Title: CONSTRUCTION COST DATA OF PAKISTAN INSTITUTE OF COST AND CONTRACTS (PICC) (www.picc.org.pk) By: Engr.M.Mazhar-Ul-Islam (CEO PICC)
1CONSTRUCTION COST DATAOFPAKISTAN INSTITUTE OF
COST AND CONTRACTS (PICC) (www.picc.org.pk)By
Engr.M.Mazhar-Ul-Islam(CEO PICC)
2BACKGROUND
- A contract is a set of conditions at a price
- Unreasonable construction cost and inadequate
cash flows results poor quality delayed
construction - Right cost of contract for sustainable
construction - Departmental FBS data found inadequate
- Need exists for single source authentic data for
all construction inputs
3BACKGROUND
- Needed organization having capacity to prepare
such data - Since year 2007 MoH W initiated such efforts
- PPRA formally requested to PEC to be resource
organization for such data - Working papers finalized after two years
deliberations by 12 organizations - PEC amendment Bill 2011 envisages creation of
subsidiary and preparation of construction cost
data as PEC function
4ESTABLISHMENT OF PICC
- Approved by Governing Body on April 30th 2009 Rs.
50 million seed money for PICC as subsidiary - Commenced Operation from May 01, 2009
- Cost data was hosted on website on Sep 2009
- PC-1 for three years with an amount of Rs. 118
million approved by MoST and sent on 13.07.11 to
PC for CDWP approval
5ORGANIZATION AND MANAGMENT
- Incorporated in Lahore with SECP U/s-42 of
Company Ordinance as non- profit research
organization - PICC members are member organizations-represented
by their Natural persons - Majority members and Chairman in the PICC BoD
are from PEC and other from NESPAK and APCA - Independent Board of Directors comprises of PEC
and other Stakeholders. - CEO PICC to work under the PICC BoD
- Recruited 35 staff including 8 Market Surveyors
in major cities
6ORGANIZATION AND MANAGMENT
- National Steering Committee for controlling
authenticity of cost data - Prepared and got approved comprehensive Service
Manual from BoD. - PICC management committee holds meeting every
week for decision making in managing the PICC
affairs. - Recruitment is conducted in accordance with
predetermined job description and criteria on
merit. - State of the art online office environment.
7PICC ORGANIZATION CHART
8FUNCTIONS
- Prepare, update and maintain on PICC website the
cost data base for all construction inputs - Country specific schedule of rates
- Country specific procurement documents
- Guidelines for construction cost estimate
- Standard method of measurement
- Uniform classification system for specs BOQs
- Training and research on cost and contracts
9 PROGRESS
- Maintaining, monthly updating and progressively
uploading on the website the cost data, as per
detail given below, for all the districts of
Pakistan including AJK and Gilgit-Baltistan. - About 3134 basic input rates
- About 1986 composite item rates for concrete,
brick masonry, Stone masonry, Block masonry,
steel bars, formwork, plastering, pile works,
Earthwork and road works etc - Presently about 644,493 data items are being
monthly updated which are to be increased
progressively - Per unit rates and rates for quality control tests
10 PROGRESS
- Standard methods of measurements and Model BOQ
guidelines have been developed in line with the
international standards. - Comprehensive mechanism established for
determining the Transportation Charges for
various types of terrain. - Technical Specifications for concrete, masonry
works, piles and water supply sanitation are
developed and uploaded on website whereas for
various other sections are under development.
