Title: The Power Sector in the Russian Far East: Recent Status and Plans
1The Power Sector in the Russian Far East Recent
Status and Plans
- Ruslan GULIDOV
- Economic Research Institute, FEB, RAS
- Alexander OGNEV
- Vostokenergo Far Eastern Branch of InterRAO
-
2007 Asian Energy Security Project
Meeting Energy Futures and Energy Cooperation in
the Northeast Asia Region Tsinghua University,
China October 31 November 2, 2007
2Outline
- Restructuring Program in Russia
- Particular Features of Electricity Restructuring
in the Russian Far East - Electricity Demand Supply Trends in the Region
- Electricity Export Projects Status and Prospects
- Russias and the RFE Nuclear Status and Plans in
Brief
3Electric Power Restructuring in Russia
- Decision on Completion of Electric Power
Restructuring was adopted by Government and
Stakeholders (October 2007) - Vertically-Integrated System of Electricity
Supply has been already divided into competitive
(generation, sale) and monopolistic
(transmission, dispatching) sectors - National Power Company RAO UES of Russia will
be finally restructured and liquidated by July
2008 - Governmental control will be keeping on Federal
Grid company, Central Dispatching company,
Hydro-OGK, Rosenergoatom (nuclear) and some other
entities
4RFEs Features
- Vast territory (7 mln sq. km), uneven economic
development, low population (6.3 mln) - No economic and technical opportunities to have
unified power grid (UPG) in the region - UPG operates only within the Southern part of
the Russian Far East
5Particular Features of RFEs Electricity
Restructuring
- After discussions it has been recognized that
there is no conditions for electric power
competition in the RFE (at least) during
transition period to the electricity market - Duration of transition period is keeping
uncertain - Two types of electricity market are currently in
operation in the RFE - Single Producer is in remote, separate districts
in northern areas - Single Buyer market is in UPG zone
- Decision made that all operating companies
(including generation and sale) are kept under
the federal government control (52 and more) for
a while - Electricity export contracts and development of
export infrastructure have been appointed to
national single operator InterRAO Close
Corporation
6Electricity Supply Demand Trends and Plans
- Positive dynamics of economic activity (4.6 p.a.
over 2000-2006) - Low growth rate of electricity consumption (4.3
totally in 2000-2006) - Electric power generation capacities are
increasing - 4th unit at Khabarovskya CHP-3 (180 MW,
Dec.2006), 5th and 6th units at Bureyskaya HPP
(670 MW, June Oct. 2007) were commissioned - Blagoveschenskaya CHP, Komsomolskaya CHP-3,
Khabarovskaya CHP-2 to be expanded - New TPPs in Sov.Gavan (Khabarovskiy Krai) and
in the south of Primorskiy Krai to be constructed
- Shifting in primary energy production mix
- Khabarovskaya CHP-1, Khabarovskaya CHP-2
? Nikolaevskaya CHP to be switched to
natural gas - Network strengthening in the Southern part of the
RFE - Investments in power grid totaled 0.9 bln over
2001-2006 - Investment programs approved in fuel-fired
electricity generation and transmission lines
3.8 bln over 2008-2015
7Elect. consumption in Russia and the RFE
overview and outlook
Russian Federation
Max Path 2006-2010 6.0, 2011-2015 4.9,
2016-2020 4.6 Base Path 2006-2010 4.9,
2011-2015 3.6, 2016-2020 3.7
Bln kWh
The Russian Far East
Max Path 2006-2010 3.8, 2011-2015 7.7,
2016-2020 9.0 Base Path 2006-2010 2.4,
2011-2015 4.2, 2016-2020 6.5
Bln kWh
8Capacity Additions in the RFE Base Scenario
2006-2010 2006-2010 2011-2015 2011-2015 2016-2020 2016-2020
GW GW GW
NPPs - - - - 0,7 18,4
HPPs 1,2 80,0 1,0 15,6 2,2 57,9
TPPs, including 0,3 20,0 5,4 84,4 0,9 23,7
coal-fired 0,3 20,0 4,3 67,2 0,5 13,2
gas-fired - - 1,1 17,2 0,4 10,5
Total 1,5 100,0 6,4 100,0 3,8 100,0
- Source General Plan for Electric Power Industry
up to 2020
9Installed Capacity and Production Structure by
Feedstock (Base Scenario)
Installed Capacity
2006
2020
GW
0.05
0.7
NPPs
32.5
36.8
4.0
8.7
44.5
HPPs
51.3
6.3
10.4
TPPs (coal)
0.4
15.8
2.0
3.7
TPPs (gas)
2.9
15.8
12.3
23.5
Production
2020
2006
Bln kWh
0.1
1.7
NPPs
32.6
13.1
33.5
HPPs
56.2
22.6
50.4
TPPs (coal)
10.9
4.4
12.3
0.3
TPPs (gas)
40.2
97.9
10Electricity Border Trade with
China
- Three inter-state power transmission lines
(110-220kV) currently exists to supply
electricity from the RFE (Amurskaya Oblast) to
Northeast China (as of 2006 0.5 bln kWh) - In 2003 Russian InterRAO and Chinese "Sirius"
signed a Framework Agreement on electricity
supplies of 13 billion kWh over 2004-2013 - Border trade has a history of 12 years but are so
far controversial issue - export contracts does not include short and
long-term price formula - contract duration is one year, once a year
finished a new one-year contract to be concluded
- an export price used to be lower than that for
domestic consumers - Since February 2007 China Russia border trade
has been suspended due to electricity price
disagreements
11Large-Scale Electricity Export from Russia to
China
- In November 2006 Joint Pre-Feasibility Study of
