Title: BME/CompE/EE/ME 297 Senior Design Seminar Contracts
1BME/CompE/EE/ME 297 Senior Design Seminar
Contracts Contract Management
Andrew W. Dozier FGH 249
2System Life Cycle
- In order to discuss contracts and contract
management, it is necessary to understand where
in the system life cycle contracting is used - Typically, project engineers get involved at
various phases of a system development - Front end studies
- System Engineering
- Development
- Production
- Fielded systems
- Logistics, maintenance and support
3Front End Studies
- Typically, the customer has an existing system
that they want to advance to current state of the
art - A significant amount of work is required to
define and refine the requirements for the new
system - The only deliverable is a paper study, with no
delivery or performance requirement - This requires a different contract type from
later system development phases - Time and Material
4Later Phases
- As system development proceeds the number of
unknown unknowns diminishes - This implies that the risk of performance on the
contract diminishes with each advancing phase - As before, the contract type changes
- Cost reimbursable
- Fixed price
- Time and material (again)
5Contract Life Cycle
- Each phase of development typically is competed
and awarded incrementally - This allows the customer to deal with differences
in implementation risk via the contract type used - Typical phases
- Requirements Development
- Prototype/breadboard development
- First article production
- Low rate initial production
- Production
- Life cycle support
- Each development phase goes through the same
process
6Contract Development
- Request for Proposal
- Includes contract type, or form
- Proposal development
- Cost/Schedule
- Technical
- Data/deliverables
- Factfinding
- Negotiations
- Best and Final Offer (BAFO)
- Award
- Performance
- Closeout
7Estimating
- Estimating takes place at the time of the
proposal for each phase, and includes an estimate
of the following - Time phased cost
- Direct labor
- Direct material
- Overhead
- General and Administrative Expenses
- The sum of cost and GA equals your cost through
GA - The above defines your breakeven point
- Please note that this is based on your cost
estimate, not what you end up spending on a
project - Actual cost can vary significantly from the
estimate
8Contract Negotiations
- The customer spends a lot of time understanding
what is contained in the proposal, also known as
factfinding - After factfinding, a final iteration of the
contract cost and fee is generated - The idea is to define the cost and the fee
for the entire project - The price of the contract equals cost plus fee
- Based on the final submittal by all competitors,
an award is granted - There are a variety of incentives available to
the customer based on the type of contract - Cost reimbursable
- Fixed price
- Time and Material
9Direct Material and Labor
- The term Direct implies that both the labor
hours expended and the material utilized in
accomplishing the project is incorporated into
the deliverable product - Consider a building/construction project
- Direct Material and Labor do not include the cost
of the contractors facilities, rent, utilities,
etc. - These items are included in the Overhead that
is applied to the cost of Direct Material and
Labor - The cost of direct material and labor does
include employee benefits, the cost of buyer
labor to procure material, etc.
10Typical Overhead Items
- Direct Labor would include
- Vacation pay
- Sick pay
- Insurance
- FICA
- Direct Material would include
- Cost of shipping
- Buyers to purchase the material and their overhead
11How are Overhead Rates Calculated?
- By an accounting methodology that conforms to the
Federal Accounting Standards Board (FASB) for
government contracts, and generally acceptable
accounting practices for commercial companies - The approach may vary from Company to Company
- Overhead does not include Wheat Tax or the cost
of non-direct labor - Supervisors, department heads, executives, etc.
- Also referred to as Indirect cost
- Overhead does include the Cost of Doing Business
12Overhead Rate Calculation Example
13Methods for Apportioning Overhead
14Application of O/H, G A, and Profit
15Definition of a Contract
- A bilateral agreement between two business
entities to do something in the future for
Consideration - The giving party is the Customer (or Buyer, or
Client) - Receiving party is the Contractor (or Seller)
- The contractor can subcontract work to other
companies and individuals - However, the contractor is still responsible for
contract performance - Typically, this decision is made by going through
a make vs. buy analysis - All contracts are governed by the Uniform
Commercial Code of the United States - A body of law
16Contractual Relationships
- Interactions between business entities are based
on Common Law - Ultimately, contracts are administered by the
Federal and State Government if a dispute arises - Court of Claims
- Settlement of Contract Disputes
- Court of Patent Appeals
- Settlement of Intellectual Property Disputes
17Consideration
- Consideration is provided to the contractor upon
successful completion of the contract terms - Consider the following scenario
- Contractor builds a building, pays for all labor,
subcontractors, and material suppliers - Contractor delivers the finished building with a
perfect title. - Owner gives the contractor money as consideration
- All contracts and changes to contracts have
consideration - Consideration can take forms other than money,
such as schedule relief, technical performance
relief, etc.
