Title: METAL FURNITURE SURFACE COATING MACT COMPLIANCE ASSURANCE
1METAL FURNITURE SURFACE COATING MACT COMPLIANCE
ASSURANCE
- 40 CFR PART 63, SUBPART RRRR
- July 2006
2Compliance Dates
- Initial startup on or before April 24, 2002
(determined by General Provisions requirement to
decide new or existing sources using proposal
date as cutoff date) the facility is an existing
source and must comply by May 23, 2006
3Compliance Dates (Contd)
- Initial startup after April 24, 2002 the
facility is a new source and must comply by May
23, 2003 or the initial startup of the affected
source whichever is later - Non-compliance may result in fines and penalties
of up to 25,000 per day per violation
4Compliance Calculations
- Compliance Option 1 The collected data for
coatings, thinners, and cleaning materials are
used to calculate the organic HAP content of each
material used each month - If supplier information is not available, Method
24 is still the best choice to determine HAP
content for calculating compliance status - Compliance Options 2 3 An average monthly
emission rate is calculated
5Sample Calculations
- This example of calculations required by Subpart
RRRR, and frankly, similar Surface Coatings
NESHAP is provided in this context for objective
review. The regulatory and affected sources must
work through the Initial to Continued compliance
issues using the mandated calculations if
appropriate for a particular facility.
6SAMPLE CALCULATION (contd)
- Initial Notification of Compliance Calculation
(63.4951(e - g) - H e A B C R w where
- H e Total Mass Organic HAP during compliance
period - A Total mass of Organic HAP coatings used
7SAMPLE CALCULATION (contd)
- B Total mass Organic HAP in thinners used
- C Total mass Organic HAP in cleaning materials
used - R w Total mass of Organic HAP in waste
materials - Calculate the mass of Organic HAP in the coatings
used
8SAMPLE CALCULATION (contd)
- Similar calculations are repeated for thinners,
cleaning materials and waste materials used in
the compliance test period - Average Organic HAP Emission Rate
- H avg He / V st
- H avg Organic HAP Emission Rate (kg/l) during
compliance period
9SAMPLE CALCULATIONS (contd)
- He Total Mass Organic HAP during compliance
period - Vst Total volume of coating solids used during
compliance period (l) - The sample calculations contain similarity to
other surface coating rules
10SAMPLE CALCULATIONS (contd.)
- However, regulatory personnel must establish
clear understanding of Subpart RRRR (generally
true for all Subparts) in order to maximize
source T5 permitting clarity, facility inspection
efficiency and finally a high level of affected
facility compliance assurance.
11Initial Compliance Demonstration
- Initial Notification (63.4910)
- Initial Notification states that a facility is
subject to the Metal Furniture Surface Coating
Standards. - Facility must submit the Initial Notification no
later than May 23, 2004 for an existing source
(issue Section 112j connection) - September 30, 2003 or at startup, whichever is
later for a new source
12Initial Compliance (contd.)
- Notification of Intent to Conduct a Performance
Test 63.9 (e) - If facility required to conduct performance tests
(e.g., add-on control equipment), facility must
submit a notification of intent to conduct a
performance test 60 days prior to the test
13Initial Compliance (contd.)
- Performance test is required no later than May
23, 2006 for existing sources - New or reconstructed sources must conduct the
performance test by November 19, 2003 or within
180 days of startup, whichever is later
14Notification of Compliance Status 63.4910
- Facility must submit a Notification of Compliance
Status (NOCS) by July 30, 2006 for an existing
source - For new sources, the NOCS must be submitted
within 30 days after the end of the initial
compliance period
15Performance Test Report 63.4920
- For facilities required to conduct performance
tests (e.g., those with add-on control
equipment), a performance test report must be
submitted 60 days after completion of the
performance test
16Startup, Shutdown, Malfunction Reports 634920
- Compare to Exceedance or Incident Reports for VOC
issues.
17Reports 634920 (Contd.)
- A Startup, Shutdown, Malfunction (SSM) report
must be submitted immediately if there was a
startup, shutdown, or malfunction of the control
device during the reporting period that is not
consistent with the SSM Plan. - If actions were consistent with the SSM Plan, the
report must be submitted semi-annually
18Semi-Annual Compliance Reports (63.4920)
- After the initial compliance period each affected
source must submit semiannual compliance reports
19Compliance Options
- Compliance Material Option An affected facility
may comply with the necessary emission limits
using the following options - Each coating a facility uses (either as
pre-purchased or as-applied) must not exceed
0.10 kg HAP per liter solids for existing
sources, determined monthly.
