Title: Control of Mercury Emissions by Injecting Powdered Activated Carbon (PAC)
1Control of Mercury Emissionsby Injecting
Powdered Activated Carbon (PAC)
Presentation to Utility MACT Working Group May
13, 2002 EPA, RTP, NC
Michael D. Durham, Ph.D., MBA ADA Environmental
Solutions 8100 SouthPark Way B-2 Littleton, CO
80120 303 734-1727
2Outline
- ADA-ES DOE/NETL Hg Control Program
- Background on PAC Injection Technology
- Results from PAC with an ESP
- Results from PAC with a FF
- Conclusions and Future Plans
3ADA-ES Hg Control Program
- Full-scale field testing of sorbent-based mercury
control on non-scrubbed coal-fired boilers - Primary funding from DOE National Energy
Technology Laboratory (NETL) - Cofunding provided by
- Southern Company
- Wisconsin Electric
- PGE NEG
- EPRI
- Ontario Power Generation
- TVA
- First Energy
- Kennecott Energy
- Arch Coal
4Project Overview
- Perform first full-scale evaluations of mercury
control on coal-fired boilers (up to 150 MW
equivalent). - Evaluate effectiveness of sorbent-based Hg
control (activated carbon). - Test several different power plant
configurations. - Document all costs associated with Hg control.
5DOE/NETL Test Sites
Test Site Coal Particulate Test Control Dates A
labama Power Bituminous HS ESP Spring Gaston
COHPAC FF 2001 Wisconsin Electric PRB Cold Side
ESP Fall Pleasant Prairie 2001 PGE
NEG Bituminous Cold Side ESP Summer Brayton
Point 2002 PGE NEG Bituminous Cold Side
ESP Fall Salem Harbor 2002
6Coal-Fired Boiler with Sorbent Injection and
Spray Cooling
7Semi-Continuous Mercury Analyzer
Heater
Dry Air
CVAA
Flue Gas
Chilled Impingers
Gold Trap
Mass Flow Controller
Micro controller with Display
Waste
8Sampling Time Required
9Comparison of OH and S-CEM, Long Term Tests (10
lbs/MMacf)
10Capture of Vapor Phase Hg by Solid Sorbents
- Mass Transfer Limits (getting the Hg to the
sorbent) - Removal increases with particle concentration
- Produces percentage removal independent of
concentration - Particle control device (FF vs ESP) is a critical
parameter - Sorbent Capacity to hold Hg depends upon
- Sorbent characteristics
- Temperature
- Mercury concentration
- Concentrations of SO3 and other contaminants
11Equilibrium Adsorption Capacities at
250FUpstream and Downstream of SO3 Injection
12WEPCO Pleasant Prairie
- Testing completed fall of 2001
- PRB coal
- ESP only
- Spray cooling
- SO3 conditioning system
13(No Transcript)
14Activated Carbon Storage and Feed System
15ESP Configuration, PPPP
16Powdered Activated Carbon Injection System
17Baseline Hg Measurements (?g/dscm)
Location Particle Bound Oxidized, Hg2 Elemental, Hg0 Total, Hg
Inlet 99 0.16 2.29 6.21 8.65
Inlet 01 1.84 2.34 11.39 15.55
18Mercury Trends Week 1
19Response Time for PAC Injection on an ESP
20Carbon Injection Performance on a PRB Coal with
an ESP
21Long Term Trend Data
22Speciated Mercury Measured by Ontario Hydro
Method (10 lbs/MMacf)
(microgram/dncm)
PARTICULATE ELEMENTAL OXIDIZED TOTAL Baseline
ESP Inlet 1.97 12.22 2.51
16.71 ESP Outlet 0.01 9.80
6.01 15.82 Removal Efficiency 99.5
19.8 -139.3 5.3
PAC Injection ESP Inlet 0.98
14.73 1.73 17.44 ESP Outlet
0.00 4.27 0.44 4.71 Removal
Efficiency 100.0 71.0 74.5
73.0
23Alabama Power E.C. Gaston
- Alabama Power Company E.C. Gaston Electric
Generating Plant Unit 3, Wilsonville, AL - 270 MW Firing a Variety of Low-Sulfur, Washed
Eastern Bituminous Coals - Particulate Collection System
- Hot-side ESP, SCA 274 ft2/1000 acfm
- COHPAC baghouse supplied by Hamon
Research-Cottrell - Wet Ash Disposal to Pond
24Site Test Configuration with EPRI TOXECON at
Alabama Power Plant Gaston
25S-CEM Duct Traverse
26Example of S-CEM Data
27Response Time of PAC Injection with a Fabric
Filter
28Mercury Removal vs. Injection Rate
29Pressure Drop Increase from PAC Injection
30Mercury Removal vs. Injection Rate
315-Day Continuous Injection
32Average Mercury Removal Long-Term Tests Gaston,
Ontario Hydro
(microgram/dncm)
PARTICULATE OXIDIZED ELEMENTAL TOTAL Baseline
COHPAC Inlet 0.09 9.54 5.97
15.60 COHPAC Outlet 0.01 11.19
3.34 14.54 Removal Efficiency
89.1 -17.3 44.1 6.8
PAC Injection COHPAC Inlet 0.23
6.37 4.59 11.19 COHPAC Outlet
0.12 0.91 0.03 1.05 Removal
Efficiency 45.6 85.7 99.3
90.6
33Comparison of Sorbent Costs for a Fabric Filter
and an ESP
34Conclusions (PAC General)
- PAC injection can effectively capture elemental
and oxidized mercury from both bituminous and
subbituminous coals - Additional field tests and long-term
demonstrations are necessary to continue to
mature the technology - Fabric filters provide better contact between the
sorbent and mercury than ESPs resulting in higher
removal levels at lower sorbent costs - New COHPAC FFs will have to be designed to
handle higher loadings of PAC to insure high
(gt90) mercury removal - Conventional FFs should not require any
modifications for PAC
35Conclusions (Response to Concentration Variations)
- Response times to changes in inlet
concentrations - Feedback data from outlet CEMstens of minutes
- Impact of changes in injection rate tens of
minutes to hours - Long averaging times will be required to recover
from upsets - Injection at somewhat higher rates will make the
technology more capable to handle inlet
fluctuations - PAC injection lends itself to the use of feed
rate parameters as a definition of Maximum
Achievable Control Technology
36Future Plans
- Short-term testing at additional sites
- PGE Brayton Point (Bituminous coal, large ESP)
6/ 2002 - PGE Salem Harbor (Bituminous coal, SNCR, large
ESP) 9/2002 - TBD (PRB coal, small ESP) 3/2003
- Southern Company (Bituminous coal, small
ESP) 8/ 2003 - Long-term testing
- Alabama Power (Bituminous coal, COHPAC
FF) 2002-2003 - CCPI Program (PRB Coal, COHPAC FF) 2004-2006
- CCPI Program (Bituminous Coal, COHPAC
FF) 2004-2006 - Proposed
37For More Information
- www.adaes.com
- www.adaes.com/mercury.htm
- Link to other mercury related web sites
- Publications/reports
- www.adaes.com/MercuryPublic.htm
- Public information on DOE/NETL Mercury Control
Program - www.netl.doe.gov/products/environment/index.html
DOE/NETL Website