11AUTHENTICITY OF PICC COST DATA
- PICC Steering Committee of Experts approved the
PICC rates in six meetings before hosting to web - National Conference on Construction Cost on
10.08.10 validate PICC Cost Data by 19
stakeholders - Compared Oct-Dec, 2010 Govt of Punjab data with
PICC - Bid price of 5 different projects was compared
with PICC Cost data and found within 10 - PICC rates for sand, aggregate etc is almost
double in City than in quarry - PICC submitted itself for constant public review
by displaying providers/ sources detail
addresses
12(No Transcript)
13VIEW OF BASIC INPUT RATES
14VIEW OF BASIC INPUT RATES
15VIEW OF BASIC INPUT RATES
16VIEW OF COMPOSITE ITEM RATES
17VIEW OF COMPOSITE ITEM RATES
18VIEW OF COMPOSITE ITEM RATES
19BASIS FOR DETERMINATION OF TRANSPORTATION CHARGES
- Truck Capacity Monthly Hired Truck of 10 Ton
Capacity - Speed For a distance of 1 Km the Average Speed
is taken 10 Km/hr. An increment of 0.5 Km/hr is
considered for each Km upto a maximum average
speed of 30 Km/hr - Diesel Oil Consumption Diesel_at_3Km/ Liter
Engine oil_at_100Km/ Liter - Labor 06 No. Laborers are considered for
Loading, Unloading Stacking within 3/ 4 Hours
for each Trip - Allowances For Katcha, Hilly Hard Hilly Areas
An allowance for Katcha Hilly Areas is
considered as 25 where as For hard Hilly area as
40 - Toll Taxes Toll Taxes are also included
20TRANSPORTATION CHARGES
- A comprehensive mechanism is developed for
determining transportation charges in various
types of terrain
21PRICE FLUCTUATION TRENDS OF MAJOR MATERIALS
22PRICE FLUCTUATION TRENDS OF MAJOR MATERIALS
23PRICE FLUCTUATION TRENDS OF MAJOR MATERIALS
24(No Transcript)
25VIEW OF TECHNICAL SPECIFICATIONS
26UTILITY OF PICC COST DATA
- Preparation of budget cost estimates
- Preparation of Engineers Estimates
- Cost validation of PC-1 and third party cost
validation - Reference data for resolution of contractual
disputes - Reference data for price adjustment
- Reference data for Bidders to prepare the bids
27BENEFITS OF PICC COST DATA
- Verification for accuracy of project cost
- Transparency in the estimates
- Minimize malpractices and corruption
- Quality construction
- Timely completion
- Effective contract administration
- Minimizing cost overrun and financial loss to
the National exchequer during the currency of
contracts - Facilitate Cost Plus project execution
28RECOGNITION OF PICC DATA
- PICC cost data is appreciated in Seminars/
Workshops-so far by UET and NUST. - ADB from Pakistan mission and Manila made 6
visits and has approved the reward of Technical
Assistance of 149,500 U.S Dollar. - Upon invitation CEO PICC presented PICC cost data
in Feb, 2011 in Donors club (WB, USAID, EU,
DFID, ADB) in Islamabad - PICC Cost data was presented in TCDPAP/FIDIC
conference in Malaysia on 25 April 2011. - WB ADB arranged tour for presentation of PICC
cost data in Kathmandu on 27 April, 2011 as
model for South East Asia
29SELF-SUSTAINABILITY PLAN
- PICC yearly average budget is Rs. 25-30 M
- PICC is established with Rs. 50 M seed money
from PEC - Sustainability plan envisaged in PEC PC-1
- 10 of constructors license fees (5th 8th GB
Minutes) - 0.01 from ECNEC approved projects
- Donations from stakeholders Donor agencies
- Profit from training programs and Arbitration etc
- Fees from users of PICC data
- Advertisements
30SELF-SUSTAINABILITY PLAN
- PICC designed Self-sustainability plan in 3-5
years - Issuance of Notification is key to success
- ADB approved 149,500 grant for non-salary
component - Year 2011-2013 from PC-1 amount Rs. 118 M
31SELF-SUSTAINABILITY PLAN
- Year 2013-2015 from 3 years earning and earning
up to 2015 - Self-sustainability beyond 2016 through
- Professional services on cost contracts
- Fees from users of PICC data
- Advertisements on PICC website
- Savings from training programs and Arbitration
- Donations from stakeholders and Donor agencies
- Year 2011-13 stop gap funding arrangement by PEC
due to current financial crunch of GoP
32Thank you