Where We Go Wrong - With Compressors - PowerPoint PPT Presentation

1 / 34
About This Presentation
Title:

Where We Go Wrong - With Compressors

Description:

Steam driver mass balances Hot gas turbine mass ... Problems The following are some of the problems found in compressor design and operation. The compressor ... – PowerPoint PPT presentation

Number of Views:123
Avg rating:3.0/5.0
Slides: 35
Provided by: Dick133
Category:

less

Transcript and Presenter's Notes

Title: Where We Go Wrong - With Compressors


1
Where We Go Wrong - With Compressors
  • Dick Hawrelak
  • Presented to ES-317y in 1999 at UWO

2
Introduction
  • 5 of large property damage losses are caused by
    failures in pumps and compressors.
  • When a major failure takes place, the average
    trended Loss is 19.2MM.
  • C3H6 compressor,driver spares in a world scale
    ethylene plant costs 17MM purchased.

3
Compressors Costs FS LHC1
  • Cost Summary By Elliott RAH Estimated
  • CG K-201/K-321 17,239,800 17,472,331
  • Propylene K-601 8,667,000 6,674,797
  • Ethylene K-651 6,014,000 5,478,011
  • 31,920,800 29,625,139
  • 1.077 1.000

4
Compressor Problems
  • The following are some of the problems found in
    compressor design and operation.
  • The compressor train includes compressors,
    drivers, KO Pots, exchangers and storage vessels.

5
ComplexCompSystemsCan BeFoundIn
AnEthylenePlant
6
Mass Balance Problems
  • Process start-up, shut down or upset conditions
    not well defined.
  • Refrigerant mass balances.
  • Steam driver mass balances
  • Hot gas turbine mass balance.
  • Designers did not consider all problems
    associated with recycle for turn-down or
    false-load conditions.

7
Typical Steam Balance
8
Pressure / Temperature
  • Operating points not well located.
  • Poor data from the field.
  • Poor data is useless for determining compressor
    performance.

9
Interstage Conditions
  • If low stage pressure drops are higher than
    designed, final stage discharge pressure may not
    be achieved.
  • See NCOMP example for demonstration.

10
NCOMP Results
11
Discharge Conditions
  • Discharge temperatures higher than allowable
    limits. Indicates lower efficiency and pending
    trouble.
  • See NCOMP example for demonstration.

12
Composition
  • Actual plant feed stock differs from design feed
    stock.
  • Condensate compositions differ from one oil field
    to another.
  • Design for 100 ethane cracking but operate with
    mixed HC feeds.

13
Physical Properties
  • Vendor and customer did not agree on physical
    properties.
  • Non-ideal vapor / liquid systems.
  • VCM plant operates at 50 of capacity.

14
Vendor Offering
  • Vendors often quote unusually high compressor
    efficiency to try and win the contract.
  • Many customers are gullible enough to swallow the
    offering.
  • Difficult to pin vendor down on final
    performance. Too many degrees of wiggle freedom.

15
Follow-up
  • Customer fails to up-date material and energy
    balance after vendor shop tests confirm projected
    adiabatic compression efficiency.

16
Prototypes
  • Customer accepts vendor prototype offering with
    blind faith.
  • Ford Edsel example.

17
Spare Parts
  • Customer fails to request a spare rotor. 6 months
    to fabricate.
  • Customer orders a spare rotor but stores it
    incorrectly.
  • Rotor must be balanced in a coffin, turned
    regularly and the coffin nitrogen purged under
    positive pressure.

18
Shop Tests
  • Customer goes the cheap route and specifies only
    a one point shop test.
  • Customer fails to witness construction and final
    shop test.

19
Fabrication
  • Customer accepts vendor without shop visit.
  • Poor fabrication techniques.

20
Interstage Seals
  • Poor seal selection.
  • Mechanical seal.
  • Hot gas seal.
  • Water seal.

21
Vibrations
  • Vendor fails to identify all critical speeds.
  • Vendor makes a poor vibration corrections.
  • Poor vibration monitors and trip system.

22
Bearings
  • Poor fabrication.
  • Poor alignment.
  • Poor maintenance.

23
Anti-surge Control
  • High vibrations on approaching stonewall point.
  • Anti-surge control does not respond as required.

24
Shut-down Trip Systems
  • Cheap trip systems do not identify what tripped
    the compressor by a first out diagnostics trip
    system.
  • Poor trip systems do not permit good diagnostics
    following a compressor trip.

25
Lube Oil Systems
  • Insufficient lube oil reservoir capacity for
    roll-down.
  • Lube oil lines not cleaned before start-up.
  • Poor lube oil supply.
  • Non union lube oil system reassembled by local
    union.

26
Field Inspection
  • Customer fails to inspect lines after contractor
    finishes job.
  • Contractor hammer wrecks compressor on start-up.

27
Compressor Gears
  • Poor gear design.
  • High noise.
  • Poor alignment on maintenance.
  • Poor lubrication.

28
Compressor Configuration
  • Over-hung lines on compressors are poor for
    maintenance.
  • Bottom-hung lines on compressors are good for
    maintenance but require taller compressor
    building.

29
Typical Configuration
30
3 Case C3H6 Compressor
31
Foundations
  • Poor soil bearing tests fail to disclose soil
    loading problems.
  • Compressor experiences settling.
  • Alignment suffers and compressor wrecks.
  • One project manager doubles all foundation
    specifications to be on the safe side.

32
Inlet Piping
  • Inlet lines too small.
  • Inlet vanes do not receive design flow due to
    poor flow distribution.

33
Driver Selection
  • Electrical motor.
  • Diesel motor.
  • Gas turbines.
  • Steam turbines.
  • Drivers require as much attention as the
    compressor.

34
Possible Exam Questions
  • In a multi-stage compressor, if the low stage
    pressure drops are higher than designed, how will
    the final final discharge pressure be affected?
  • What is the problem of running a compressor with
    a very high discharge temperature?
  • Why do we install vibration monitors and high
    vibration trips on centrifugal compressors?
Write a Comment
User Comments (0)
About PowerShow.com