Name of Work:- Various other works in Unit-I, Ajmer Construction of Canteen cum Guest House at Engineering College, Ajmer Total Cost : 0.42 Crore Location : Ajmer ... – PowerPoint PPT presentation

Number of Views:115
Avg rating:3.0/5.0
Slides: 38
Provided by: HP896
Learn more at: http://www.rsrdc.com
Category:
Tags: rsrdc | engg

less

Write a Comment
User Comments (0)
Transcript and Presenter's Notes

Title: RSRDC


1
Welcome to the Jurisdiction
of Unit-1
R.S.R.D.C. Ltd., Ajmer
2
ORGANISATION CHART OF RSRDC UNIT-1, AJMER
RE Rakesh Kr. Jain
AAO Sh. Shiv Kr. Sharma
ARE Sh. Brijesh Kr. Mathur
ARE. Sh. Avinash Kumar
ARE Sh. N.K. Tak
ARE Sh. J.P. Kansal
ARE Sh. Harsh Rai
J.En. (Elect.) Sh. O.P. Sharma
3
Financial Work Load in Unit
Rs. in Lacs.
S. No. Name of Work Client Deptt. A F Sanction Expenditure till date Balance Work
ARE I Sh. Brijesh Mathur ARE I Sh. Brijesh Mathur ARE I Sh. Brijesh Mathur
1 Parking space at G/F F/F, Office chamber on S/F and Auditorium on 3rd floor at BSER, Ajmer B.S.E.R., Ajmer 1400.00 288.76 1111.24
2 1st floor 2nd floor over old answer book at BSER, Ajmer B.S.E.R., Ajmer Total 106.00 1506.00 49.34 338.10 56.66 1167.90
4
Financial Work Load in Unit
Rs. in Lacs.
S. No. Name of Work Client Deptt. A F Sanction Expenditure till date Balance Work
ARE II Sh. N.K. Tak ARE II Sh. N.K. Tak ARE II Sh. N.K. Tak
1 Urban Hatt Bazar, Ajmer Industries Deptt. 190.00 113.68 76.32
2 LSQ at GRP Campus, Nareli, Ajmer (Part-IV) Police Deptt. 434.72 334.18 100.54
3 USQLSQ at 11th RAC Battalion, Nareli, Ajmer (Part-I II) Police Deptt. 555.25 378.25 177.00
4 Company Store Office for 11th RAC Battalion Nareli, Ajmer Police Deptt. 21.00 7.90 13.10
5 1st floor on computer centre (Arya Bhatt Bhawan) at MDSU Ajmer M.D.S.U., Ajmer 79.40 53.01 26.39
6 Women Hostel at MDSU Ajmer M.D.S.U., Ajmer 180.91 7.62 173.29
7 Academic Staff College (Guest House) at MDSU Ajmer M.D.S.U., Ajmer Total 75.00 1536.28 11.05 905.69 63.95 630.59
5
Financial Work Load in Unit Rs. in
Lacs.
S. No. Name of Work Client Deptt. A F Sanction Expenditure till date Balance Work
ARE III Sh. Avinash Kumar ARE III Sh. Avinash Kumar ARE III Sh. Avinash Kumar
1 Part of Academic Building and Workshop at Govt. Mahila Engg. College, Ajmer Principal Women Engg., Ajmer 257.00 253.02 3.98
2 Compound wall at Mahila Engg. College, Ajmer Principal Women Engg., Ajmer 12.00 7.00 5.00
3 Internal Road at Mahila Engg. College, Ajmer Principal Women Engg., Ajmer 35.89 6.55 29.34
4 Canteen Cum Guest House at Engg. College, Ajmer Engg. College Society, Ajmer 42.00 25.90 16.10
5 USQ LSQ at GRP Campus, Nareli, Ajmer (Part-I, II, III V) Police Deptt. 1138.56 875.16 263.40
6 2ndfloor on Management block at MDSU, Ajmer MDSU, Ajmer 81.83 53.19 28.64
6
S. No. S. No. Name of Work Client Deptt. A F Sanction Expenditure till date Balance Work
ARE III Sh. Avinash Kumar ARE III Sh. Avinash Kumar ARE III Sh. Avinash Kumar ARE III Sh. Avinash Kumar
7. Social Science Block at M.D.S.U., Ajmer (Development Work) Social Science Block at M.D.S.U., Ajmer (Development Work) MDSU Ajmer 305.52 223.86 81.66
8 (A) App. Road and Parking Shed at Management Block at MDSU, Ajmer App. Road and Parking Shed at Management Block at MDSU, Ajmer MDSU Ajmer 48.22 31.36 16.86
