Title: Task%20Group%204%20Low%20Rate%20WPANS%20Closing%20Report
1Project IEEE P802.15 Working Group for Wireless
Personal Area Networks (WPANs) Submission Title
Task Group 4 Low Rate WPANS Closing
Report Date Submitted January 16th -
2003 Source José A. Gutierrez Company
Eaton Corp Address 4201 North 27th Street
Milwaukee WI. 53005 Voice414-4496525, FAX
414-4496131, E-Mailjosegutierrez_at_eaton.com R
e Closing Report from Ft. Lauderdale Meeting
Abstract A summary of the comment resolution
activities for Sponsor Ballot, status and plan
for IEEE802.15 Task Group 4 Purpose Closing
Report - Ft. Lauderdale Meeting Notice This
document has been prepared to assist the IEEE
P802.15. It is offered as a basis for discussion
and is not binding on the contributing
individual(s) or organization(s). The material in
this document is subject to change in form and
content after further study. The contributor(s)
reserve(s) the right to add, amend or withdraw
material contained herein. Release The
contributor acknowledges and accepts that this
contribution becomes the property of IEEE and may
be made publicly available by P802.15.
2Task Group 4 Low Rate WPANSClosing Report
- Ft. Lauderdale, FL
- January 17, 2003
3Task Group 4 Low Rate WPANS
- TASK GROUP 4 OBJECTIVES FOR THIS MEETING
- 1. Comment Resolution for Sponsor Ballot
- 2. Planning for Sponsor Ballot recirculation
- 3. Planning for miscellaneous TG4 activities
- 4. Objectives for Dallas Meeting
4Task Group 4 Low Rate WPANS
Sponsor Ballot Results
365 Comments
88.7 Participation!
5Sponsor Ballot
6Sponsor Ballot
7Sponsor Ballot
8(No Transcript)
9TG4 Performance
Projected!
100
97.9
10Comment Resolution Progress
Done!
11Revised Draft Almost Done!
- Need to implement final 12 Technical Comment
Resolutions (resolutions have been agreed upon
and documented) and various editorial comment
resolutions
12WG Motion
- Move that the 802.15 WG approve the comment
resolutions to the P802.15.4/D17 draft standard
and further that the 802.15 WG empower the TG4
editing team to implement all of the comment
resolutions in compliance with the stated
resolutions in the 03010r0P802-1_TG4-meeting-minut
es to form the P802.15.4/D18 draft standard. - Moved by Jose Gutierrez
- Seconded by Phil Jamieson
- Vote results
13When are we planning to go to recirculation? Late
-February
14Technical Editing Team Focus
- Implementing Comment Resolution
- Go to sponsor ballot re-circulation
15Activities Roadmap
February 27th 10 Days Recirculation
March - 14th Comment Resolution Done
March 20th RevCom Review
Late March PARTY!
16- Goals for Dallas - 2003
- Sponsor Ballot recirculation comment resolution
- Final Edits to Draft 19
- Preparation for RevCom
17Task Group 4 Low Rate WPANS
Project Timeline
18Summary
- Sponsor Ballot with 97.9 approval
- Editorial comment resolution finished
- Draft 18 ready by Mid-February
- Recirculation planned for late February
- Anticipated release planned for March-2003