Endcap%20assembly%20update - PowerPoint PPT Presentation

About This Presentation
Title:

Endcap%20assembly%20update

Description:

Endcap assembly update C Buttar UK-SCT-MB RAL 2nd Sept 04 – PowerPoint PPT presentation

Number of Views:110
Avg rating:3.0/5.0
Slides: 20
Provided by: Craig384
Category:

less

Transcript and Presenter's Notes

Title: Endcap%20assembly%20update


1
Endcap assembly update
  • C Buttar
  • UK-SCT-MB RAL 2nd Sept 04

2
Nikhef disk? cylinder assembly tooling
3
Service Handling
LMT trays
4
Disk insertion tooling
5
Disk?cylinder tooling
  • Shielding foil added to cylinder
  • Thermal feedthrough prepared
  • Cylinder and stub wings assembled onto tooling
  • 4 disk alignment tools being made by Manchester?
    delivered to Liverpool
  • Disk grabber-design by Nikhef-manufactured by
    Sheffield/Lancaster tested with a diskCCDs and
    lighting now added and tested
  • Disk fixations from Nikhef and Liverpool-delivered
  • alignmenttarget holders designed (Nikhef) and
    manufactured (Lancaster)z-alignment tool needs
    to be finished
  • Still to do..
  • Qualify disk-grabber and disk alignment
  • How to mount and de-mount the central beam
  • concept ready, need to test

6
Cylinder?tooling
  • Pre-aligment of rear stub wing mounting point
  • Rear stub wing mounted onto frame
  • Cylinder placed over beam and left on table with
    foam supports
  • Cylinder bolted to rear stub-wing
  • front wing offered up using sling for support and
    mounted
  • Disk placed on disk grabber and cylinder aligned
  • Disk moved through cylinder
  • Very useful exercise! - lots of details to be
    sorted/have been sorted

7
(No Transcript)
8
Disk?cylinder insertion
  • Capture and align a disk
  • need to consider disk masses

9
(No Transcript)
10
Service status
  • LMTsTesting of UK tapes at GlasgowPreparation
    of LMTs before assembly into trays?JT
  • TIsWill be tested as part of LMT-TI harness at
    GlasgowFirst 100 delivered, full order soon
  • String test LV/HV?test cable?TPPC?TI?LMT?PPF0?wi
    ggly tape?hybrid/module at Liverpool
  • FibresLancaster has volunteered to take on
    reception testingFibres for disk testing (D1D2)
    at Liverpool, D9 at the end of Aug (?)
  • Cooling pipesNow too late to assemble cooling on
    cylinder at Liverpool, now retro-fitted at CERN
    ?Assume no cooling pipes initially and connect
    direct to disk as for disk testing, then connect
    at STFT if pipes are delivered

11
TPPC string test (J.VoosebeldP.Dervan)
  • String test
  • Test cable ?TPPC?TI?LMT harness?PPF0?wiggly tape
    ?hybrid

TPP-C String-test on single channel test board
complete TPP-C ordered, string test on 32
channel pre prod board (1ch only) completetry
and do 2ch test ? (need additional LMT)
12
Service handling
  • Thermal plug ordered and being manufactured in
    Sheffield (caravans!)
  • PPF1 trays for LMTs in production
  • PPF1 tray holdersorder placed last week-being
    modified
  • temporary PPF1 for fibresLancaster have
    volunteered to make this, awaiting design from
    NikhefAt Liverpool we need to ensure we can
    connect in the coldroom
  • Cooling-replicate disk testing system and connect
    direct to the disk-or similar
  • re-evaluate when cooling pipes/connects start to
    be available

13
Test cable installation
  • Test Cables for endcap testing installation
    startedRay Thompson, Andy Elvin, Richard French
  • Basic mapping ready

14
Thermal plug
15
Status, going forward
  • Assembly tooling is ready needs to be tested
  • cylinder mounted and disk moved through on the
    beam
  • Still to do
  • test run of disk alignment, capture and
    removaldone but need disk masses
  • Z-alignment tool
  • Removal and insertion of the beam
  • interface to disk holder
  • floor, bracing and wheels, move in and out of
    cold room
  • scaffolding for working on the cylinder

16
Status, going forward
  • Service handling is progressing
  • thermal plug being assembled
  • LMT trays and tray holders in production
  • Still to do
  • DCS to be investigated
  • Fibre holder design to be finalised
  • Cooling, connect direct to disks at Liverpool,
    otherwise interfaces must be defined now to allow
    disk insertiontesting to go forward? assume HEX
    that we connect to disks/pipes at STFT so no
    longer need cooling pipes in service
    handling-how to make connections in the cold
    room-design manifold?? replicate disk test
    system and connect to disks
  • Need services (LMTsFibres) to start developing
    methods for putting services on
  • what tooling is required
  • how to make test-fibre connections !

17
Status, going forward
  • Developing tests for disk?cylinder assembly
  • test cooling on disk with services
  • during assembly to check connectionseg LMTs,
    check thermistors on modules
  • Similar tests to those made on populated disks

18
DAQ/DCS
  • PSU system
  • 2 Artysyn power packs / shelves received
    installed.
  • Original batch of LV/HV cards installed.
  • Dummy load fabricated to allow testing of each
    channel. Testing of 6 channels completed.
  • Readout and display disk thermal sensors
  • DAQ
  • 2 Rev E RODs installed.
  • 5 hybrids 1 module mounted on disk 9 in cold
    room for multi-module readout tests (NB.
    Convective cooling to 0C room only).

19
Cooling plant
  • Cooling Plant
  • Manifold re-located to cold room, re-connected
    tested with 3kW load OK.
  • Interlock using DCS from cooling pipes being
    developed
Write a Comment
User Comments (0)
About PowerShow.com