(B) C.C. Interlocking paver block at Bharti niwas at MDSU, Ajmer C.C. Interlocking paver block at Bharti niwas at MDSU, Ajmer MDSU Ajmer 48.22 31.36 16.86
(C) Laying Jointing Pipeline UG Tank to Girls Hostel at M.D.S.U., Ajmer Laying Jointing Pipeline UG Tank to Girls Hostel at M.D.S.U., Ajmer MDSU Ajmer 48.22 31.36 16.86
(D) Tube Well submersible pump set laying jointing GI Pipe. Tube Well submersible pump set laying jointing GI Pipe. MDSU Ajmer 48.22 31.36 16.86
9 10 Environmental Sc. Building at MDSU, Ajmer Dormetory on 1st Floor at Food Craft Institute at Ajmer Environmental Sc. Building at MDSU, Ajmer Dormetory on 1st Floor at Food Craft Institute at Ajmer M.D.S.U., Ajmer Principal Foof Craft Institute Total 238.62 38.00 2197.64 0.00 0.00 1476.04 238.62 38.00 721.6
7
Financial Work Load in Unit Rs. in
Lacs.
S. No. Name of Work Client Deptt. A F Sanction Expenditure till date Balance Work
ARE IV Sh. J.P. Kansal ARE IV Sh. J.P. Kansal ARE IV Sh. J.P. Kansal
1 Ad.Trainee at PTS Kishangarh. Police Deptt. 150.00 130.06 19.14
2 Hostel Building for Trainee at PTS., Kishangarh Police Deptt. 100.00 54.79 45.21
3 Adm. Block at RPL Hadirani Battalion, Ajmer Police Deptt. 125.00 31.30 93.70
4 Adm. Buidling for Police Outpost at Shastri Nagar, Ajmer Police Deptt. 11.00 9.17 1.83
5 Adm. Building for Police out post at Gandhi Nagar, Kishangarh Police Deptt. 11.00 6.00 5.00
8
6 Adm. Building for police out post at Saket Nagar, Beawar Police Deptt. 11.00 5.55 5.45
Adm. Building for Police Police Deptt. out post at Kasai Mohalla, Beawar Adm. Building for Police Police Deptt. out post at Kasai Mohalla, Beawar Adm. Building for Police Police Deptt. out post at Kasai Mohalla, Beawar 11.00 2.27 8.73
8 Adm. Building for Zone officer for CID office, Ajmer Police Deptt. 31.50 1.40 30.10
9 30 Mens Barracks at PTS, Kishangarh Police Deptt. Total 17.00 467.50 5.76 246.30 11.24 221.20
9
Financial Work Load in Unit Rs. in
Lacs.
S. No. Name of Work Client Deptt. A F Sanction Expenditure till date Balance Work
ARE V Sh. Harsh Rai ARE V Sh. Harsh Rai ARE V Sh. Harsh Rai
1 100 men barrack at RPLHadirani Battalion (Part-I ) Police Deptt. 100.00 2.91 97.09
2 100 Men Barrack at RPL Hadirani Battalion, Ajmer (Part-II) Police Deptt. Total 100.00 200.00 0.58 3.49 99.42 196.51
10
Important Works Completed during last 5 years
Bharat Vidhya Adhayan Sankul at M.D.S.U., Ajmer
Completion Cost Rs. 1.10 Crs.
Foundation Stone laid by Honble Minister for
Higher Education Rajasthan State Sh. Ghanshyam
Tiwari in March, 07 Inaugurated by Prof. Sukhdev
Thorat Chairman UGC on 12.10.09
11
Important Works Completed during last 5 years
Boys Hostel at M.D.S.U., Ajmer
Completion Cost Rs. 1.65 Crs.
Foundation Stone laid by Honble Minister for
Higher Education Rajasthan State Sh. Ghanshyam
Tiwari in March, 07
12
Important Works Completed during last 5 years
Girls Hostel at M.D.S.U., Ajmer
Completion Cost Rs. 1.40 Crs.
Completion Cost Rs. 1.65 Crs.
Foundation Stone laid by Honble Minister for
Higher Education PWD Rajasthan State Sh. Lalit
Kishor Chaturvedi on 24.09.1998
Inaugurated by Honble Mininster for Higher
Education Rajasthan State Govt. Sh.
Ghanshyam Tiwari on 21.08.2006
13
Important Works Completed during last 5 years
Social Science Block at M.D.S.U., Ajmer
