TriDAS%20Update - PowerPoint PPT Presentation

About This Presentation
Title:

TriDAS%20Update

Description:

USCMS HCAL TriDAS Update Drew Baden University of Maryland http://www.physics.umd.edu/hep/HTR/hcal_may_2003.pdf – PowerPoint PPT presentation

Number of Views:111
Avg rating:3.0/5.0
Slides: 24
Provided by: DanG121
Category:
Tags: 20update | tridas | serdes | test

less

Transcript and Presenter's Notes

Title: TriDAS%20Update


1
USCMS HCAL
  • TriDAS Update
  • Drew Baden
  • University of Maryland
  • http//www.physics.umd.edu/hep/HTR/hcal_may_2003.p
    df

2
FE/DAQ Electronics
S-Link 64 bits _at_ 25 MHz
Trigger Primitives
READ-OUT Crate
Rack CPU
12 HTRs per Readout Crate, 2 DCC
FRONT-END RBX Readout Box (On detector)
HPD
Shield Wall
Fibers at 1.6 Gb/s 3 QIE-channels per fiber
FE MODULE
3
DCC
  • Production boards made
  • Logic boards made
  • Firmware shakedown
  • LRBs made
  • DCC motherboards successfully tested testbeam 2002

4
HTR Principal Functions
  • 1. Receive front-end data for physics running
  • Synchronize optical links
  • Data validation and linearization
  • Form TPGs and transmit to Level 1 at 40 MHz
  • Pipeline data, wait for Level 1 accept
  • Upon receiving L1A
  • Zero suppress, format, transmit to the
    concentrator (no filtering)
  • Handle DAQ synchronization issues (if any)
  • 2. Calibration processing and buffering of
  • Radioactive source calibration data
  • Laser/LED calibration data
  • 3. Support VME data spy monitoring
  • Will adhere to CMS VME64 standards

5
HTR Status
  • Rev 1 run Summer 2002 testbeam
  • Board worked well all functional requirements
    met
  • Big concern on mechanical issues for production
  • Had a difficult experience with previous board
    manufacturing
  • Rev 2 produced March 2003
  • Board production changes
  • New assembler, in-house X-ray, DFM review, QC
  • Gold plated (Rev 1 was white-tin) for better QC
  • Changes to HTR
  • Change from Virtex 1000E FBGA (1.00mm) to Virtex2
    3000 BGA (1.27mm)
  • Added stiffeners
  • Moved all SLB/TPG output to front-panel
    daughterboards
  • Modified Rx refclk scheme (the usual TTC/refclk
    clocking concerns)
  • Full 48 channel capability (Rev 1 was half HTR)
  • As of this date, no issues this board is
    functionally a success

6
HTR Rev 3
  • No more design changes this is the final HTR
  • 30 boards delivered April 21
  • As of Friday (May 2) 12 have gone through final
    checkout
  • All systems except connectivity to SLB
  • Fiber links checked out at 1.7Gbaud bit rate
    (1.6Gbaud is CMS requirement)
  • Frame clock up to 2.0Gbaud bit rate and it stays
    synchronized
  • No BER yetwill do a lab measurement soon
  • 12 boards x 16 links 200 links(5 of total)
    with no problems
  • Minor adjustments will be needed for front
    panels, stiffeners, etc.
  • Will battle test these boards this year
  • Testbeam to begin this month
  • Vertical Slice tests after summer

7
HTR Rev 3 (cont)
8
HCAL Clocking
  • DCC no difficult synchronization issues here
  • For HTR, need 2 different kinds of clocks
  • 1. Synchronized LHC clock for Xilinx system clock
    and SLBs
  • Maintain phase synchronization with entire CMS
    pipeline
  • Allow SLBs to do their job
  • Frequency jitter requirement not critical
  • 2. Precise 2xLHC clock for Deserializer refclk
    ONLY
  • 30-40ps pkpk jitter spec
  • Used ONLY for deserializers
  • Phase synchronicity with LHC clock not important
  • Princeton fanout board will receive TTC, clean up
    clocks with QPLL, fanout signals

