* References FAR Subpart 44.3 Contractors Purchasing Systems Reviews ... Negotiation Techniques Price Analysis / Cost Analysis Writing a Price Negotiation ... – PowerPoint PPT presentation

Number of Views:692
Avg rating:3.0/5.0
Slides: 36
Provided by: GraphicD8
Category:

less

Transcript and Presenter's Notes

Title: Contractor Purchasing System Reviews (CPSR


1
(No Transcript)
2
Contractor Purchasing System Reviews (CPSRs) Can
Improve Company Profitability
Breakout Session 707 Name Phil Bail Phil Bail
Associates - (A Center for Veterans Enterprise
(CVE) verified Veteran-Owned Small
Business) Date July 21, 2010 Time 0930-1045
1
3
Outline
  • Background
  • Unapproved versus Approved Purchasing System
  • Benefits
  • What is a CPSR?
  • Is Your Company a Target for a CPSR?
  • Core Elements of a Compliant Purchasing System
  • Process
  • Purchasing Policies Procedures Manual
  • Supply Chain Buyer Training
  • Key Compliance Areas / Clause Flow Down
  • Summary
  • Questions?
  • References

2
4
Background
  • In 1990 CPSR Audit at my company
  • In 1991 wrote an article for Contract
    Management magazine titled Being Audited By the
    Government Can Increase Contractor Profitability
    article received the Charles J. Delaney
    Memorial Award for most outstanding article of
    the year.

3
3
5
Unapproved Versus Approved Purchasing System
6
What if Purchasing System is Not Government
Approved?
  • Consent to Subcontract FAR 44.201 and FAR
    52.244-2, Subcontracts (June 2007)
  • CR, TM, L-H,
  • FP and exceeds
  • 100,000 or 5 of the total estimated cost of the
    contract.
  • Advance Notification FAR 44.201-2
  • CPFF subcontract or FFP Subcontract gt100,000 or
    5 of the total estimated cost of the contract

5
5
7
What If Purchasing System is Approved by the
Government?
  • The level of government administrative oversight
    on prospective contracts is reduced Consent to
    Subcontract and Advance Notification requirements
    are no longer issues unless required by
    52.244-2
  • Opportunities for future contracts are increased
    because purchasing system has more creditability
    with customers
  • Bottom Line More potential revenue profit
    dollars

6
6
8
The Definition and Objective of a CPSR
  • What is a CPSR?
  • What is the objective of a CPSR?

7
7
9
Definition and Objective of a CPSRFAR 44.3
  • Definition CPSR - the complete evaluation of a
    contractors purchasing of material and services,
    subcontracting, and subcontract management from
    development of the requirement through completion
    of subcontract performance.
  • Objective to evaluate the efficiency and
    effectiveness with which the contractor spends
    Government funds and complies with Government
    policy when subcontracting.

8
8
10
Is Your Company a target for a CPSR?
  • ACO considers recommending a company for a CPSR
    by performing a risk assessment.
  • - Sales to government expected to exceed 25
    Million in next year excluding competitively
    awarded FP contracts and sales of FAR Part 12
    commercial items
  • Are there signs of trouble in the contractors
    supply chain?
  • Failure to comply with laws, or prime contract
    requirements
  • Quality or delivery issues
  • Contract mix moving from FFP to CR type contracts
  • DCAA audits

9
9
11
Is Your Company a target for a CPSR? (continued)
  • Direct Materials and material overhead as a of
    sales appears out of sync
  • Experience, knowledge, and training of the
    companys purchasing personnel is low
  • Sales to the government as a percentage of a
    contractors total sales
  • A contractors relative position within an
    industry
  • Mergers, acquisitions, or divestitures
  • Significant increases or decreases in sales

10
10
12
The Core Elements of a CPSR Compliant Purchasing
System
  • Process
  • Purchasing Policies and Procedures Manual
  • Supply Chain Buyer Training
  • Key Compliance Areas / Clause Flow Down