Completion Cost Rs. 3.05 Crs.
Foundation Stone laid by Honble Minister for
Mahilla Bal Vikas JanJati Kashetrya Vikas,
Rajasthan State Sh. Kankmal Katara on 01.06.2005.
Inaugurated by Honble Mininster for Higher
Education Rajasthan State Govt. Sh.
Ghanshyam Tiwari on 10.08.2006.
14
Important Works Completed during last 5 years
Yoga Centre at M.D.S.U., Ajmer
Completion Cost Rs. 0.63 Crs.
Foundation Stone laid by Honble Minister for
Higher Education PWD Rajasthan State Sh. Lalit
Kishor Chaturvedi on 24.09.1998
Inaugurated by Honble Mininster for Higher
Education Rajasthan State Govt. Sh. Ghanshyam
Tiwari on 29.06.2007.
15
Important Works Completed during last 5 years
Women Engineering College at Ajmer
Completion Cost Rs. 2.57 Crs.
Foundation Stone laid by Honble Chief Minister
Govt. of Rajasthan Smt. Vasundhra Raje on
30.04.07
Handed Over in November, 2009
16
Important Works Completed during last 5 years
Women Engineering College at Ajmer
Completion Cost Rs. 2.57 Crs.
Foundation Stone laid by Honble Chief Minister
Govt. of Rajasthan Smt. Vasundhra Raje on
30.04.07
Handed Over in November, 2009
17
Important Works Completed during last 5 years
Management Block at M.D.S.U., Ajmer
Completion Cost Rs. 1.97 Crs.
Inaugurated by Honble Mininster for Industries
Rajasthan State Govt. Sh. Rajendra
Pareek on 17.09.09.
18
Important Works Completed during last 5 years
New Answer Book Halls at 1st Floor 2nd Floor in
B.S.E.R., Ajmer
Completion Cost Rs. 2.15 Crs.
Handed Over in November, 2009
19
Important Works Completed during last 5 years
Engineering College, Ajmer
Completion Cost Rs. 5.40 Crs.
Inaugurated by Honble Chief Mininster Govt. of
Rajasthan Smt.Vasundhra Raje on 25.01.08.
20
POLICE HOUSING SCHEME (ONGOING WORK AT GRP CAMPUS)
No. of Quarters 304 Nos. (L.S.Q.-292
U.S.Q.-12) Total Cost 15.73 Crores Location
G.R.P. Campus, Nareli, Ajmer Date of Start
February, 2008 / October, 2008 Stipulated Date of
Completion January, 2009 / September,
2009 Expenditure till Date 12.09
Crores Likely Completion date March,
2010 Bottlenecks if any (i) Sanction for
Development works not given. (ii) Water supply
connection in campus is to be carried out by
PHED. For which Six Months period
required. (iii) 60 Nos Qtrs. (L.S.Q.) taken in
Phase-II
21
POLICE HOUSING SCHEME (ONGOING WORK AT GRP CAMPUS)
22
POLICE HOUSING SCHEME (ONGOING WORK AT
RAC,NARELI CAMPUS)
No. of Quarters 108 Nos. (L.S.Q.-104
U.S.Q.-4) Total Cost 5.55 Crores Location R.
A.C. Campus, Nareli, Ajmer Date of
Start February, 2008 / October,
2008 Stipulated Date of Completion January,
2009 / September, 2009 Expenditure till
Date 3.78 Crores Likely Completion
date March, 2010 Bottlenecks if any (i) 56
L.S.Q. taken in Phase-II work in month of
October, 2008 therefore, campus may be
ready for handing over by March, 2010.
23
Name of Work- Various Works in M.D.S.
University, Ajmer
Construction of First Floor at Computer Centre
  • Total Cost 0.54/0.79 Crore
  • Location M.D.S. University, Campus
  • Date of Start September, 2008
  • Stipulated Date of Completion April, 2009
  • Expenditure till Date 0.53 Crore
  • Likely Completion date March, 2010
  • Bottlenecks if any Revised Sanction for
    additional work received in June, 2009 and
    delay in payment from client.

