Title: Porous Pavement and Model Municipal Operations Center Demonstration Project Phase II
1Porous Pavement and Model Municipal Operations
Center Demonstration Project Phase II
- Photo Document Project
- County of San Diego
- DEPARTMENT OF GENERAL SERVICES
- August 1, 2008
1
2Order of Review
- Overview of Phase I Results
- Treatment Train
- Site Preparation
- Construction
- Post Construction
- Porous Pavement
- Site Preparation
- Construction
- Post Construction
- Rain Event
- Results to Date
2
3Overview of Phase I
3
47
Porous Concrete 14,936 s.f.
Porous Asphalt 40,126 s.f.
Pavers 7,896 s.f.
Reference Area.
M12A
4
11
Porous Pavement Center COC 62,958 s.f.
5Cost Summary Porous Pavement
7
6PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS PHASE I PAVEMENT REPLACEMENT SQUARE FOOT COSTS
Demolition Excavation Installation of Sub Base Pavement Costs Square Foot Costs Annual Est. Square Foot Maintenance Costs Comments
Porous Asphalt 2.75 1.88 1.87 6.50 0.04 18" excavation/backfill. 3" porous asphalt.
Standard Asphalt 2.13 1.04 1.32 4.49 0.06 6"-Excavation/Backfill. 6"-Asphalt.
Porous Concrete 3.19 1.88 6.34 11.41 0.02 18"-Excavation/Backfill. 5-1/2" pervious concrete.
Standard Concrete 1.51 - 3.42 4.93 0.01 No new base material. 6"-Reinforced Concrete
Porous Pavers 2.75 1.88 9.63 14.26 TBD 18"-Excavation/Backfill. 3"-Paver.
Square foot cost are based on actual cost received by the County of San Diego. Square foot cost are based on actual cost received by the County of San Diego. Square foot cost are based on actual cost received by the County of San Diego. Square foot cost are based on actual cost received by the County of San Diego. Square foot cost are based on actual cost received by the County of San Diego. Square foot cost are based on actual cost received by the County of San Diego. Square foot cost are based on actual cost received by the County of San Diego.
8
7Phase I Treatment Train Schematic
5
8Targeted Pollutants of Concern
- Suspended Solids
- Oil/Grease
- Metals (Copper, Zinc, Chromium, Cadmium)
- Organics
- Nitrogen
- Note These are consistent between Phase I and
Phase II.
6
9Phase II
9
1010
Current and Proposed Porous Pavement and
Treatment Train Locations
11Phase II Expansion
- Three additional media filtration units
- Three additional porous paving test plots (54,000
sf) - One additional porous concrete test plot
- Two additional porous asphalt test plots
- Geogrid stabilization under 1/2 of each new
porous asphalt test plot - 26,000 sf of roof runoff diverted to porous
asphalt test beds - Enhanced monitoring to evaluate current/expanded
BMP effectiveness
11
12Phase II Treatment Train Schematic
12
1313
14TREATMENT TRAIN
Site Preparation
14
15TREATMENT TRAIN
15
Site Preparation and Excavation
16TREATMENT TRAIN
16
Excavation Around Phase 1 Treatment Train
17TREATMENT TRAIN
CONSTRUCTION
17
18TREATMENT TRAIN
20
Installation of MFS and Storm Filter Chambers
19TREATMENT TRAIN
21
Installation of MFS and Storm Filter Chambers
20TREATMENT TRAIN
26
Installation of Diversion Pipe and Monitoring
Boxes
21TREATMENT TRAIN
28
Backfilling Treatment Train
22TREATMENT TRAIN
Maintenance
30
23TREATMENT TRAIN
29
CONSTRUCTION
24TREATMENT TRAIN
31
MSF Unit Replacement Filter
25TREATMENT TRAIN
32
Filter Replacement of Phase 1 MSF Unit
26CDS PRE-TREATMENT CLEAN-OUT
33
After Three Rain Events
27POROUS PAVEMENT
Site Preparation
34
28POROUS PAVEMENT
35
Excavation Engraving
29POROUS PAVEMENT
CONSTRUCTION
37
30POROUS PAVEMENT
38
Installation of Subsurface Overflow Drainage and
Monitoring System
31POROUS PAVEMENT
39
CONSTRUCTION
3241
POROUS ASPHALT PROFILE
33POROUS PAVEMENT
44
Installation of Geotech Style Fabric and Aggregate
34POROUS PAVEMENT
45
Installation of Geogrip Re-enforcement
35POROUS PAVEMENT
52
Porous Asphalt Overlain Aggregate Bed
36POROUS PAVEMENT
50
Installation of Porous Asphalt
37POROUS ASPHALT PROFILE
46
38POROUS PAVEMENT
47
Installation of Porous Concrete
39POROUS PAVEMENT
48
Porous Concert Curing Process
40POROUS PAVEMENT
POST CONSTRUCTION
54
41POROUS PAVEMENT
55
Asphalt concrete Interface
42POROUS PAVEMENT
56
POST-CONSTRUCTION
43POROUS PAVEMENT
57
Porous Concrete Infiltration
44POROUS PAVEMENT
58
Porous Asphalt Infiltration
45POROUS PAVEMENT
59
Rain Event November 30, 2007
46POROUS PAVEMENT
60
RAIN EVENT (11/30/2007)
47POROUS PAVEMENT
61
RAIN EVENT (11/30/2007)
48POROUS PAVEMENT
62
RAIN EVENT (11/30/2007)
49POROUS PAVEMENT
63
RAIN EVENT (11/30/2007)
50Results to Date
64
51Porous Paving Treatments
65
- Rainfall and Runoff measured during 11 events
during the 2005-2006 wet season. - Events ranged from 0.23 inches to 1.07 inches
during Phase I monitoring. - All Three Porous Paving Treatments eliminated 100
percent of the runoff and associated contaminants.
52Infiltration Works!
66
5367
5468
55MFS Performance (Phase I)
69
- Perlite used as Media
- Initial data based upon only 3 events
- Effective at further removal of sediment
- Coarse sediments (gt63 µ) to lt1.8 mg/L.
- Fine sediments (lt63 µ) to lt14 mg/L
- Effective at further removal of contaminants
strongly associated with particulate contaminants - e.g. Total Lead concentrations reduced 27-60
percent
5670