Title: CSR Charts
1GLAST Large Area Telescope ISOC Peer Review
Section 7.1 Pre Launch Operations and
Calibrations Eduardo do Couto e Silva Manager
of the Science Verification Analysis and
Calibration Department of IT Subsystem
2Outline
- Connection between IT/SVAC and ISOC/SOG
- IT/SVAC Requirements
- Examples of IT/SVAC activities
- Lessons Learned from IT/SVAC
- Examples of preliminary data analysis
- Summary
3Connection between SVAC/IT and SOG/ISOC
- The Science Verification Analysis and
Calibration (SVAC) Department of the IT
subsystem will gradually transition into the
Science Operations Group of the ISOC. - The main responsibilities of the SVAC Department
are - Coordinate Data Analysis for Science Verification
- Perform final pre launch calibrations
- Perform first in-flight calibrations prior to
hand off to ISOC/SOG (see talk in section 7.2) - Deliver calibration products to ISOC/SOG
4IT Pre Launch Experience with EM
- The Science Operations Group (SOG) has been
recently created and does not yet have all of its
documentation in place - In this talk we will present an overview of the
IT/SVAC experience using the Engineering Model
(EM) test as an example of the activities that
will be performed by the SOG during mission
operations - The lessons learned on following items will be
discussed - Documentation
- Data Processing
- Operations
- Calibrations
- Data Analysis
5Science Verification, Analysis and Calibration
(SVAC) Plan
Science and Calibration requirements from
Subsystems Plans were captured in LAT-MD-00446
Science Requirement Document
443-SRD-00010
LAT Performance Specifications
LAT-SS-00010
Level II Levels III and IV Level III
LAT-SS-00016, LAT-SS-00017 LAT-SS-00018,
LAT-SS-00152, LAT-SS-00210
ACD, CAL, TKR Specifications
GLAST LAT SVAC Plan
LAT-MD-00446
Calibration
Data Analysis
Science Verification
6 SVAC Plans and Technical Documents
LAT-MD-00446 LAT-MD-01587 LAT-MD-00613
LEVEL III
Co-owned with Systems Engineering
Contributed Manpower Plan
Co-owned with Project Scientist
LEVEL IV
Existing docs are shown in red boldface
Hardware Test Plan/Results Calibrations
Simulations Databases Interfaces
Engineering Model EM
LAT-MD-00573 LAT-TD-01588
LAT-TD-00582 LAT-TD-00578 LAT-TD-00571
LAT-TD-01593
LAT-TD-01340
LAT-MD-00575 LAT-TD-01590 SAS
responsibility LAT-TD-00580 LAT-TD-00573
LAT
LAT-MD-00576
LAT-MD-00577
LAT-MD-00581
Co owned with Instrument Operations Center
LAT-TD-01595
At this time we are reviewing the EM documents
and lessons learned to produce the necessary
documentation for the LAT Integration
7Level III Documents - Contents
Co owned with Systems Engineering
Co owned with Project Scientist
- LAT-MD-00446 - SVAC Plan
- Instrument Calibrations
- SVAC Compliance
- Pre Launch Test Matrix
- Post Launch Test Matrix
- LAT-MD-01587 SVAC Test Requirements Plan
- Hardware Required
- Flight Software Required
- Test Configuration
- EGSE Required
- MGSE Required
- Test Software
- Support Instrumentation
- Test Data Record
- Data Format
- Test Products
- Analysis Activities
- Environmental Conditions
- Test performance Procedures
- Facility Requirements
- Quality Program Performance Requirements
- System Assurance Requirements
- Test Equipment Calibration
Contributed Manpower Plan
- LAT-MD-00613 - SVAC Plan
- Engineering Model
- TKR,CAL,SAS
- Calibration Unit
- ACD,TKR,CAL,SAS,IOC
- LAT
- ACD,TKR,CAL,SAS,IOC
8Level IV Technical Documents Contents
- Test Plan/Results
- LAT-MD-00573 SVAC EM Plan
- Describes the hardware data taking
configurations, infrastructure needed for
calibrations, calibration types, data analysis
requirements. Run time estimation using MC
simulation - LAT-MD-01593 SVAC Results from the Engineering
Model Test - Describes the results and how requirements were
met - Calibrations
- LAT-TD-01588 Calibration Algorithms for the
Engineering Model - Describes the calibration algorithms developed in
conjunction with SAS and subsystems - Simulations
- LAT-TD-00582 EM Geometry for the Monte Carlo
Simulation - Describes the geometry used in the simulation,
includes table to translate nomenclature from
software developers to engineers and also
contains traceability - Database
- LAT-TD-00578 SVAC Database for the Engineering
Model - Describes the table schema and how a web based
engine will allow access to a subset of
calibration data for the purpose of tracking
changes in time. - Interfaces
- LAT-TD-00571 SVAC/SAS Interface Control
Document - Describes the responsibilities between SAS and