9
Princeton Fanout Board
10
Clock Distribution
TTC fiber
O/E
TTCrx
TTC
TTC
TTC
Brdcstlt70gt, BrcstStr, L1A
TTC
.. .. .. ..
.. .. .. ..
BC0
BC0
distribution to 6 SLBs and to 2 Xilinx
Cat6E or Cat7 Cable (very low X-talk)
CLK40
CLK40
CLK80
CLK80
Princeton Clock/TTC Fanout Board
to Ref_CLK of SERDES (TLK2501)
Test Points for RxCLK and RxBC0
80.0789 MHz
.. ..
HTR
11
TTC receiver - TTCumd
  • General purpose TTC receiver board (TTCumd)
  • TTCrx ASIC and associated
  • PMC connectors
  • Will be used to receive TTC signal by HTR, DCC,
    and clock fanout boards
  • No signal receivers!
  • Copper/fiber receivers must be on the motherboard
  • Signal driven through TTC connectors
  • Tested successfully by Maryland, Princeton, BU
    groups

12
HTR Integration Goals 2003
  • Continued development of HTR firmware
  • Commission TPG path
  • Firmware, LUTs, synchronization, SLB output
  • Monitoring, error reporting, etc. (information
    sent to DCC)
  • Testbeam May 2003
  • Support calibration effort and continue
    commissioning the system
  • Run synchronously in May
  • Vertical slice tests, Fall 03
  • Fully pipelined, monitoring, TPG, DAQ,
    synchronization, clocking.
  • Develop software to support DAQ activities
  • Testbeam software improvements
  • Princeton group built testbeam DAQ
  • Software for commissioning
  • Allow us to verify fiber mapping
  • Download LUTs, firmware version, etc.

13
HCAL TPG
  • Under development
  • Preliminary FPGA code for TPGs done
  • LUT for linearization (downloadable), 0.5GeV
    steps, 255Gev max ET
  • E to ET and sums over as many as 7 channels
  • Not implemented in code yetTBD
  • Muon window in E
  • BCID filter algorithm TBD from testbeams
  • Compression LUTs for output to SLBs
  • Utilization is 50 of Virtex2 3000
  • We are confident this chip will be sufficient
  • Simulation effort under way
  • Latency issue
  • See below we are working on this

14
HTR Production
  • Full contingent of HTRs 260 boards
  • Includes 10 spares, 20 spares for parts
  • Full production will begin after
  • Testbeam demonstrates I/O works under battle
    conditions
  • Successful testing of the 6 SLB daughter card
    functions
  • Understanding of how to meet latency issues
  • We are still some clock ticks short, but
    firmware is still very immature for the TPG part
    of the HTR (see slides below)
  • If all goes wellsometime this summer or fall
  • There is no reason to hurry other than to finish
    with the RD part of the project
  • We are confident that the current board design
    will be final

15
Overall Commissioning Schedule
  • Summer 2003 testbeam
  • Repeat previous test w/production prototype
    boards
  • Fall 2003 Slice tests
  • HCAL will join as schedule allows
  • 2003/2004 HCAL burn-in
  • Continue with firmware development/integration as
    needed
  • 2004/2005 Vertical Slice and magnet test
  • We will be ready
  • All HCAL TriDas production cards involved
  • October 05 beneficial occupancy of USC
  • Installation of all racks, crates, and cards
  • We do not anticipate any hardware integration
  • Should be all firmware / timing / troubleshooting

16
ESR Review Item 1
  • Use of an obsolete TI component for the data
    link receiver
  • Misconception on the part of the committee
  • TI TLK2501 is NOT obsolete.
  • This is a Gigabit ethernet transceiver.
  • There is no reason to believe TI will stop making
    these parts.
  • If they do, someone will make something else
    compatible.
  • Stratos receivers are also NOT obsolete.
  • Dual receivers are out of favor, Transceivers are
    in favor
  • What is obsolete is our 99/part. If we need
    more, they will charge 133/part (or more)

