Chapter 8: Project Analysis - PowerPoint PPT Presentation

1 / 43
About This Presentation
Title:

Chapter 8: Project Analysis

Description:

Use sensitivity, scenario, and break-even analysis to see how project ... Annuity factor=[1-1/1.14]/.10=3.17. EAC=$163,397/3.17=$51,547. Project B (life of 3 years) ... – PowerPoint PPT presentation

Number of Views:420
Avg rating:3.0/5.0
Slides: 44
Provided by: comm199
Category:

less

Transcript and Presenter's Notes

Title: Chapter 8: Project Analysis


1
Topic Project Analysis and Evaluation
Objectives
  • NPV estimates depend on projected future cash
    flows
  • Use sensitivity, scenario, and break-even
    analysis to see how project profitability would
    be affected by a change in forecasting
  • Explain the concept of operating leverage

2
Project Analysis
  • Some What If Analyses
  • Scenario Analysis
  • Sensitivity Analysis
  • Simulation Analysis
  • Break-Even Analysis
  • Additional Considerations in Capital Budgeting
  • Managerial Options
  • Capital Rationing

3
Scenario Analysis
  • The determination of what happens to NPV
    estimates when we ask what-if questions
  • Allow managers to look at different but
    consistent combinations of variables, and compare
    one particular combination with another
  • Forecasters usually prefer to give an estimate of
    revenues or costs under a particular scenario
    rather than giving some absolute optimistic or
    pessimistic value
  • Scenario analysis allows variables to be
    interdependent

4
Sensitivity Analysis
  • Investigation of what happens to NPV when only
    one variable is changed
  • e.g., sales, variable costs, fixed costs...
  • Sensitivity analysis is useful in pinpointing
    those variables that deserve the most attention
  • Sensitivity analysis assumes that the
    individual variables are independent of each
    other
  • Simulation analysis a combination of scenario
    and sensitivity analyses

5
Break-Even Analysis
  • Question How bad do sales have to get before we
    actually loose money?
  • Examines the relationship between sales volume
    and profitability
  • Variable Costs costs that change when the
    quantity of output changes
  • Fixed Costs costs that do not change when the
    quantity of output changes during a particular
    period

6
Example A-Sensitivity Analysis
  • A project currently generates sales of
    10million, variable
  • costs equal to 50 of sales, and fixed costs of
    2million. The
  • firms tax rate is 35. What are the effects of
    the following
  • changes on after-tax profits and cash flows?
  • a) Sales increase from 10million to 11million
  • b) Variable costs increase to 60 of sales

7
Example A
8
Example A
9
Operating Leverage
  • Operating leverage the degree to which a project
    or firm is committed to fixed costs
  • Degree of Operating Leverage (DOL) the change
    in operating cash flow relative to the change
    in the quantity sold
  • DOL measures the sensitivity of OCF to the
    quantity sold. Since FC do not vary with sales, a
    small change in Q can be magnified into a large
    change in OCF
  • The danger from incorrectly forecasting sales is
    directly related to its DOL. The higher the fixed
    costs, the greater the variation in operating
    cash flows given a change from estimated sales

10
Operating Leverage
  • Given that
  • Can you prove (ignoring taxes) that
  • Hint OCF(P-v)Q-FC, ignoring taxes, where P is
    unit price, v is unit cost, Q is sales and FC is
    fixed cost. Think about what happens when sales
    increases by 1.

11
Operating Leverage
12
NPV Break-Even Analysis
  • NPV Break-Even analysis calculates the level of
    sales that generates an NPV of zero the
    textbook calls this the financial break-even.
  • Sales higher than the zero NPV sales will produce
    positive NPV
  • This is equivalent to finding the sales level for
    which the cost of the project equals the present
    value of the cash flows

13
Simple Example, based on pp359
  • Victoria Sailboats Limited is considering
    whether to launch its new Mona-class sailboat.
    The selling price would be 40,000 per boat and
    the cost per boat would be 20,000. Fixed costs
    would be 500,000 per year. The total investment
    needed to undertake this project would be 3.5 M
    for factory improvements. This amount will be
    depreciate straight-line over the 5-yr life of
    the equipment. The salvage value is zero, and
    there are no working capital consequences.
    Victoria has 20 required return on new projects.
  • Calculate the NPV break-even ignoring taxes.
  • Calculate the NPV break-even, assuming a tax rate
    of 35.