the project of large-scale electric supply from
Eastern Russia to China was prepared. Capital
costs 18 bln. Phases are - 2008-2012 the expansion of the frontier
electricity trade by 3.6-4.5 bln kWh annually (a
500 kV line will be built to Heilongjiang) - 2012-2015 two coal-fired TPP (totally 3.6 GW)
to be commissioned in the RFE so that to expand
annual electricity export up to 22.5 bln kWh (a
500 kV line will be built to Liaoning) - After 2015 to build coal-fired 7.2 GW in the
RFE and Eastern Siberia so that to enlarge annual
export up to 60.0 bln kWh (a 800 kV line will be
built to Beijing area) - In November 2006 the contract for deliveries in
the frame of the 1st stage of the project was
signed
12Large-Scale Electricity Export from Russia to
China
Notation Conventions
Thermal Power Plant
DC Power Line
AC Power Line
AC/ DC Converter
13Prospects for DPRK Russia Electricity Trade
Background
- ROK DPRK RFE electricity interconnections
were being under discussions at various levels in
2001-2004 - Project profile considered was as follows
- construction of 500kV AC Transmission Line
Vladivostok - Chongiin (200 mln) - DC Transmission Line 500-600 kV Vladivostok
Seoul - Due to some political and economic reasons the
discussions was suspended
Russia DPRK 500 kV transmission line
suggested, 380 km
Chongiin
Extension to the border with ROK 900 km,
?500-600 kV
14Prospects for DPRK Russia Electricity Trade
Current Status
- Since 2007 favorable conditions are being emerged
to recover RFE DPRK interconnection project - APEC 2012 Summit in Vladivostok will require the
construction of generation and transmission
facilities (TPP, SS, TL) - new electricity demand aroused in the area of
DPRK Russia border - DPRK RFE railroad section planned
- two ports of Primorskiy Krai (Poset and
Zarubino) applied for more power to consume - crude oil export terminal project and expansion
of seaport in RaSon FEZ - Political support of the project from DPRK
Russia Intergovernmental Commission (4th Meeting
in Moscow, March 19-23, 2007) - Real prospects of electricity demand and
political conditions make RFE DPRK
interconnection project commercially viable
15Russias Nuclear Power Sector
The Russian Far East Bilibinskaya NPP 4x12 MW,
138.4 thous. kWh 130.8 Gcal
- Russia 10 NPPs, 31 power units with total
capacity of 23,2 GW (11 that of Russia),
electricity production of 154.8 bln kWh (16 that
of Russia), 5 of nuclear energy fraction in
Russias TPES (as of 2006) - 15 PWR (9 VVER-1000 6 VVER-440)
- 15 Channel Boiling Reactors (11 RMBK-1000 4
EGP-6) - 1 Fast Neutron Reactor BN-600
16Bilibinskaya NPP CHP
- Single small Russias NPP of public utility
- Provides 30 of electricity heat supplies in
Chukotka, 0.4 of those in the RFE - Actual Capacity Factor 32.5, MCF 79
- 4 EGP-12 reactors (G-I) were commissioned over
1974-1976
- Lifetime period of the units as designed had to
be completed in 2004-2006 - After auditing the lifetime period was prolonged
up to 2009/2010/2016 (subject to unit) - Based on the Federal Program on Nuclear Energy
Sector Development up to 2015 it is scheduled to
decommission BNPP over 2019-2021
17Outlook for Nuclear Energy Development in Russia
Expansion and Decommissioning Projections
Nuclear Generation Projection
Source General Plan for Electric Power Industry
up to 2020 Note All projections are based on
Rosenergoatom Company capabilities
18Nuclear Energy Development in the
RFE Background
- In 1980s, early 1990s a range of projects and
intentions to site some NPPs in the Russias Far
East was under discussion - Nuclear Energy Inland Area in Primorskiy Krai (2
NPPs of firstly 1.28 then 2.56 GW each and
NPP-CHP of 1.28 GW 6.4 GW as combined) - Nuclear Energy Coastal Area in Primorskiy Krai
(NPP of firstly 1.28 GW, then 2.56 GW as well as
2 NPPs of 2.56 GW each 11.52 GW) - Nuclear Energy Area in Khabarovskiy Krai (NPP of
2.56 GW each and NPP-CHP of 1.28 GW 3.84 GW as
combined) - Sitting Small Floating NPPs in many territories
of North, Northeast Russia - In reality only two NPP was under consideration
- The Feasibility Study was done for Far Eastern
NPP (Khabarovskiy Krai) with 2.56 GW (4 VVER
-640) (1994) - The Pre-Feasibility Study was done for
Primorskaya NPP with 2.56 GW (4 VVER-640) (1996)
19Nuclear Energy Development in the
RFE Current Status
- Based on General Plan for Electric Power Industry
up to 2020 it is planned to construct two NPPs in
the RFE over 2016-2020 - Pevekskaya Floating NPP with 70 MW (KLT-40S) to
replace Bilibinskaya NPP in Chukotskiy Autonomous
Okrug - Primorskaya NPP with 600 MW (2 x VBER-300) to
meet the increase in domestic power electricity
demand - Primorskaya NPP could be constructed by IPP to
supply New aluminum plant planned in Primorskiy
Krai - Up to 2016 in Russia it is planned to produce 7
KLT floating reactors. Probably more than one of
them will be sited in the Northern territories of
the RFE
20Thank you for attention!
- Dr. Ruslan Gulidov,
- Economic Research Institute, FEB, RAS
- Khabarovsk, Russia
- gulidov_at_ecrin.ru
- Dr. Alexavder Ognev
- Vostokenergo Far Eastern Branch, InterRAO
Close Corporation - oay1_at_mail.ru