13
Process
  • Part I
  • Purchase Requisition
  • Identification of Sources
  • Part 2
  • Issuance of PO / Subcontracts at Reasonable
    Prices (Buyer Actions)
  • Part 3
  • Timely Delivery of Quality Products or Services
  • Evaluation of Vendors
  • Part 4 (really part of entire process)
  • Self Inspection of Process
  • Management Oversight

14
Process - Part 1Purchase Requisition / Source
Selection
  • Initiation of Purchase Requests
  • By Whom?
  • What Information is included?
  • Sources?
  • Prime Contract Requirements?
  • Oversight (Management Review)

15
Process - Part 2 Buyer Actions
  • Subcontract / PO Selection
  • FFP or CR
  • Terms Conditions / Clause Flow Down
  • Source Selection FAR 52.219-8
  • Extent of Competition
  • Determining Prices Fair and Reasonable
  • Competition
  • Price Analysis
  • Cost Analysis
  • Certified Cost or Pricing Data
  • Writing a Price Negotiation Memorandum

16
Process - Part 3 Order Administration
  • Receipt Acceptance of Products or Services
  • Update of Vendor Rating System
  • Quality of Products
  • Timely Delivery
  • Management Oversight

15
17
Process Part 4 Self Inspection
  • Internal Audit Program
  • Management Oversight

16
18
Purchasing Manual
  • Should explain the Purchasing Process for the
    Benefit of ALL Employees, not just the Supply
    Chain
  • Should include the 55 separate topics CPSR
    auditors expect in a Purchasing Manual (refer to
    DCMA Guidebook, Appendix B for a list of the
    topics)

19
The 55 Topics(examples)
  • Advance Notification and Consent
  • 10. Commercial Acquisitions
  • 19. Make or Buy Program
  • 26. Truth In Negotiations
  • 43. Single/Sole Source Procurements
  • 45. Small Business Program
  • 54. Specialty Metals

20
The 55 Topics1. Advance Notification and Consent
  • FAR 52.244-2, Subcontracts (JUN 2007)
  • Is the clause in your contract?
  • Is your purchasing system approved by the
    government?
  • What kinds of contracts do you have? FFP/CR?

21
The 55 Topics10. Commercial Items
  • Definition of commercial item at FAR 2.101
  • Who determined a vendor purchase was for a
    commercial item? How was the decision made?
  • Government may look at a sample of commercial
    item Purchase Orders / Subcontracts

22
The 55 Topics19. Make or Buy Program
  • FAR 15.408 is a make-or-buy program
    incorporated into any of your contracts?
  • FAR 52.215-9, Changes or Additions to Make-or-Buy
    Program

23
The 55 Topics26. Truth In Negotiations
  • Public Law 87-653
  • FAR 15.403-4, Requiring Cost or Pricing Data
  • FAR 52.215-12, Subcontractor Cost or Pricing Data
    (OCT 1997)
  • Threshold?

24
The 55 Topics43. Single/Sole Source Procurements
  • CPSR Auditor will look at single/sole source
    purchase orders to determine if sole source is
    justified
  • Price reasonableness assessment will be performed
    on single/sole source Purchase Orders and
    single/sole source Subcontracts

25
The 55 Topics45. Small Business Program
  • FAR 19.7 The Small Business Subcontracting
    Program
  • FAR 52.219-8, Utilization of Small Business
    Concerns (MAY 2004)
  • FAR 52.219-9, Small Business Subcontracting Plan
    (APR 2008)
  • Thresholds?

