Texas Nodal Program Update

Description:

Texas Nodal Program Update Jerry Sullivan – PowerPoint PPT presentation

Number of Views:36
Avg rating:3.0/5.0
Slides: 14
Provided by: erco153
Learn more at: http://www.ercot.com
Category:

less

Write a Comment
User Comments (0)
Transcript and Presenter's Notes

Title: Texas Nodal Program Update


1
Texas Nodal Program Update
  • Jerry Sullivan

2
Agenda
Item Purpose Page
Program Status For Information 3
EMS CSD Status For information 4
User Interface Development Schedule for Market-facing applications For Information and comment 5
Appendix More details on UI Development Schedule For information 8
3
The program has made significant progress on
reducing the backlog of NPRRs to synchronize all
projects
Nodal Delivery
Cost
Schedule
Scope / Quality
Amber
Amber
Amber
Summary
The program is spending under budget through
Mays actuals. Discussions with the ERCOT
Executive Committee outlined possible ways to
ensure we are on budget at completion.
TPTF/PRS approved Baseline 1 on June 12 and
Baseline 2 on June 21. TAC recommended baseline
12 NPRRs on June 28. Program scope can be
declared Green subject to Board approval of NPRRs
for Baseline 1 and 2.
EDS1 and 2 proceeding on schedule. EDS3 approach
approved by TPTF on June 11. There are
schedule risks in Baseline 1 2 which we are
mitigating.
Legend
Estimate at Complete gt263m
Red
Go-live gt30 days
Program is not wholly aligned to protocols
Amber
Estimate at Complete 248 - 263m
Go-live lt30 days
Program is aligned to previous version of
protocols
Green
Estimate at Complete lt248m
Go-live 12/1/08
Program is aligned with current protocols
4
EMS CSD Status Update
  • Provisionally Approved EMS CSD, Ver. 0.11
  • Version Excluding AREVA IP Now Posted Ver.
    0.11a
  • Complete Document Available To MP Employees
  • No NDA Required
  • Contact Stacy Bridges For Immediate Access
  • sbridges_at_ercot.com

5
TPTF have made clear their want for a plan and
consultation to resolve dissatisfaction over the
existing user experience offered by ERCOT
  • To address user experience issues ERCOT has
  • Established User Experience and Visual Design
    Guidelines which contain the user interface (UI)
    Development Process and expected results in style
    and design approach
  • Provided these to the vendors as standards for UI
    for the applications being developed
  • Created a UI design schedule for each Nodal
    project that will be market-facing in the go-live
    market

6
Nodal UI Schedule Summary
Q3
Q2
Q4
2008
Ongoing activity (Design, evaluation)
June
July
August
September
October
November
December
one-time activity (meeting/milestone)
Market Management System
Data collection base product evaluation
Evaluation of revised UI with MPs
Revisions from ABB (Jan)
Validate with MPs (Feb)
Sent to ABB
Validate with MPs
Sent to ABB
With Market Participants (MPs)
Internal
From ABB
Created 2nd design
Validate with MPs
Create initial redesign
Outage Scheduler
Validate with MPs (Feb)
Evaluation of revised UI with MPs
Revisions from ABB (Jan)
Sent to ABB
From ABB
Created 2nd design
Validate with MPs
Revisions from Siemens (Jan)
Network Model Management System
Validate with MPs (Jan)
Sent to Siemens
Prototype Evaluations
Revised UI for PTC expected
Created 2nd design
Validate with MPs
Redesign provided to Siemens (Apr 2007)
Received from Nexant
Congestion Revenue Rights
Data collection base product evaluation
Created initial re-design
Assessment of CRR system w/MPs
Assessment of CRR prototypes w/MPs
Sent to Nexant
Market Information System
Define contents of landing pages
Navigation validation assessment w/MPs
Initial build received from vendor
MIS Validation with MPs
7
Our Long Range Plan
  • Make User Experience an essential element of the
    Change Process
  • Iterative process
  • Evolutionary process
  • Goal directed
  • Form the User Interface Design Council
  • Market Participant focused, extension of MIS
    subgroup
  • Collaborate on designs
  • Provide means for getting feedback
  • Structured
  • System reviews
  • Surveys
  • Unstructured
  • Help Desk ticket analysis
  • Comment Box

8
Texas Nodal Program Update
  • UI Development Schedule
  • Appendix showing each project

9
MMS UI Schedule
  • Data collection and Base product evaluation Jun
    Jul 2007
  • Internal Jun Jul 2007
  • With Market Participants Jul 2007
  • Initial redesign
  • created Jul 2007
  • validated with Market Participants early Aug
    2007
  • sent to ABB Mid Aug 2007
  • from ABB Mid Oct 2007
  • Evaluation of Revised UI with Market
    Participants Oct Nov 2007
  • Second Redesign
  • created Nov 2007
  • validated with Market Participants late Nov 2007
  • sent to ABB early Dec 2007
  • Revisions from ABB Jan 2008
  • Evaluation of Revised UI with Market
    Participants Feb 2008

10
Outage Scheduler UI Schedule
  • Initial Guidance provided tutorial for OS
    system prepared by ERCOT with Market Participants
  • Forms basis for design
  • ABB assessing changes
  • from ABB Mid Oct 2007
  • Evaluation of Revised UI with Market
    Participants Oct Nov 2007
  • Second Redesign
  • created Nov 2007
  • validated with Market Participants late Nov 2007
  • sent to ABB early Dec 2007
  • Revisions from ABB Jan 2008
  • Evaluation of Revised UI with Market
    Participants Feb 2008

11
Network Model Management System UI Schedule
  • Initial Review of Project Tracker (NOMCR
    submission and tracking system
  • Redesign provided to Siemens Apr 2007
  • Evaluation of Revised UI with Market
    Participants
  • Prototype evaluations Jul 2007
  • Revised UI for PTC expected Sep 2007
  • Second Redesign
  • Created Oct 2007
  • Validated with Market Participants late Oct
    2007
  • Sent to Siemens early Nov 2007
  • Revisions from Siemens late Dec 2007
  • Evaluation of Revised UI with Market
    Participants Jan 2008

12
Congestion Revenue Rights UI Schedule
  • Data collection and Base product evaluation Jun
    Jul 2007
  • Initial redesign
  • created Jun 2007
  • sent to Nexant Jun 2007
  • from Nexant Mid Oct 2007
  • Evaluation of Revised UI with Market Participants
  • Using prototypes Aug 2007
  • Using CRR system Oct 2007 (may not have all
    changes implemented)

13
Market Information System UI Schedule
  • Collaborative effort between ERCOT, Market
    Participants, and vendor since mid 2006
  • Initial build of MIS received from vendor Jun
    2007
  • Most links are broken sources not in place yet
  • Define contents of Landing pages with Market
    Participants Jul 2007
  • Navigation Validation assessment with Market
    participants Sep 2007
  • MIS Validation with Market Participants Dec 2008