14
Simple Example, based on pp359
  • The initial investment is 3.5 M
  • Ignoring taxes, the annual OCF is (P-v)Q-FC
    (40,000-20,000)Q- 500,000

15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
Example B
  • Emperors Clothes Fashions can invest 5 million
    in a new plant for producing invisible makeup.
    The plant has an expected life of 5 years, and
    expected sales are 6 million jars of makeup a
    year. Fixed costs are 2 million a year, and
    variable costs are 1 per jar. The product will
    be priced at 2 per jar. The plant will be
    depreciated straight-line over 5 years to a
    salvage value of zero. The opportunity cost of
    capital is 12 and Tc is 40.
  • a) What is the project NPV under the base-case
    assumptions?
  • b) What is the NPV if variable costs turn out to
    be 1.20 per jar?
  • c) At what price per jar would the NPV equal
    zero?
  • d) Whats the NPV break-even sales per year?

19
Example B,Part a)
20
Example B,Part b)
21
Example B,Part c)
22
Example B,Part d)
23
Topic Project Analysis and Evaluation
Objectives
  • Analyze projects with alternative sequential
    decisions and possible outcomes by using decision
    trees
  • Make investment timing decisions
  • Choose between projects with different lives by
    comparing the equivalent annual costs of the
    projects
  • Use equivalent annual costs to decide whether to
    replace an aging machine with a new one

24
Example of a Decision Tree
  • Your midrange guess as to the amount of oil in a
    prospective field is 10 million barrels, but in
    fact there is a 50 percent chance that the amount
    of oil is 15 million barrels, and a 50 percent
    chance of 5 million barrels. If the actual
    amount of oil is 15 million barrels, the present
    value of the cash flows from drilling will be 8
    million. If the amount is only 5 million
    barrels, the present value will be only 2
    million. It costs 3 million to drill the well.
    Suppose that a seismic test that costs 100,000
    can verify the amount of oil in the field. Is it
    worth paying for the test? Use a decision tree
    to justify your answer.

25
Decision Tree
Big oil field (.5)
NPV 8 3 5 million
Test (cost .1m)
NPV 0 (abandon)
Small oil field (.5)
Big oil field (.5)
NPV 8 3 5 million
Do not test
NPV 2 3 - 1 million
Small oil field (.5)
EV(test) -.1M .5x5M .5x0 2.4M EV (no test)
.5x5M .5x(-1) 2.0M
26
Decision Tree - Part II
  • Suppose the probability of the oil field being
    large is p. For what value of p would you be
    indifferent between paying for the test and not
    paying for it?

27
Decision Tree - Part II
EV(test) -.1M px5M (1-p)x0 (5p-.1)M EV (no
test) px5M (1-p)x(-1)M (6p-1)M EV(test)
EV (no test) (5p-.1)M(6p-1)M p0.9
28
Investment Timing Decision
  • When to make an investment is a difficult
    decision in a dynamic world, where new
    cost-saving technology is always improving and
    NPVs are greater if delayed until later.
  • Decision Rule
  • - compute NPVs for each possible year of
    investment
  • - compare NPVs computed all in t 0 values
  • - choose the time that gives the highest NPV0

29
Example on Investment Timing
  • You can purchase an optical scanner today for
    400. The
  • scanner provides benefits worth 60 a year. The
    expected life
  • of the scanner is 10 years. Scanners are
    expected to decrease
  • in price by 20 percent per year. Suppose the
    discount rate is
  • 10. What is the best purchase time?