17
ESR Review Item 2
  • The random latency problem that comes with using
    the 8bit/10bit link protocol
  • The random latency has to do with the TI Serdes
    function
  • Two clocks here incoming data clock and
    reference clock
  • Serdes part has an internal asynchronous FIFO to
    implement 8B/10B protocol
  • But this is NOT the fault of the protocol!
  • Any protocol which includes a clock, to be
    recovered, will have this.
  • TI does have a 2-3 clock tick random latency with
    50 probability for 2 or 3
  • We can use VME controllable reset and comparison
    to achieve the 2 clock tick lesser latency
  • Can readout SLBs and use relative latency to
    correct pointers
  • Can use FE BC0 signals

18
ESR Review Item 3
  • Routing of large no. of stiff cables to the
    front of the HTRs versus other configurations
    such as a transition module
  • Transition module is NOT POSSIBLE. Forget about
    this.
  • Would cost us 6 months at least (time and
    engineering )
  • Strain relief
  • Each HCAL rack will have 2 VME 9U crates
  • Each 9U crate will have an accompanying 6U strain
    relief panel
  • Changing to 15m quad cables (from 20m 2xdual
    Wesley cables) will greatly reduce torques on
    SLB cards
  • We will test these cables this summer need
    Wisconsin Vitesse test setup
  • Each SLB card will be attached to the HTR front
    panel, and screwed into HTR motherboard
  • We believe this will work fine.

19
ESR Review Item 4
  • Ensuring appropriate quality assurance and
    testing at the HTR board fabrication facility
  • We agree, this is a big worry.
  • Have used new high-tech assembler for Rev 3
    (pre-production)
  • Note almost any assembler will have startup
    issues
  • Overall techniques are more important than QA,
    which comes after the fact
  • We have chosen an assembler with very modern (and
    expensive) equipment.
  • An engineering review by the assembler is
    included in the assembly cost
  • Our biggest problem was fine-line BGA (1.0 mm
    pitch) implementation
  • Current version uses standard 1.27mm pitch BGA
  • Given current experience, we believe we have
    solved this

20
ESR Review Item 5
  • Providing sufficient FPGA excess capability
    against possible future enhancements to the
    firmware
  • HTR FPGA change Virtex/1000E to Virtex2/3000
  • Current firmware uses
  • 83 of all RAM resources
  • FIFOs, LUTs, etc. this will not change
  • 50 of all Logic resources
  • Room for more logic
  • Room for more memory (can use distributed memory)
  • The sky is not the limit, but we think were ok
    here
  • Firmware has evolved quite far thanks to Tullio
    Grassis efforts

21
ESR Review Item 6
  • Minimizing the trigger latency

Item Latency
TOF .5
HCAL Optics 1
FE (CCAQIE) 8-9
GOL 2
Fiber Tx to HTRs 18
Deserializer 2-3
HTR Alignment 6
HTR TPG path 5-10
SLB 3
TPG Cables 4
TOTAL 50 - 57
  • Current total 50 57 clocks
  • Very rough guesses
  • Many numbers have not been measured
  • Optimizations
  • Fiber cables need to be 90m?
  • HTR firmware needs optimization
  • Deserializer random latency fix
  • TPG cables changed to 15m will save 1 tick
  • Othersmain efforts over next 6 months

22
TPG Path
L1 Filter
Sum in ET
INPUT LUT Lineariz. and Et
ETcomp
Compression LUT
TP
Sum Consecutive Time-samples
ET90
QIE-data
10
10
7
10
Muon LUT
Peak Detection
Muon bit
2
1
Mask Reset
NO-SHOWER LUT take care of cases where showers
can leak into a cell and incorrectly set the
muon bit.
BCID
Delay to synchronize with BCID
2
2
2
2
BCID avoids to flag as a muon the tail of a more
energetic event
23
Other ESR Concerns
  • Reliability/maintenance
  • Replacement of HTRs not an issue HTRs not in
    hi-rad region
  • Data link error detection
  • Not difficult to implement, just requires
    coordination.
  • Under consideration, schemes are evolving,
    dealing with e.g.
  • Loss of synch
  • Trigger acceptance violations
  • Buffer overflow (actual and warnings so DCC can
    cause L1 to throttle)
  • Use of BC0 from front end
  • Inline pedestal determination
  • Zero suppression
  • DAQ format
Write a Comment
User Comments (0)
About PowerShow.com