18Requirements for the Creation of a Contract
- In order to establish a contract, a mutual
understanding as to what each business entity
will give and receive must be defined - Consideration
- Cost and fee
- Deliverable items and data
- Technical performance of deliverables
- Schedule
- Tasks (work) to be performed
- If you dont have all of the above items defined,
you do not have an executable contract
19Requirements for the Creation of a Contract
(contd)
- The contractor makes an offer to the customer
(Proposal) - Can be a written or verbal offer, or an offer
created by other acts of communication by
responsible officers of the seller - Fax, email?
- Contractor defines the period within which the
proposal will be honored - Customer enters into negotiations by issuing a
letter of acceptance - The offer must be revoked in writing if something
happens that requires withdrawal of the offer
prior to expiration - The offer defines all cost, schedule, and
technical requirements - Factfinding then takes place with the customer
team - Negotiations are then held to clarify items in
the proposal, and to state the customers
perception of the should cost
20Requirements for the Creation of a Contract
(contd)
- The customer then counteroffers to the seller to
converge differences in understanding - This can take multiple iterations
- Customer then generates a Best and Final Offer,
or BAFO - This is then either accepted by the performer
(seller) or the seller takes a hike - If the offer is accepted, a contract is generated
which incorporates all of the final changes, and
everyone signs it - The signators must be able to legally obligate
the business - Typically, signators would be officers of the
company with a delegated signature authority
greater than the value of the contract - This could be many 100 Million
21Requirements for the Creation of a Contract
(contd)
- Upon everyones signature, the project starts
- The seller is under contract to perform in
accordance with the final negotiated document
22Contract Changes
- Things happen during the course of the project
that change either the amount of work (), or
the schedule - A formal change process is incorporated into all
contracts - Unilateral Change
- Imposed by the Customer on the Contractor without
concurrance - Constructive Change
- Failure by the Customer to meet contractual
requirement, ie. Breach of Contract - Bilateral Change
- Mutually agreed to change between the Customer
and Contractor - Unilateral and Constructive Changes generally
result in a Dispute
23Disputes and Breaches
- Unilateral changes are typically not acceptable
to the Contractor - Consideration is insufficient
- Need more money to do the additional work
- Impossible to perform to changed schedule,
performance, etc. - A breach of contract occurs when the Customer or
the Contractor fail to meet the requirements of
the contract - Failure to provide Customer Furnished Equipment,
Facilities, etc. - Failure to deliver on time
24Dispute Resolution
- Negotiations are required by all parties to
resolve disputes - Contract letters and supporting documentation are
very important in order to document the situation
and position of both parties - Getting ready to go to trial
- Lawyers get involved
- Generally very unproductive and expensive
- Not worth the effort for less than 10K on a
large job - Disputes must eventually adjudicated by the Court
of Claims, which requires a legal trial - This is a very expensive process
25Termination
- Contract Termination is possible under certain
pre-negotiated conditions - Termination for Convenience of the Government
- Termination is also possible for failure to meet
Contract requirements - Cost, Schedule, or Technical Performance
- Termination for Cause
- Termination for Default
- Termination clauses are always included as a part
of the original Contract
26Termination (contd)
- Termination for cause allows the customer to
re-procure the item at the expense of the
original contractor! - This is extremely serious and can bankrupt a
company - Termination for convenience requires a
Termination Proposal, which is then negotiated
like a new contract - Material purchased is packaged and turned over to
the customer - Subcontracts must also be terminated
- Costs associated with early termination of
employees are included - Layoff notification, etc.
27Contract Concepts
- Different contract types are available
- The contract type selected must be based upon a
mutual understanding of the risk of success of
the project - If the customer is incorrect with regard to their
perception of risk, than there should be no
bidders on the contract - Success is defined as the achievement of all
contract objectives Cost, Schedule, Performance - Improper utilization of a contract type can, and
does frequently result in project failure - All contracts provide a concept of Profit or
Fee - Related to consideration
- Generally, the fee equals funds left over at
contract completion, and after closeout
28Contract Concepts (contd)
- Residual materials or equipment are not included
in the final profit - Sold as surplus and credited to overhead
- Delivered to Customer
- Profit percentage varies with the type of
contract, ie. cost reimbursable or fixed price
The residual funds can be negative!!
