BME/CompE/EE/ME 297 Senior Design Seminar Contracts - PowerPoint PPT Presentation

1 / 50
About This Presentation
Title:

BME/CompE/EE/ME 297 Senior Design Seminar Contracts

Description:

BME/CompE/EE/ME 297 Senior Design Seminar Contracts & Contract Management Andrew W. Dozier FGH 249 – PowerPoint PPT presentation

Number of Views:117
Avg rating:3.0/5.0
Slides: 51
Provided by: AndyD157
Category:

less

Transcript and Presenter's Notes

Title: BME/CompE/EE/ME 297 Senior Design Seminar Contracts


1
BME/CompE/EE/ME 297 Senior Design Seminar
Contracts Contract Management
Andrew W. Dozier FGH 249
2
System Life Cycle
  • In order to discuss contracts and contract
    management, it is necessary to understand where
    in the system life cycle contracting is used
  • Typically, project engineers get involved at
    various phases of a system development
  • Front end studies
  • System Engineering
  • Development
  • Production
  • Fielded systems
  • Logistics, maintenance and support

3
Front End Studies
  • Typically, the customer has an existing system
    that they want to advance to current state of the
    art
  • A significant amount of work is required to
    define and refine the requirements for the new
    system
  • The only deliverable is a paper study, with no
    delivery or performance requirement
  • This requires a different contract type from
    later system development phases
  • Time and Material

4
Later Phases
  • As system development proceeds the number of
    unknown unknowns diminishes
  • This implies that the risk of performance on the
    contract diminishes with each advancing phase
  • As before, the contract type changes
  • Cost reimbursable
  • Fixed price
  • Time and material (again)

5
Contract Life Cycle
  • Each phase of development typically is competed
    and awarded incrementally
  • This allows the customer to deal with differences
    in implementation risk via the contract type used
  • Typical phases
  • Requirements Development
  • Prototype/breadboard development
  • First article production
  • Low rate initial production
  • Production
  • Life cycle support
  • Each development phase goes through the same
    process

6
Contract Development
  • Request for Proposal
  • Includes contract type, or form
  • Proposal development
  • Cost/Schedule
  • Technical
  • Data/deliverables
  • Factfinding
  • Negotiations
  • Best and Final Offer (BAFO)
  • Award
  • Performance
  • Closeout

7
Estimating
  • Estimating takes place at the time of the
    proposal for each phase, and includes an estimate
    of the following
  • Time phased cost
  • Direct labor
  • Direct material
  • Overhead
  • General and Administrative Expenses
  • The sum of cost and GA equals your cost through
    GA
  • The above defines your breakeven point
  • Please note that this is based on your cost
    estimate, not what you end up spending on a
    project
  • Actual cost can vary significantly from the
    estimate

8
Contract Negotiations
  • The customer spends a lot of time understanding
    what is contained in the proposal, also known as
    factfinding
  • After factfinding, a final iteration of the
    contract cost and fee is generated
  • The idea is to define the cost and the fee
    for the entire project
  • The price of the contract equals cost plus fee
  • Based on the final submittal by all competitors,
    an award is granted
  • There are a variety of incentives available to
    the customer based on the type of contract
  • Cost reimbursable
  • Fixed price
  • Time and Material

9
Direct Material and Labor
  • The term Direct implies that both the labor
    hours expended and the material utilized in
    accomplishing the project is incorporated into
    the deliverable product
  • Consider a building/construction project
  • Direct Material and Labor do not include the cost
    of the contractors facilities, rent, utilities,
    etc.
  • These items are included in the Overhead that
    is applied to the cost of Direct Material and
    Labor
  • The cost of direct material and labor does
    include employee benefits, the cost of buyer
    labor to procure material, etc.