24
Name of Work- Various Works in M.D.S.
University, Ajmer
Construction of Women Hostel
Foundation Stone Lead by Honble State Minister
for Information Technology Communication Govt.
of India Sh. Sachin Piolet on 15th September,
2009
  • Total Cost 1.81 Crores
  • Location M.D.S. University, Campus
  • Date of Start September, 2009
  • Stipulated Date of Completion June, 2010
  • Expenditure till Date 0.08 Crore
  • Likely Completion date June, 2010
  • Bottlenecks if any Work started in October,
    2009 due to foundation stone ceremony in
    September, 2009.

25
Name of Work- Various Works in M.D.S.
University, Ajmer
Construction of Academic Staff College (Guest
House)
  • Total Cost 0.75 Crore
  • Location M.D.S. University, Campus
  • Date of Start August, 2009
  • Stipulated Date of Completion December, 2009
  • Expenditure till Date 0.11 Crore
  • Likely Completion date March, 2010
  • Bottlenecks if any Funds not released by
    client timely.

26
Name of Work- Various Works in M.D.S.
University, Ajmer
Construction of Environmental Science Building
Foundation Stone Lead by Honble State Minister
for Information Technology Communication Govt.
of India Sh. Sachin Piolet on 15th September,
2009
  • Total Cost 2.39 Crores
  • Location M.D.S. University, Campus
  • Date of Start December, 2009
  • Stipulated Date of Completion November, 2010
  • Expenditure till Date 0.00 Crore
  • Likely Completion date November, 2010
  • Bottlenecks if any -

27
Name of Work- Various Works in Board of Sec.
Edu., Rajasthan, Ajmer
Construction of Parking, Office, Chamber
Auditorium
  • Total Cost 14.00 Crores
  • Location B.S.E.R. Campus
  • Date of Start September, 2008
  • Stipulated Date of Completion August, 2011
  • Expenditure till Date 2.89 Crores
  • Likely Completion date August, 2011
  • Bottlenecks if any Work stopped on account of
    decision not given by client for Construction
    of Auditorium hence, Construction of 2rd
    Floor held up for Two Months.

