Description:

Nuclear Power Turkey Point Power Plant Process Turkey Point Power Plant Built on 12, 700 acres in Homestead Opened in 1972 Cost to build both reactors $235,000,000.00 ... – PowerPoint PPT presentation

Number of Views:238
Avg rating:3.0/5.0
Slides: 21
Provided by: 19585
Category:
Tags: nuclear | power | reactor

less

Transcript and Presenter's Notes

Title: Nuclear Power


1
Nuclear Power
  • Turkey Point Power Plant Process

2
Turkey Point Power Plant
  • Built on 12, 700 acres in Homestead
  • Opened in 1972
  • Cost to build both reactors 235,000,000.00
  • Employs 680 workers

3
Nuclear Energy
  • Fission releases the energy
  • Radiation is a product of this energy release
  • Three types of radiation are Alpha, Beta and
    Gamma
  • We are exposed to about 360 mRems of radiation
    annually

4
Nuclear Energy
5
Primary System
  • Reactor Vessel
  • 8 thick,
  • 40 tall
  • 13 diameter
  • 635,000 lbs.
  • operating pressure 2,235 psi
  • operating temperature 600 degrees F

6
Primary System
  • Reactor Vessel

7
Primary System
  • Reactor Core
  • Fuel Pellets
  • .5 long
  • .5 wide
  • Fuel Rods
  • 12 tall
  • 328 pellets per rod
  • 204 rods per assembly
  • Fuel Assemblies
  • 13 tall, 8 square wide, 1,300 lbs., 157
    assemblies per core, replaced every 18 months

8
Primary System
  • Reactor Core Pellets and Rods

9
Primary System
  • Reactor Core Fuel Assemblies

10
Primary System
  • Reactor Core

11
Secondary System
  • Steam Generators
  • 3 per reactor vessel
  • 63 tall
  • Turbine and Generator
  • Steam pressure applied 785 psi
  • 1,800 rpm
  • Generators connected to shaft produce 693 Mwatts
  • Condenser
  • Condenses steam after used returns to steam
    generator at 13,00 gallons per minute

12
Secondary System
  • Steam Generator

13
Secondary System
  • Turbine and Generator

14
Tertiary System
  • Water from the canals cools steam running through
    turbines and condenses it
  • Enters plant at a rate of 156,000 gallons per
    min.
  • Leaves plant at same rate
  • Takes 48 hours to travel 150 miles of canals to
    cool off
  • Pumps water back to the steam generators 13,000
    gallons per min.

15
Tertiary System
  • Canals

16
Containment Buildings
  • Houses the Primary and Part of the Secondary
    Systems
  • 210 tall
  • 124 in diameter
  • 4 walls of iron reinforced concrete
  • 10 deep foundation

17
Containment Buildings
18
Spent Fuel Pools
  • Used fuel assemblies are stored
  • 41 long
  • 39 deep
  • Wall thickness 3-6 feet
  • Stores up to 1,376 assemblies

19
Spent Fuel Pools
20
Overview of Process
Write a Comment