10
Typical Overhead Items
  • Direct Labor would include
  • Vacation pay
  • Sick pay
  • Insurance
  • FICA
  • Direct Material would include
  • Cost of shipping
  • Buyers to purchase the material and their overhead

11
How are Overhead Rates Calculated?
  • By an accounting methodology that conforms to the
    Federal Accounting Standards Board (FASB) for
    government contracts, and generally acceptable
    accounting practices for commercial companies
  • The approach may vary from Company to Company
  • Overhead does not include Wheat Tax or the cost
    of non-direct labor
  • Supervisors, department heads, executives, etc.
  • Also referred to as Indirect cost
  • Overhead does include the Cost of Doing Business

12
Overhead Rate Calculation Example
13
Methods for Apportioning Overhead
14
Application of O/H, G A, and Profit
15
Definition of a Contract
  • A bilateral agreement between two business
    entities to do something in the future for
    Consideration
  • The giving party is the Customer (or Buyer, or
    Client)
  • Receiving party is the Contractor (or Seller)
  • The contractor can subcontract work to other
    companies and individuals
  • However, the contractor is still responsible for
    contract performance
  • Typically, this decision is made by going through
    a make vs. buy analysis
  • All contracts are governed by the Uniform
    Commercial Code of the United States
  • A body of law

16
Contractual Relationships
  • Interactions between business entities are based
    on Common Law
  • Ultimately, contracts are administered by the
    Federal and State Government if a dispute arises
  • Court of Claims
  • Settlement of Contract Disputes
  • Court of Patent Appeals
  • Settlement of Intellectual Property Disputes

17
Consideration
  • Consideration is provided to the contractor upon
    successful completion of the contract terms
  • Consider the following scenario
  • Contractor builds a building, pays for all labor,
    subcontractors, and material suppliers
  • Contractor delivers the finished building with a
    perfect title.
  • Owner gives the contractor money as consideration
  • All contracts and changes to contracts have
    consideration
  • Consideration can take forms other than money,
    such as schedule relief, technical performance
    relief, etc.

18
Requirements for the Creation of a Contract
  • In order to establish a contract, a mutual
    understanding as to what each business entity
    will give and receive must be defined
  • Consideration
  • Cost and fee
  • Deliverable items and data
  • Technical performance of deliverables
  • Schedule
  • Tasks (work) to be performed
  • If you dont have all of the above items defined,
    you do not have an executable contract

19
Requirements for the Creation of a Contract
(contd)
  • The contractor makes an offer to the customer
    (Proposal)
  • Can be a written or verbal offer, or an offer
    created by other acts of communication by
    responsible officers of the seller
  • Fax, email?
  • Contractor defines the period within which the
    proposal will be honored
  • Customer enters into negotiations by issuing a
    letter of acceptance
  • The offer must be revoked in writing if something
    happens that requires withdrawal of the offer
    prior to expiration
  • The offer defines all cost, schedule, and
    technical requirements
  • Factfinding then takes place with the customer
    team
  • Negotiations are then held to clarify items in
    the proposal, and to state the customers
    perception of the should cost

20
Requirements for the Creation of a Contract
(contd)
  • The customer then counteroffers to the seller to
    converge differences in understanding
  • This can take multiple iterations
  • Customer then generates a Best and Final Offer,
    or BAFO
  • This is then either accepted by the performer
    (seller) or the seller takes a hike
  • If the offer is accepted, a contract is generated
    which incorporates all of the final changes, and
    everyone signs it
  • The signators must be able to legally obligate
    the business
  • Typically, signators would be officers of the
    company with a delegated signature authority
    greater than the value of the contract
  • This could be many 100 Million

21
Requirements for the Creation of a Contract
(contd)
  • Upon everyones signature, the project starts
  • The seller is under contract to perform in
    accordance with the final negotiated document

22
Contract Changes
  • Things happen during the course of the project
    that change either the amount of work (), or
    the schedule
  • A formal change process is incorporated into all
    contracts
  • Unilateral Change
  • Imposed by the Customer on the Contractor without
    concurrance
  • Constructive Change
  • Failure by the Customer to meet contractual
    requirement, ie. Breach of Contract
  • Bilateral Change
  • Mutually agreed to change between the Customer
    and Contractor
  • Unilateral and Constructive Changes generally
    result in a Dispute