29Types of Contracts
- Fixed Price
- Cost Reimburseable
- Time and Material
30Fixed Price Contracts
- Highest risk to Seller. Used for low risk
procurements. - Three Types
- Fixed Fee (FFP)
- Incentive Fee (FPIF)
- Fixed Price with Redertimination (FPR)
31Firm Fixed Price Contracts (FFP)
- Fixed profit, no ceiling price
- Exceptions
- Constructive Changes
- Unilateral Changes
- Definition of Change subject to interpretation
- Generally used as negotiating tool
- Customer has upper hand by withholding of funds
- Can overrun! Can also have costs disallowed.
32Fixed Price Incentive Fee (FPIF)
- Lower Risk to Seller, fee determined by targets
- Ceiling Price
- Cost/Profit Sharing
- Incentive Curve
- 30/70 Share for Underrunns
- 70/30 Share for Overruns
- Still subject to Changes Clause
- Can receive minimal or no profit and overrun!
- Customer can also disallow costs.
33Fixed Price with Redetermination (FPR)
- Two types Prospective and Retroactive
- Prospective FPR negotiates prices to be paid in a
prospective period - Similar to two FFP arrangements negotiated at
stated times during contract performance period - Retroactive FPR provides for adjusting price
after performance - Essentially like FPIF
- Maximizes Project Managers attention on happines
of Customer
34Cost Reimbursable Contracts
- Lower Risk to Seller than Fixed Price Contracts
- Used for higher risk procurements
- Uncertainty of performance goals, etc.
- Three Types
- Fixed Fee (CPFF)
- Incentive Fee (CPIF)
- Award Fee (CPAF)
35Cost Plus Fixed Fee (CPFF)
- Fixed profit, no renegotiation of contract
allowed - No ceiling price
- Exceptions
- Constructive Changes
- Unilateral Changes
- Definition of Change subject to interpretation
- Generally used as negotiating tool
- Customer has upper hand by withholding of funds
- All Costs are paid
- Subject to interpretation as to Allowable cost
36Cost Plus Fixed Fee (contd)
- If project overruns at cost, no increase in fee
(lower profit margin) - If project underruns at cost, higher profit
margin achieved - Can overrun, but will always make a profit
37Cost Plus Incentive Fee (CPIF)
- Lower Risk to Seller
- Established Targets (Cost, Schedule, Performance)
- Cost/Profit Sharing
- Incentive Curve
- 30/70 Share for Underrunns
- 70/30 Share for Overruns
- Still subject to Changes Clause
- Can overrun and still make a profit subject to
the Incentive Curve
38Cost Plus Award Fee (CPAF)
- Fee determined by Customer via award criteria
- No rules regarding Award Criteria
- Typical targets established
- Responsiveness to Customer
- Cost/Schedule Controls, etc.
- Completely dependent on Grade of Customer.
- Can receive 0 profit, but will always be
reimbursed for costs - Maximizes Project Managers attention on
happiness of Customer
39Time and Material Contracts
- Lowest risk to Seller. Generally used for
studies with indeterminate outcome, or support,
operational or maintenance contracts. - Not to Exceed Contract for labor and material
- Task orders from Customer are negotiated with
Seller - Defines effort for small tasks
- Minimizes any cost uncertainty
40Cost/Fee Examples
Note In the following slides, the price to
the customer equals the sum of the profit and
cost.
41Firm Fixed Price (FFP)
42Fixed Price Incentive Firm Target (FPIF)
43Cost Plus Fixed Fee (CPFF)
44Cost Plus Incentive Fee (CPIF)
45Elements of a Contract
- Contract Form
- Schedule
- Statement of Work (SOW)
- Deliverables
- Contract Data Requirements
- Contract Data Requirements List
- Specifications
46Contract Form
- Document which provides all contractual details
- Type of Contract
- Total Cost
- Deliverables/Services and Prices
- Packaging and Marking
- Inspection and Acceptance
- Contract Clauses and Administration Data
- List of Documents, Exhibits
- Representations and Certifications
47Contract Form (contd)
- Technically, Schedule and SOW are part of
Contract - Generally referenced in body of Contract Form
- No Schedule or Technical Information. Cost only!
48Schedule
- Time phased tasks and deliverables which are
detailed in SOW, Supplies List, and CDRL - Generally identical to the proposed schedule,
with modifications resulting from negotiations - No Cost or Technical Information. Schedule only!
49Statement of Work
- Details all tasks and activities to be
accomplished on Contract - References the following documents
- Contract Data Requirements
- Contract Data Requirements List (CDRL)
- Deliverable Items
- Specifications
- Defines all design activities, documentation,
etc. - No Cost or Schedule Information. Technical Only!
50Other Topics of Interest
- Government Acquisition Regulations
- DARS/FARS
- Government Contracting vs. Commercial Contracting
- Estimating/Scheduling Methodology
- Work Planning
- Specification Development and System Engineering