Title: An Overview of the Building Delivery Process: How Buildings Come Into Being
1An Overview of the Building Delivery ProcessHow
Buildings Come Into Being
Chapter 1
2Building Delivery Process
- Invoke first principles
- idea (owner )
- building design (architect, engineer)
- construction (contractor/construction
- manager)
3Project Delivery Phases
- Predesign
- Design
- Preconstruction
- Construction
- Postconstruction
4Predesign Definition
- The owners objectives, schedule, constraints
and criteria including space requirements and
relationships, special equipment, flexibility,
expandability, systems and site requirements - From Standard Form of Agreement Between Owner
and Architect (AIA Document B141)
5Predesign Phase
- Define building program
- Assess economic feasibility
- Site assessment and/or selection (Ch. 2)
- Assess governmental constraints (Ch. 2)
- Select design team
6Building Program
- Detailed written document used to guide design
- reduce liability risk for architect
- avoid misinterpretation
7Building Program
- Activities
- Functions
- Space requirements
- Space sizes
- Adjacencies
8Economic Feasibility
- Owners budget
- Cost/benefit analysis
- Availability of financing
9Design Team
- Typical design team under traditional contractual
organization
10Consultants
- Civil and structural engineers
- Mechanical, electrical, plumbing fire
protection - Geotechnical
- Acoustical
- Landscape architect
- Building type specialist
11Relationships between design team members
- Relationships between design team members
12Design phase components
- Schematic design
- Design development
- Construction documents
13Schematic Design
- Overall design concept that illustrates key ideas
of the design solution. - Graphic solution to owners program
- Multiple revisions
14Design Development
- Work with consultants to develop practical and
pragmatic solutions to building systems
envelope, structure, interior systems, MEPF, etc.
15Construction Documents
- Documentation required by the contractor to
construct the building - Drawings
- Specifications
16Drawings Specifications
Graphic Written
Product/material shown many times Product/material described only once
Product/material generic Product/material specific
Quantity Quality
Location established Installation requirements established
Size, shape, relationship of building elements Description, properties, characteristics and finishes of building elements
17Construction Drawings
- Dimensioned drawings that delineate the building
- floor plans
- elevations
- sections
- large scale details
18Specifications
- Written technical descriptions of design intent.
19Construction Documents
20MasterFormat
- Standard organizational format for specifications
- Constructions Specifications Institute (CSI)
21MasterFormat Numbering System
Level 1 Level 2 Level 3
Divisions Sections Subsection
01-50 00 00
22(No Transcript)
23(No Transcript)
24Divisions 2 - 14 Facilities Construction Subgroup
- Visualize construction process
25Division 00 - Procurement Contracting
- Advertisement for bids
- Invitation to bid
- Instruction to bidders
- Prebid meetings
- Land survey information
- Geotechnical information
26Division 00 - Procurement Contracting
(continued)
- Bid forms
- Owner-contractor agreement forms
- Bond forms
- Certificate of substantial completion form
- Certificate of completion form
- Conditions of the contract
27Division 00 - General Requirements
- Summary of work
- Price and payment procedures
- Product substitution procedures
- Contract modification procedures
- Project management and coordination
- Construction schedule and documentation
28Division 00 - General Requirements (continued)
- Contractors responsibility
- Regulatory requirements (codes, laws, permits,
etc.) - Temporary facilities
- Product storage and handling
- Owner supplied products
- Execution and close-out requirements
29Preconstruction Phase
- General Relationships Construction Team
30Methods of Selecting a General Contractor
- Competitive bidding
- Invitational bidding
- Negotiated contract
- Multiple prime contracts
31Bidding Documents
32Bidding Documents/Contract Documents
- Design team must produce graphics and text to
convey design intent to contractors, and assure - accurate and competitive bids
- detailed and descriptive submittals
- efficient and accurate construction process
- minimal questions, revisions or changes
33Surety Bonds
- Bid bond
- Performance bond
- Payment bond
34Competitive Bidding - public projects
- Advertisement for bids
- Bid documents
- Qualification of bidders
- Bid bond
35Invitational Bidding - private projects
- Competitive process
- Pre-screened (invited) general contractors
36Negotiated Contract - private projects
- Pre-qualified, trusted general contractor
- General contractor involved during design or
predesign phase - Helps control costs
- Competition among subcontractors and material
suppliers
37Multiple Prime Contracts - fast track delivery
- Form of negotiated contract used to speed up
construction time - Multiple construction phases and contractors
- Extensive coordination and sequencing required
38Construction Phase
- Implement contract documents
- Submittals
- shop drawings
- mock-ups
- material samples
- product data
- certifications
- calculations
39Architects review stamp
40Construction Contract Administration
- Review and approve submittals shop drawings
- Observe construction
- Prepare change orders (if required)
- Interpret contract if needed
- Certify pay requests
- Inspect work
41Postconstruction Phase - project closeout
- Substantial completion
- Punch list
- Certificate of final completion
- Record documents
42Design - Bid - Build (Traditional ) Process
43Construction Management
44Construction Management At Risk - CMAR
45Design - Build
- Single firm designs and constructs the building
- cost plus
- lump sum