Title: 4TH STREET BRIDGE Pueblo, Colorado


1
4TH STREET BRIDGEPueblo, Colorado
December 2006 Project Overview
2
Project Team
  • Colorado Department of Transportation
  • FHWA
  • Design Consultants
  • FIGG Project Management Bridge
    Engineering
  • PBSJ Civil, Roadway, Traffic,
    Utilities, Environmental
  • Ayres Associates
    Hydraulics Drainage
  • Goodson/MWWA
    Geotechnical, Geology
  • The Szynskie Group
    Lighting Electrical Design
  • EDAW Urban Design
    Landscape Architecture
  • Abel Engineering
    Survey ROW Support

3
Project History
  • Replacement of existing bridge K-18-Z
  • Structurally Deficient, Functionally Obsolete
  • Statewide Transportation Plan 1996
  • Consultant Services - 2000
  • Conceptual Design 2001/2002
  • Preliminary Design 2003
  • Environmental Clearance 2003 thru 2005
  • Final Design 2006

4
Project Timeline
  • 90 Plans October 18, 2006
  • PSE December 18, 2006
  • Advertisement March 2007
  • Contract Award May- June 2007
  • Construction (3-4 years) 2007-2011

5
Project Description
6
Project Aerial Map
Mall
To I-25
Loop Ramp Rd
River
RR Yard
Bluff
Floodwall
Bluff
7
Site Photo
8
Project Description
  • Study Corridor
  • Elizabeth St. to Abriendo Ave.
  • Construction Limits
  • Midtown Circle to Corona Ave.

9
Site Description West End
Bluff Arkansas River Trail Fishing Pier Kayak
Course
10
Site Description East End
Railroad Facilities Midtown Mall Commercial Downto
wn Pueblo
11
Existing Bridge Conditions
  • Undesirable Roadway Geometry
  • Insufficient Safety Clearances
  • Substandard Load Carrying Capacity
  • Structurally Deficient
  • Functionally Obsolete
  • Insufficient Pedestrian/Bicycle Facilities

12
Existing Bridge Conditions
  • Narrow Lanes, Shoulders, Sidewalks

13
Project Considerations
  • Railroad Coordination
  • City Coordination
  • Utilities
  • Phasing / Maintenance of Traffic
  • Arkansas River Recreation Area
  • Access to Midtown Mall
  • Construction Access and Staging Areas
  • Environmental Compliance

14
Proposed Roadway Section
  • 4-Lane Build / 6-Lane Future Capacity

15
Proposed Structure Alignment
16
Proposed Alignment
  • North Alignment - Aerial

17
Proposed Structure Information
  • Twin Structures 6-ft Separation
  • Average Length
    1,137 feet
  • 5 Spans (151, 235,
    378, 228, 145)
  • Clear Spans
  • Arkansas River Levee
  • River Trail
  • UPRR BNSF Yards (w/ pier between)
  • Loop Ramp Road

18
Proposed Bridge (from Bluff)