20Options (Contd.)
- New sources with an approved emissions limit must
emit no more than 0.094 kg HAP per liter solids
determined monthly - Each thinner and cleaning material must contain
no organic HAP
21Options (contd.)
- Emission Rate Without Add-on Controls
- The monthly organic HAP emission rate for
coatings (including adhesives), thinners, and
cleaning materials must not exceed 0.10 kg HAP
per liter solids for existing sources
22Options (contd.)
- 0.094 kg HAP per liter solids for new sources
with approval for an alternative emission limit - New sources without approval for an alternative
emission limit must emit no organic HAP
23Options (contd.)
- Emission Rate With Add-on Controls
- The monthly organic HAP emission rate from
coatings, thinners, and cleaning materials
(including the emission capture and control
efficiency) must not exceed 0.10 kg HAP per liter
solids for existing sources
24Options (contd.)
- 0.094 kg HAP per liter solids for new sources
with an approval for an alternative emission
limit - New sources without an approval for an
alternative emission limit must emit no organic
HAP
25TIMELINE
26Records 63.4930 and 63.4931
- An affected facility is required to keep records
of reported information and all the other
information necessary to document compliance with
the proposed rule for 5 years - There may be additional requirements depending on
the compliance option that is chosen
27Title V Connect
- Check Facilities that have Federally Enforceable
Limits - Limited number of Major Facilities who are they?
- Section 112j, T5 connection (ltgt3 years on T5
Permit - Section 112j is no longer factor on surface
coaters
28Title V Issues
- Each affected source that has obtained a title V
operating permit required by 40 CFR part 70 or 71
must report all deviations as defined in the
regulation for the semiannual monitoring report
required by Sec. 70.6(a)(3)(iii)(A) or Sec.
71.6(a)(3)(iii)(A).
29TITLE V (contd.)
- If an affected source submits a compliance report
required by Subpart RRRR along with, or as part
of, the semiannual monitoring report required by
Sec. 70.6(a)(3)(iii)(A) or Sec.
71.6(a)(3)(iii)(A), and the compliance report
includes all required information.
30TITLE V (contd.)
- concerning deviations from any organic HAP
emissions limitation (including any operating
limit) or work practice requirement in subpart
RRRR, submission of the compliance report shall
be deemed to satisfy any obligation to report the
same deviations in the semiannual monitoring
report. In other words, no double jeopardy
31TITLE V (contd.)
- However, submission of a compliance report shall
not otherwise affect any obligation the affected
source may have to report deviations from permit
requirements to the permitting authority. (THIS
IS VERY IMPORTANT)
32Title V Compliance Report Example
- For each affected source that is subject to
permitting requirements required by 40 CFR part
70 or 71, and if the permitting authority has
established dates for submitting semiannual
reports required by Sec. 70.6 (a)(3)(iii)(A) or
Sec. 71.6(a)(3)(iii)(A), you may submit the first
and subsequent compliance reports according to
the dates the permitting authority has
established instead of according to the dates in
paragraphs (b)(1) through (4) of this section.
(NOTE WELL)
33NESHAP Control Requirements
- Generally, speaking, if the affected source
cannot meet the no HAP component requirement,
or some use of compliant coatings to meet the
facility compliance requirement, the facility
must install add-on controls (i.e. Thermal
Oxidation, Carbon Adsorber, Condenser), and
operate and maintain according to supplier
manuals.
34SSM PLANS
- Only facilities that use add-on control devices
to comply with the standard must complete an SSM
Plan - Data Collection
- Supplier information on delivered/stored
coatings, adhesives, thinners and cleaning
materials
35Section 112j Implications
- States approach to Initial Notification
requirements connection to Section 112j
36SURFACE COATING ALTERNATIVES
- Any option for surface coating needs?
- The facility can determine a compliant material
option by demonstrating that the organic HAP
content of each coating used in the coating
operations is less than or equal to the
applicable emission rate limit in 63.4890 and
that each thinner and each cleaning material used
contains no organic HAP.
37Compliance Examples
- Combination HAP/no-HAP organic solids
- Handling cleaning materials and production
materials
38Pollution Prevention Options
- Remove HAP organic solids from formulation
- Application equipment design state-of-the-art
- Powder Coat Technology