Risk Assignment in The Delivery of a Project - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Risk Assignment in The Delivery of a Project

Description:

Risk Assignment in The Delivery of a Project RISK! Construction projects have lot of it Contractors manage it Owners pay for it – PowerPoint PPT presentation

Number of Views:204
Avg rating:3.0/5.0
Slides: 22
Provided by: Univers222
Category:

less

Transcript and Presenter's Notes

Title: Risk Assignment in The Delivery of a Project


1
Risk Assignment in The Delivery of a Project
  • RISK!
  • Construction projects have lot of it
  • Contractors manage it
  • Owners pay for it

2
FACT
  • Todays owner is placing more demands on designer
    constructor to get job done.
  • ON TIME
  • ON BUDGET
  • WITHOUT UNANTICIPATED CHANGES
  • FAILURE TO SATISFY ANY OF THE ABOVE IS CONSIDERED
    RISK AND CAN OFTEN CAUSE FINANCIAL PENALTY
    AND/OR LIQUIDATED DAMAGES

3
FACT
  • Traditionally, owners seek to minimize their risk
    through the contract
  • They like to allocate the majority of the risk to
    others, depending on the contract type
  • Construction Manager
  • Prime Contractor
  • Multiple Primes, etc

4
RESULT
  • project participants develop strategies to
    minimize their own financial risk
  • inflate job costs to cover potential loss
  • seeking reimbursement for insurance costs
    associated with excessive or owner-imposed risks
  • FINAL EFFECT HIGHER ULTIMATE
    JOB COST TO OWNER

5
Risk
  • Risk is inherent to the construction process
  • If risk is managed through assignment to the
    team member most able to manage it..
  • Owner
  • Designer
  • Contractor
  • then risk can be shared in a manner that
    results in reduction of the job cost.

6
Why Owners Should be Concerned with Risk
Allocation
  • If unexpected risk is experienced that causes
    financial loss
  • Adversarial relationships develop
  • Time/energy/money is wasted on disputes and
    claims
  • Focus of the team is lost to get the job done
    right, on time on budget

7
Origin of Risk
  • Many risks are common to all projects
  • Time delays
  • Overruns
  • The amount by which actual costs exceed estimates
  • Unexpected changes
  • Other risks are very specific to type of
    construction and/or location of the project

8
Examples of Risk
  • Who is responsible for the acquisition of
    easements?
  • What happens if theres an archaeological
    discovery?
  • What if environmental hazardous waste is
    encountered?
  • Subsurface conditions may vary from those
    expected.
  • Late or unsuitable owner furnished materials may
    cause a time delay.

9
Risk Allocation
  • The process of identifying project risks is
  • Determining how risks may be equitably shared by
    all parties
  • Develop dispute avoidance techniques
  • The result is more project for the money

10
Benefits to The Owner
  • Costly disputes are minimized
  • Avoids
  • unexpected delays added job costs
  • WHY?
  • Contractors are able to avoid addition of
    contingencies in the bid
  • contingency money is fluff money added for
    the WHAT IF situation.
  • Contractors are not saddled with having to
    recognize, anticipate and cost risk which may
    be unfairly allocated to them
  • If risk issues are dealt with in advance, owner
    will realize a price advantage.

11
Benefits to the Contractor
  • When uncertainties are minimized and specific
    risk is allocated
  • Contractor can submit more competitive bids
  • Lower contingencies
  • Disputes litigation avoided

12
Benefits To The Project
  • Shortened project delivery
  • Minimal resources allocated to conflict
    resolution
  • Owner, designer contractor realize a
    partnership relationship

13
What is The Owners Role In Allocating Risk?
  • Willingness
  • to share project risk
  • to be realistic in terms conditions
  • to become educated regarding potential problems
    with the project
  • to make educated risk allocation decisions
    approve necessary contract procedures

14
Basic Principles of Risk Allocation
  • Identify risk as specifically and early as
    possible
  • Risk Sharing
  • Contractually place risk upon parties according
    the their ability to
  • Minimize it
  • Handle the potential risk if it occurs

15
Example
  • Sharing risk due to unusually severe weather
  • Typical boilerplate AIA contract clause grants
    contractor the right to a time extension, but
    does not provide additional compensation for the
    costs incurred as a result.
  • THIS IS A FINANCIAL RISK ASSUMED BY THE
    CONTRACTOR DUE TO LOSS OF WORK TIME
  • HOWEVER, the Owner assumes risk of delay in
    progress/completion (no liquidated damages or
    penalty may be assessed)
  • This is an example of risk sharing

16
What Owners are Doing To Better Allocate Risk
Reduce Project Costs
  • Thorough front-end document review
  • Include a dispute resolution system in the
    General Conditions or Supplementary Conditions
  • Use of AIA or EJCDC documents which do the above

17
What Owners are Doing To Better Allocate Risk
Reduce Project Costs
  • Owners SHOULD invest in subsurface investigation
  • Boring logs should be available to contractors
    during bidding process
  • results in more competitive bid
  • Some owners think this may lead to claims if
    the logs dont accurately identify all
    encountered conditions.
  • BUT IT IS APPROPRIATE THAT THE OWNER PAY FOR
    THESE CHANGED CONDITIONS IF ENCOUNTERED!

18
What Owners are Doing To Better Allocate Risk
Reduce Project Costs
  • Quality Design
  • Comprehensive and complete design effort
  • Multidisciplinary Constructability Review
  • Owner (functionality)
  • Contractor (builders perspective)
  • Design Professional (quality of design)

19
What Owners are Doing To Better Allocate Risk
Reduce Project Costs
  • Adequate funding of
  • Pre-design surveys
  • Investigation of rite-of-way easement issues
  • Investigation if site access issues
  • THESE SOFT ENGINEERING ISSUES MAKE A
    DIFFERENCE IN PREPARATION OF ADEQUATE,
    RESPONSIBLE AND COMPLETE BID PRICING

20
The Importance of the Contract
  • Focal point should be risk allocation
  • Importance cannot be over-emphasized
  • Ideally, the contract will
  • Clearly identify risks and responsibilities
    associated with the project
  • Assign risks to party best equipped to manage them

21
In The End
  • The Contract will
  • Serve as framework of the legal agreement between
    the parties
  • Establish which party has assumed what risk
  • Be significant in defining the duties of each
    party
Write a Comment
User Comments (0)
About PowerShow.com