26
The 55 Topics54. Specialty Metals
  • DFARS 225.7003-5(a)(1)
  • What clause applies to your contract?
  • DFARS 252.225-7014, Preference for Domestic
    specialty Metals (JUN 2005) (Deviation) Alternate
    1 (OCT 2007) or
  • DFARS 252.225-7008, Restriction on Acquisition of
    Specialty Metals
  • DFARS 252.225-7009, Restriction on Acquisition of
    Certain Articles Containing Specialty Metals
  • DFARS 252.225-2010, Commercial Derivative
    Military Article Specialty Metals Compliance
    Certificate

27
Buyer Training
  • At a minimum the Supply Chain Buyer should
    receive training on the following subjects
  • Overview of the Federal Acquisition Regulation
    (FAR)
  • Negotiation Techniques
  • Price Analysis / Cost Analysis
  • Writing a Price Negotiation Memorandum (PNM)
  • Truth in Negotiation Act (P.L 87-653)
  • Cost Accounting Standards (CAS) (P.L. 100-679)
  • DPAS (Title I of Defense Production Act of 1950)
  • Small Business Program (P.L. 95-507 of 1978)
  • Selecting Contract Types (FAR Part 16)
  • Commodity Specific Education
  • Ethics Training

26
28
Key Compliance Areas / Clause Flow Down
but first
29
How should a government contractor flow Federal
Acquisition Regulation (FAR) and Department of
Defense FAR Supplement clauses to its vendors?
  • Identifying them in full text on the Purchase
    Order?
  • Identifying them by reference on the Purchase
    Order?
  • By referring vendors to a FAR and DFARS clause
    list on their web site?
  • Dont bother, just include company standard
    terms and conditions on Purchase Orders?
  • Answer Refer to FAR 52.102 and 52.301
  • National Defense Industrial Association (NDIA),
    (703) 522-1820 or http//www.ndia.org 50.00

28
30
Key Compliance Areas / Clause Flow DownSource
Document
  • A Study of the Applicability of Federal
    Acquisition Regulation (FAR) Clauses to
    Subcontracts Under Prime Defense and NASA
    Contracts, including Defense FAR Supplement
    (DFARS) and NASA FAR Supplement (NFS)
  • National Defense Industrial Association (NDIA),
    (703) 522-1820 or http//www.ndia.org 50.00

29
31
Key Compliance Areas / Clause Flow Down
(examples)
  • What clauses are included in the prime contract ?
  • For exampleall values
  • 52.244-2, Subcontracts
  • 52.211-15, Defense Requirements and Allocation
    Requirements
  • Greater than 30,000
  • 52.209-6, Protecting the Governments Interest
    When Subcontracting with Contractors Debarred,
    Suspended, or Proposed for Debarment
  • Greater than 100,000
  • 52.203-11, Certification and Disclosure Regarding
    Payment to Influence Certain Federal Transactions
  • 52.219-8, Utilization of Small Business Concerns
  • EO 13496 Duty of Federal Contractors,
    Subcontractors to Notify Employees of Their Right
    to Form and Join Unions

30
32
Key Compliance Areas / Clause Flow Down
  • Greater than 550,000
  • 52.219-9, Small Business Subcontracting Plan
  • Greater than 650,000
  • 552.230-2, Cost Accounting Standards (P.L 100-679
    CAS Applicability and Disclosure Statement
    Determination)
  • P.L 87-653 Truth in Negotiation Act (TINA)

31
33
Summary
  • Establish a Process from PR initiation to PO
    issuance to receipt and acceptance or rejection
    of products or services, and FOLLOW IT
  • Rate vendors so you dont keep buying from poor
    providers
  • Allow the Supply Chain to focus on purely buying
    activities, emphasizing a need to negotiate with
    vendors
  • Justify single/sole source procurements and price
    reasonableness determinations
  • Track negotiated savings

32
34
References
  • FAR Subpart 44.3 Contractors Purchasing Systems
    Reviews
  • Http//guidebook.dcma.mil/26/guidebook_process.htm
  • DCAA Internal Control Matrix for CPSR/Purchasing
    System Audit

35
Questions?
34
Write a Comment
User Comments (0)
About PowerShow.com