30
Example on Investment Timing
  • Time Cost PV of Benefits till Purchase
    at Purchase Date
  • 60x(1/.1)x(1-1/1.110)
  • 0 400 368.67
  • 1 320 368.67
  • 2 256 368.67
  • 3 204.8 368.67
  • 4 163.84 368.67
  • 5 131.07 368.67
  • 6 104.86 368.67
  • 7 83.88 368.67

31
Example on Investment Timing
  • Time NPV at NPV at till
    Purchase Purchase Date Time 0
  • 0 -31.33 -31.33 -31.33
  • 1 48.67 48.67/(1.1) 44.25
  • 2 112.67 112.67/(1.1)2 93.12
  • 3 163.87 163.87/(1.1)3 123.12
  • 4 204.83 204.83/(1.1)4 139.90
  • 5 237.60 237.60/(1.1)5 147.53
  • 6 263.81 263.81/(1.1)6 148.91
  • 7 284.79 284.79/(1.1)7 146.14

32
Example on Investment Timing -II
  • How does your answer change when the cost of
    scanners decreases by 50 each year?

33
Example on Investment Timing -II
34
Long-lived versus Short-lived Equipment
  • When comparing mutually exclusive projects that
    have unequal project lives, one must analyze the
    present value of investment outlays and operating
    costs of the projects
  • Decision Rule (between two machines w/ different
    lives)
  • - calculate the equivalent annual cost (EAC) of
    both machines
  • - the equivalent annual cost is the cost per
    period with the same PV as the cost of buying and
    operating a machine
  • - choose the machine with the lowest EAC

35
Example on Long- vs. Short-Lived Machines
  • Suppose your firm must decide which machine to
    buy to produce widgets. Machines A and B have
    identical capacity and do exactly the same job.
    Machine A costs 100,000, lasts 4 years, and
    costs 20,000 per year to operate. Machine B
    costs 75,000, will last only 3 years, and costs
    35,000 per year to operate. Which machine would
    you purchase? The opportunity cost of capital is
    10.

36
Example on Long- vs. Short-Lived Machines
  • PV of costs for A
  • PV of costs for B
  • Why cant we compare A and B yet?

37
To compare costs of projects with different lives
use EAC Project A (life of 4 years) Annuity
factor1-1/1.14/.103.17 EAC163,397/3.1751,5
47 Project B (life of 3 years) Annuity
factor1-1/1.13/.102.49 EAC162,040/2.4965,1
58
38
Replacing an Old Machine
  • Most equipment is replaced before the end of its
    useful economic life. Replacement decisions most
    often involve replacing old by new with different
    useful cash flow lives
  • Decision Rule
  • calculate the EAC of the new project, and compare
    to the period cost of the old project.
  • if the EAC of the new project is less than the
    period cost of the old project, accept the new

39
Example on Replacing an Old Machine
  • Suppose that a new machine has developed and it
    costs 20,000 and its economic life is 3 years.
    The existing machine will last at most for 2 more
    years. The annual operating costs of the two
    machines are given below. Both machines produce
    identical output. The opportunity cost of capital
    is 10. When should you replace the existing
    machine with the new one?
  • Annual Operating Cost
  • Machine 1 2 3
  • Old 10,000 15,000
  • New 4,000 6,000 8,000

40
Example on Replacing an Old Machine
  • The firm has 3 mutually exclusive alternatives
  • Replace immediately
  • Replace in 1 year
  • Replace in 2 years
  • First step compute EACNEW

41
Example on Replacing an Old Machine
  • 1. Immediate replacement (today)
  • 2. Replace in 1 year
  • 3. Replace in 2 years!!

42
Example on Replacing an Old Machine
  • Replace after 1 yr.

43
A Quick Summary
  • Optimal investment timing
  • - Compare the NPV0 of all future NPVs
  • Mutually exclusive equipment with different
    lives
  • - Compare the EACs of the two equipment pieces
  • Replacing an old machine
  • - Compare the EAC of a new machine with the
    period cost of the old machine
Write a Comment
User Comments (0)
About PowerShow.com