SVAC for data analysis (Statement of work) - LAT-TD-01340 SAS Calibration Infrastructure
- Describes SAS calibration infrastructure that
holds the primary calibration data
Using Engineering Model as an example
9Documentation Lessons Learned
- EM Lessons Learned
- Lots of documents and not enough time for people
to read them (i.e., less than optimal feedback
from subsystems) - In some cases ideas were discussed in details but
were not mature enough to be implemented (e.g. EM
database) - Difficult to keep up with update needs given the
manpower limitations within IT - For SOG
- Documentation shall be kept at a level that is
adequate to guide planning while allowing for
technical reviews - Interfaces need more attention and shall be more
detail oriented
10Data Analysis Chain
GENERAL USER
11Data Processing Lessons Learned
- EM Lessons Learned
- Data transfer was tedious and was partially
automated - Reprocessing of data occurred more often than
expected - The Information about datasets necessary for data
analysis was not available through a user
friendly interface (despite our planning!) - For SOG
- Fix communication problems between interfaces and
devise system tests to minimize needs to
reprocess data - Investigate with SAS how to automate Data
Processing - Create better requirements to implement database
queries
12Calibrations Lessons Learned
- EM Lessons Learned
- In some cases procedures were developed on the
fly (not a serious impact since we did not have
to deal with many software versions) - IT was not directly involved in all calibrations
- For SOG
- Implement better configuration control of data
and procedures to produce data - Develop sufficient expertise within SOG to handle
all possible calibrations - Understand better requirements for interfaces
with FSW
13Operations Lessons Learned
- EM Lessons Learned
- In some cases it was difficult to determine the
data taking configuration - Not all information was available during data
taking - New configurations were added during the data
taking period without adequate planning - For SOG
- Implement better user guides and operator
training - Develop a process to critically review
operational procedures and to address unscheduled
configuration changes - Understand interface with FSW
14EM Ground Calibration Set-up
Cosmic Background
Not a monochromatic beam!
Gammas66 17.6 MeV
34 14.6 MeV, FWHM 1.5 MeV
lots of electrons
Beam pipe
CAL
TKR
Electrons are produced by gamma conversions in
the iron shield in front of the accelerator
15 CAL Energy Spectrum
Preliminary
Photon Source OFF
From Gary Godfrey
Photon Source ON
Mostly photons
Energy (MeV)
16Source Calibration
Preliminary
From Gary Godfrey
Expect two energy lines
17Flux Measurement
Preliminary
9 of the of photons produced by the source are
measured by the EM
Top TKR face
Extrapolation to Photon Source
From Gary Godfrey
10 error is dominated by the knowledge on the
BGO position
EM Rec Direction cosine In 0.02 bins
18Energy Measurement
IDs are described in LAT-MD-00446
Calibrations
Data Analysis
19EM Energy Spectrum (VDG DATA)
Preliminary
Event selection nTkrTracksgt1 zDir lt -0.9 (25
deg from vertical) maxCalgt4MeV
From Xin Chen
Expected g Spectrum Delta function (17.6
MeV) Breit-Wigner (mean 14.5, width1.5MeV)
Energy (MeV)
20Energy Spectrum (VDG MC)
Preliminary
Event selection nTkrTracksgt1 zDir lt -0.9 (25
deg from vertical) maxCalgt4MeV
From Xin Chen
Events converted in top layer of Tracker only
Expected g Spectrum Delta function (17.6
MeV) Breit-Wigner (mean 14.5, width1.5MeV)
Energy (MeV)
21Data Analysis Lessons Learned
- EM Lessons Learned
- Expected experimental backgrounds were not
thoroughly studied prior to the test - Some algorithms and pieces of the offline
software were not validated prior to the data
taking period - Calibrations took longer than expected
- For SOG
- Develop with SAS, IT and LAT Collaboration tools
for instrument and sky simulations to address
needs of first-year operations - Develop better communications across interfaces
and sharpen calibration requirements
22Summary
- Lessons Learned
- The IT/SVAC group will revisit all EM technical
issues to ensure a successful LAT integration.
IT/SVAC will participate in the planning process
to build the infrastructure required for the SOG
during the IT integration - Concerns
- More discussions and planning are needed to
address how the operational procedures and
calibrations exercised during Integration will be
adapted to the Flight Software environment (not
present during EM)