). - Johnsons algorithm for scheduling n jobs on two
machines in the deterministic case has a natural
extension to the stochastic case as long as the
job times are exponentially distributed.
50Stochastic Scheduling Queueing Theory
- A typical queueing process
- The basic phenomenon of queueing arises whenever
a shared facility needs to be accessed for
service by a large number of jobs or customers.
(Bose) - The study of the waiting times, lengths, and
other properties of queues. (Mathworld) - Applications
-
- Telecommunications Health services
- Traffic control Predicting computer
performance - Airport traffic, airline ticket sales
Layout of manufacturing systems - Determining the sequence of computer operations
51Examples of Queueing Theory
http//www.bsbpa.umkc.edu/classes/ashley/Chaptr14/
sld006.htm
52Stochastic Scheduling Dynamic Analysis
- View network as collections of queues
- FIFO data-structures
- Queuing theory provides probabilistic analysis of
these queues - Typical operating characteristics of interest
include - Lq Average number of units in line waiting for
service - L Average number of units in the system (in
line waiting for service and being serviced) - Wq Average time a unit spends in line waiting
for service - W Average time a unit spends in the system
- Pw Probability that an arriving unit has to
wait for service - Pn Probability of having exactly n units in the
system - P0 Probability of having no units in the system
(idle time) - U Utilization factor, of time that all
servers are busy
53Characteristics of Queueing Processes
- Arrival pattern of customers
- Service pattern of servers
- Queue discipline
- System capacity
- Number of service channels
- Number of service stages
54Characteristics of Queueing Processes
- Arrival pattern of customers
- Probability distribution describing the times
between successive customer arrivals - Time independent ?Stationary arrival patterns
- Time dependent ? Non-stationary
- Batch or Bulk customer arrivals
- Probability distribution describing the size of
the batch - Customers behavior while waiting
- Wait no matter how long the queue becomes
- If the queue is too long, customer may choose not
to enter into the system - Enter, wait, and choose to leave without being
serviced - If there is more than one waiting line, customer
may switch jockey
55Characteristics of Queueing Processes
- Arrival pattern of customers
- Service pattern of servers
- Single or Batch
- May depend on the number of customers waiting ?
state dependent - Stationary or Non-stationary
- Queue discipline
- Manner in with customers are selected to service
- First Come First Served (FCFS)
- Last Come First Served (LCLS)
- Random Selection for Service (RSS)
- Priority Schemes
- Preemptive case
- Non-preemptive case
56Characteristics of Queueing Processes
- Arrival pattern of customers
- Service pattern of servers
- Queue discipline
- System capacity
- Finite queueing situations Limiting amount of
waiting room - Number of service channels
- Single-channel system
- Multi-channel system, generally assumed that
parallel channels operate independently of
each other - Number of service stages
57Notation Used in Queueing Processes
- Full notation A / B / X / Y / Z
Shorthand A / B / X -
- A indicates the interarrival-time
distribution Assumes Y is infinity, - B the probability distribution for service
time Z FCFS - X number of parallel service channels
- Y the restriction on system capacity
- Z the queue discipline (FCFS)
Symbol Explanation
A B M Exponential, D Deterministic, Ek Erlang type Hk Mixture of k exponentials, PH Phase type, G General
X Y 1, 2, ... , infinity 1, 2, ... , infinity
Z FCFS, LCLS, RSS, PR priority, GD general discipline
58Queueing Processes Littles Formulas
- One of the most powerful relationships in
queueing theory was developed by John D.C. Little
in the early 1960s. - Formulas
- and ,
- where ? is an average rate of customers entering
the system, and - W is an expected time customer will spend in
the system
59Poisson Process Exponential Distribution
- M stands for "Markovian", implying exponential
distribution for service times or inter-arrival
times, that carries the memoryless property - past state of the system does not help to predict
next arrival / departure
60Calculating Expected System Measures for M/M/1
- The utilization rate ? ? / µ
- P0 1 ?
- Pi ?i(1 ?), for i 1, 2, 3,
- these formulas hold only if lltm
CHARACTERISTIC SYMBOL FORMULA Utilization
? ? / µ Exp. No. in System L
? / (µ ?) ? / (1-?) Exp. No. in Queue
Lq ?2/ µ(µ ?) ?2 / (1-?) Exp. Waiting
Time WL/ ? 1 / (µ ?) ? / ?(1-?) Exp.
Time in Queue WqLq/ ? ? / µ(µ ?) ?2 /
?(1-?) Prob. System is Empty P0 1 (? / µ)
1 - ?
61Calculating Expected System Measures for M/M/m
http//www.ece.msstate.edu/hu/courses/spring03/no
tes/note4.ppt
62Calculating Expected System Measures for M/M/m
- Assumption
- - m servers
- - all servers have the same service rate µ
- - single queue for access to the servers
- - arrival rate ?n ?
- - departure rate
-
63Calculating Expected System Measures for M/M/m
64Example
- Unisex hair salon runs on a first-come,
first-served basis. Customers seem to arrive
according to a Poisson process with mean arrival
rate of 5/hr. Because of Ms. H.R. Cutts
excellent reputation, customers are always
willing to wait. Average service time of 10 min
is exponentially distributed. - Calculate the average number of customers in the
shop and the average number of customers waiting
for a haircut. - Calculate the percentage of time an arrival can
walk right in without having to wait at all. - The waiting room has only 4 seats. What is the
probability that a customer upon arrival rill
have to stand? - Calculate average system waiting time, and the
line delay.
65Other Systems
M/M/1/K - system with a capacity K ?eff
effective arrival rate M/D/1 M/G/1
M/G/8 Assignment download the QTS add-in for
Excel software to check the homework problems
answers http//www.geocities.com/qtsplus/Download
Instructions.htmDOWNLOAD_INSTRUCTIONS
66Homework Assignment
- Read Ch. 8 (8.1 8.10)
- Read Supplement Two (S2.1 - S2.13)
- 8.4, 8.5, 8.7, 8.12, 8.15,
- 8.18, 8.23, 8.25, 8. 27, 8.28
67References
- Presentation by McGraw-Hill/Irwin
- Presentation by Professor JIANG Zhibin,
Department of Industrial Engineering
Management, Shanghai Jiao Tong University - Production Operations Analysis by S.Nahmias
- Production Planning, Control, and Integration
by Sipper and Bulfin Jr. - Inventory Management and Production Planning and
Scheduling by Silver, Pyke and Peterson - Fundamentals of Queueing Theory by Cross and
Harris - http//www.geocities.com/qtsplus/DownloadInstructi
ons.htmDOWNLOAD_INSTRUCTIONS QTS analysis for
Excel