23
Disputes and Breaches
  • Unilateral changes are typically not acceptable
    to the Contractor
  • Consideration is insufficient
  • Need more money to do the additional work
  • Impossible to perform to changed schedule,
    performance, etc.
  • A breach of contract occurs when the Customer or
    the Contractor fail to meet the requirements of
    the contract
  • Failure to provide Customer Furnished Equipment,
    Facilities, etc.
  • Failure to deliver on time

24
Dispute Resolution
  • Negotiations are required by all parties to
    resolve disputes
  • Contract letters and supporting documentation are
    very important in order to document the situation
    and position of both parties
  • Getting ready to go to trial
  • Lawyers get involved
  • Generally very unproductive and expensive
  • Not worth the effort for less than 10K on a
    large job
  • Disputes must eventually adjudicated by the Court
    of Claims, which requires a legal trial
  • This is a very expensive process

25
Termination
  • Contract Termination is possible under certain
    pre-negotiated conditions
  • Termination for Convenience of the Government
  • Termination is also possible for failure to meet
    Contract requirements
  • Cost, Schedule, or Technical Performance
  • Termination for Cause
  • Termination for Default
  • Termination clauses are always included as a part
    of the original Contract

26
Termination (contd)
  • Termination for cause allows the customer to
    re-procure the item at the expense of the
    original contractor!
  • This is extremely serious and can bankrupt a
    company
  • Termination for convenience requires a
    Termination Proposal, which is then negotiated
    like a new contract
  • Material purchased is packaged and turned over to
    the customer
  • Subcontracts must also be terminated
  • Costs associated with early termination of
    employees are included
  • Layoff notification, etc.

27
Contract Concepts
  • Different contract types are available
  • The contract type selected must be based upon a
    mutual understanding of the risk of success of
    the project
  • If the customer is incorrect with regard to their
    perception of risk, than there should be no
    bidders on the contract
  • Success is defined as the achievement of all
    contract objectives Cost, Schedule, Performance
  • Improper utilization of a contract type can, and
    does frequently result in project failure
  • All contracts provide a concept of Profit or
    Fee
  • Related to consideration
  • Generally, the fee equals funds left over at
    contract completion, and after closeout

28
Contract Concepts (contd)
  • Residual materials or equipment are not included
    in the final profit
  • Sold as surplus and credited to overhead
  • Delivered to Customer
  • Profit percentage varies with the type of
    contract, ie. cost reimbursable or fixed price

The residual funds can be negative!!
29
Types of Contracts
  • Fixed Price
  • Cost Reimburseable
  • Time and Material

30
Fixed Price Contracts
  • Highest risk to Seller. Used for low risk
    procurements.
  • Three Types
  • Fixed Fee (FFP)
  • Incentive Fee (FPIF)
  • Fixed Price with Redertimination (FPR)

31
Firm Fixed Price Contracts (FFP)
  • Fixed profit, no ceiling price
  • Exceptions
  • Constructive Changes
  • Unilateral Changes
  • Definition of Change subject to interpretation
  • Generally used as negotiating tool
  • Customer has upper hand by withholding of funds
  • Can overrun! Can also have costs disallowed.

32
Fixed Price Incentive Fee (FPIF)
  • Lower Risk to Seller, fee determined by targets
  • Ceiling Price
  • Cost/Profit Sharing
  • Incentive Curve
  • 30/70 Share for Underrunns
  • 70/30 Share for Overruns
  • Still subject to Changes Clause
  • Can receive minimal or no profit and overrun!
  • Customer can also disallow costs.