28
Name of Work- Various Works in Board of Sec.
Edu., Rajasthan, Ajmer
Construction of 1st 2nd Floor on Old Answer
Book Hall
  • Total Cost 1.06 Crores
  • Location B.S.E.R. Campus
  • Date of Start September, 2008
  • Stipulated Date of Completion February, 2010
  • Expenditure till Date 0.49 Crore
  • Likely Completion date March, 2010
  • Bottlenecks if any (i) Funds not released by
    client timely.
  • (ii)Work stopped by client on account of
    thorough passes for access of examination
    stationary through trucks.

29
Name of Work- Various Works under Police
Modernization
Construction of Adm. Training Block at PTS
Kishangarh
  • Total Cost 1.5 Crores
  • Location Kishangarh
  • Date of Start September, 2008
  • Stipulated Date of Completion May, 2009
  • Expenditure till Date 1.30 Crores
  • Likely Completion date January, 2010
  • Bottlenecks if any Part sanction of Rs. 0.5
    crores received in phase-II.

30
Name of Work- Various Works under Police
Modernization
Construction of Hostel Building of Trainee at PTS
Kishangarh
Total Cost 1.00 Crore Location Kishangarh
Date of Start September, 2008 Stipulated Date
of Completion May, 2009 Expenditure till
Date 0.55 Crore Likely Completion
date January, 2010 Bottlenecks if any Part
sanction of Rs. 0.2 crores received in
phase-II.
31
Name of Work- Various Works under Police
Modernization
Construction of Adm. Building for RPL, Hadi Rani
Battalion, Ajmer
  • Total Cost 1.25 Crores
  • Location Nareli, Ajmer
  • Date of Start January, 2009
  • Stipulated Date of Completion December, 2009
  • Expenditure till Date 0.31 Crore
  • Likely Completion date January, 2010
  • Bottlenecks if any Work Started in July, 2009
    due to non availability of land.

32
Name of Work- Various Works under Police
Modernization
Construction of 100 mens barracks at RPL, Hadi
Rani Battalion, Ajmer (Part-I)
  • Total Cost 1.00 Crore
  • Location Nareli, Ajmer
  • Date of Start January, 2009
  • Stipulated Date of Completion December, 2009
  • Expenditure till Date 0.03 Crore
  • Likely Completion date January, 2010
  • Bottlenecks if any Work Started in July, 2009
    due to non availability of land.

33
Name of Work- Various Works under Police
Modernization
Construction of 100 mens barracks at RPL, Hadi
Rani Battalion, Ajmer (Part-II)
  • Total Cost 1.00 Crore
  • Location Nareli, Ajmer
  • Date of Start January, 2009
  • Stipulated Date of Completion December, 2009
  • Expenditure till Date 0.006 Crore
  • Likely Completion date January, 2010
  • Bottlenecks if any Work Started in July, 2009
    due to non availability of land.

34
Name of Work- Various other works in Unit-I,
Ajmer
Construction of Canteen cum Guest House at
Engineering College, Ajmer
  • Total Cost 0.42 Crore
  • Location Ajmer
  • Date of Start December, 2007
  • Stipulated Date of Completion July, 2008
  • Expenditure till Date 0.26 Crore
  • Likely Completion date March, 2010
  • Bottlenecks if any -

35
Name of Work- Various other works in Unit-I,
Ajmer
Construction of Urban Hatt at Ajmer
  • Total Cost 1.60 / 1.90 Crores
  • Location Ajmer
  • Date of Start June, 2007
  • Stipulated Date of Completion May, 2008
  • Expenditure till Date 1.14 Crores
  • Likely Completion date March, 2010
  • Bottlenecks if any Work Stopped since October,
    2008 due to funds not released by client

36
Proposed New Works
S. No. Name of Work Client Deptt. Mode Estimated Cost
Actual plus / Tendered
1. Const. of Women Engineering college (Ph.-II) Principle Mahilla Engineering College, Ajmer Actual Plus 393.00 Lacs.
2. Additional Works in ITI Building and Campus at Beawar. Institute Management Committee of ITI, Beawar Actual Plus 60.00 Lacs.
37
With RegardsThanks
About PowerShow.com