Title: 2011 Educational Facilities Master Plan
12011 Educational Facilities Master Plan
- Presentation to the
- Board of Education
- June 13, 2011
2Educational Facilities Master Plan
- Section I Mission, Standards, and Guidelines
- Educational Programs and Policies
- Section II Community Analysis
- Growth and Demographics Information
- Section III Facilities Inventory
- Building Assessment and Inventory of Facilities
- Section IV Enrollment Projections
- 2010 Enrollment Projections
- Section V Facility Utilization and Needs
- Long-Range Planning and Timeline of Capital
Projects - Section VI Letters of Approval
- State /County Enrollment and Master Plan Approval
Letters
3Project Categories
- C Capacity Projects
- M Modernization Projects
- B Building/Program Improvement Projects
- S Site/Program Improvement Projects
- Evaluation of existing buildings and sites to
both modernize and expand - Master planning to maximize the land we own
4Parameters For Decision Making
- State and Local Funding Approvals
- Educational Facilities Master Plan
- Cross-functional Steering Committee
- Balancing Enrollment
- Capacity, Infrastructure, Program Projects
5Status of Projects
- Red Pump ES - Occupancy August 2011
- Homestead/Wakefield ES - Scope Study Approved by
BOE - John Archer School Addition - Scope Study
Approved by BOE - Youths Benefit ES - Construction Documents
Complete - William Paca/Old Post ES - Scope Study Approved
by BOE - Campus Hills ES - Construction Documents
Complete - Joppatowne HS - Scope Study Approved by BOE
6Occupancy Time Changes from 2010 Plan
- Homestead/Wakefield ES - No Change (SY15-16)
- John Archer School - No Change (SY15-16)
- Youths Benefit ES - No Change (SY16-17)
- William Paca/Old Post ES - Change (SY16-17 to
SY17-18) - Campus Hills ES - Change (SY16-17 to SY18-19)
- Joppatowne HS - Change (SY18-19 to SY20-21)
7FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011
Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects
FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22
PROJECTS - STATE/LOCAL 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22
Red Pump Elementary School (SRC 696) C/O
Homestead/Wakefield ES Modernization/Addition (SRC 1029) P C C C/O
John Archer School Addition at Bel Air School (SRC 200) P C C C/O
Youth's Benefit Replacement School (SRC 1130) P C C C/O
8FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011
Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects
FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22
PROJECTS - STATE/LOCAL 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22
WP/OPR Elementary Replacement School (SRC 1154) P C C C/O
Campus Hills Elementary School (SRC 696) P C C/O
Joppatowne High School Comprehensive Addition Modernization (SRC 1475) P C C C/O
9FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011 FACILITIES PLANNING MASTER PLAN 2011
Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects Construction Timeline - Capacity, Modernization and Addition Projects
FY12 FY13 FY14 FY15 FY16 FY17 FY18 FY19 FY20 FY21 FY22
PROJECTS - STATE/LOCAL 11-12 12-13 13-14 14-15 15-16 16-17 17-18 18-19 19-20 20-21 21-22
Existing John Archer School Modernization/Renovation SS P C C/O
New Middle School Cap TBD SS P C C/O
Riverside ES Modernization SS P C C/O
Bel Air MS Modernization SS P C C/O
Magnolia ES Modernization SS P C C/O
GD Lisby ES Modernization SS P C
WS James ES Modernization SS C
Prospect Mill ES Modernization SS
Aberdeen MS Modernization
Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement Abbreviation Key - SS Scope Study, FS State Required Feasibility Study, P Planning and Design, C Construction, O Occupancy SFR State Funding Reimbursement
10Questions Discussion