33
Fixed Price with Redetermination (FPR)
  • Two types Prospective and Retroactive
  • Prospective FPR negotiates prices to be paid in a
    prospective period
  • Similar to two FFP arrangements negotiated at
    stated times during contract performance period
  • Retroactive FPR provides for adjusting price
    after performance
  • Essentially like FPIF
  • Maximizes Project Managers attention on happines
    of Customer

34
Cost Reimbursable Contracts
  • Lower Risk to Seller than Fixed Price Contracts
  • Used for higher risk procurements
  • Uncertainty of performance goals, etc.
  • Three Types
  • Fixed Fee (CPFF)
  • Incentive Fee (CPIF)
  • Award Fee (CPAF)

35
Cost Plus Fixed Fee (CPFF)
  • Fixed profit, no renegotiation of contract
    allowed
  • No ceiling price
  • Exceptions
  • Constructive Changes
  • Unilateral Changes
  • Definition of Change subject to interpretation
  • Generally used as negotiating tool
  • Customer has upper hand by withholding of funds
  • All Costs are paid
  • Subject to interpretation as to Allowable cost

36
Cost Plus Fixed Fee (contd)
  • If project overruns at cost, no increase in fee
    (lower profit margin)
  • If project underruns at cost, higher profit
    margin achieved
  • Can overrun, but will always make a profit

37
Cost Plus Incentive Fee (CPIF)
  • Lower Risk to Seller
  • Established Targets (Cost, Schedule, Performance)
  • Cost/Profit Sharing
  • Incentive Curve
  • 30/70 Share for Underrunns
  • 70/30 Share for Overruns
  • Still subject to Changes Clause
  • Can overrun and still make a profit subject to
    the Incentive Curve

38
Cost Plus Award Fee (CPAF)
  • Fee determined by Customer via award criteria
  • No rules regarding Award Criteria
  • Typical targets established
  • Responsiveness to Customer
  • Cost/Schedule Controls, etc.
  • Completely dependent on Grade of Customer.
  • Can receive 0 profit, but will always be
    reimbursed for costs
  • Maximizes Project Managers attention on
    happiness of Customer

39
Time and Material Contracts
  • Lowest risk to Seller. Generally used for
    studies with indeterminate outcome, or support,
    operational or maintenance contracts.
  • Not to Exceed Contract for labor and material
  • Task orders from Customer are negotiated with
    Seller
  • Defines effort for small tasks
  • Minimizes any cost uncertainty

40
Cost/Fee Examples
  • FFP
  • FPIF
  • CPFF
  • CPIF

Note In the following slides, the price to
the customer equals the sum of the profit and
cost.
41
Firm Fixed Price (FFP)
42
Fixed Price Incentive Firm Target (FPIF)
43
Cost Plus Fixed Fee (CPFF)
44
Cost Plus Incentive Fee (CPIF)
45
Elements of a Contract
  • Contract Form
  • Schedule
  • Statement of Work (SOW)
  • Deliverables
  • Contract Data Requirements
  • Contract Data Requirements List
  • Specifications

46
Contract Form
  • Document which provides all contractual details
  • Type of Contract
  • Total Cost
  • Deliverables/Services and Prices
  • Packaging and Marking
  • Inspection and Acceptance
  • Contract Clauses and Administration Data
  • List of Documents, Exhibits
  • Representations and Certifications

47
Contract Form (contd)
  • Technically, Schedule and SOW are part of
    Contract
  • Generally referenced in body of Contract Form
  • No Schedule or Technical Information. Cost only!

48
Schedule
  • Time phased tasks and deliverables which are
    detailed in SOW, Supplies List, and CDRL
  • Generally identical to the proposed schedule,
    with modifications resulting from negotiations
  • No Cost or Technical Information. Schedule only!

49
Statement of Work
  • Details all tasks and activities to be
    accomplished on Contract
  • References the following documents
  • Contract Data Requirements
  • Contract Data Requirements List (CDRL)
  • Deliverable Items
  • Specifications
  • Defines all design activities, documentation,
    etc.
  • No Cost or Schedule Information. Technical Only!

50
Other Topics of Interest
  • Government Acquisition Regulations
  • DARS/FARS
  • Government Contracting vs. Commercial Contracting
  • Estimating/Scheduling Methodology
  • Work Planning
  • Specification Development and System Engineering
Write a Comment
User Comments (0)
About PowerShow.com