Title: Hydropower Development Policy
1Hydropower Development PolicyRegulatory
Framework
- Keshab Dhoj Adhikari
- Senior Divisional Engineer
- Ministry of Water Resource
- 23 September 2008
2What Constitute HP Policy
- Hydropower Development Policy-2001
- Water Resources Strategy-2002
- Electricity Act 1992 Rules 1993
- Periodic plans, annual budget speech, EPA EPR,
custom tax provisions, etc.
3What Constitute HP Policy contd
- Other relevant Acts Regulations
- Foreign Investment and Technology Transfer Act
- Company Act
- Electricity Tariff Fixation Regulation, etc.
4Other important Acts on anvil
- Electricity Act and Rules (proposed)
- Nepal Electricity Regulatory Commission Act
(proposed)
5Institutions currently involved
- MoWR and DoED
- Electricity Tariff Fixation Committee
- Ministry of Environment, Science and Technology
- Ministry of Forest and Soil Conservation
6Objectives of HP-2001
- Generate electricity at low cost
- Provide reliable and quality electricity at a
reasonable price - Combine electrification with the economic
activities - Extend rural electrification and
- Develop hydropower as an export commodity
7Key Policy Provisions (HP-2001)
- Competition emphasized
- BOOT model first sector to adopt one (not under
the BOOT ACT) - In case of multipurpose projects, GoN may
participate - Environment- 10 d/s release (min)
- Facilitate property acquisition
8Key Policy Provisions (HP-2001) contd
- Water rights guaranteed
- Various provisions for RE
- No expropriation
- Foreign exchange facility for dividend and loan
- Additional 5 year term (max) for projects at risk
9Other Important Aspects of Policies
- Terms of License
- Survey License for 5 years
- Generation License
- Internal consumption 35 years
- Export Oriented 30 years
- In case of reservoir 5 years extension on the
basis of construction period - Captive Plant as it remains in operation
- Transmission and Distribution 25 years with ten
years renewable
10Some Important Aspects of Policies (contd..)
- Transfer of Projects
- Every hydropower project has to be transferred to
the government, free of costs, after the
completion of license period - Licensee has to involve the government in the
operation of the project two years prior to the
completion of license period
11Some Important Aspects of Policies (contd..)
- Utilization of Local Resources
- Developers are encouraged to-
- utilize Nepalese labour, skill, means and
resources to the maximum extent possible and have
to give priority to utilize local labour - carry out works in such a way so as to transfer
technology to the Nepalese citizens
12Private Sector Participation
-
- Ever since Hydropower Development Policy 1992
was formulated, Government hasnt turned back and
made adequate policy commitments for the
enhanced participation of private sector.
13Emerging Institutions
- Independent Electricity Regulatory Commission
(NERC) to replace ETFC with enhanced regulatory
role - Existing vertically integrated utility(ies) to be
unbundled - One agency will be allowed to do business either
generation or transmission or distribution - Separate Rural Electrification Fund
14Establishment of Grid Authority
- Operation and control of the National Grid shall
be in accordance with the Grid Code - A Licensee may transmit the electric powers
inside or outside the country by obtaining access
to the National Grid - No discrimination in accessing grid
15Special provisions in new EA
- gt100 kW developer-registered firm lt100 kW
individual and firm - After completion of submission, award of license
- Survey within 21 days
- Cap. lt10 MW within 60 days
- 10 MWltCap.lt50 MW within 90 days
- Cap.gt 50 MW within 120 days
- T D within 90 days Trade within 45 days
15
16Special provisions in new EA
- A developer to get license either for generation
or for transmission or for distribution except in
special cases - Security deposit for construction license
- Duration
- Survey license initially for 2 years and
extension up to a total maximum of 5 years - Generation 35 years for domestic consumption 30
years for export
16
17Special provisions in new EA
- Duration contd..
- 15 years for thermal
- 35 years for captive hydro and in case of captive
thermal till the industry is operated - May be extended by 5 years, at the most, for
storage projects - May be extended by 5 years, at the most, if the
project suffers from serious geological and
hydrological uncertainties - 25 years for transmission, distribution and
trading
17
18Provisions in new EA
- National Grid
- GoN, in consultation with NERC, to declare
national grid and its codes - Indiscriminate access to grid
- Power purchase import/export
- Price to be set on the basis of fixed percentage
of avoided cost or average tariff or ROE - Also by bidding following a NERC declared
procedure - NERC may declare other methods once power whole
sale market is established
18
19Provisions in new EA
- Import/Export
- Trade license for power import and export
- No separate export license needed for export
oriented generation licensee - GoN may ask for selling 10(max) of energy for
domestic consumption - Royalty (as per HP-2001)
- Applicable only for gt 2 MW projects
- Currency of royalty payment same as the currency
of power purchase
19
20Water rights environment
- Water rights ensured for generation period
- Downstream release of 10 of mean monthly flow or
as stipulated in approved EIA report whichever is
greater
20
21Land acquisition, resettlement
- Govt. land and forest area to be provided on
lease - Govt. to facilitate acquiring private land and
property - Developers to compensate for land and properties
thus acquired - Developers to prepare and implement RR plan
21
22Tax Exemption
- custom duty 1 of cost of imported material and
equipment and NO VAT - Above exemption only for the construction period
and applicable for spare parts also - No income tax for gt 2MW
- Income tax holiday for first 10 years after
commissioning and first 7 years incase of
transmission and distributio
22
23Other incentives
- 15 tax on the annual income for generation
companies - Expatriates to get other incentives like foreign
exchange, duty free and visa facilities - Protection from change in law regarding tax
exemption for the entire license period
23
24Some other important provisions
- No expropriation
- All power projects to be considered as Priority
Projects and incentives to be provided
accordingly - A bonus of 2 of net income (not exceeding annual
salary) for the employees the surplus in welfare
fund - Annual Reports to be submitted to NERC and DOED
24
25Draft NERC Act
- NERC- 5 man strong commission (including at least
a woman) - GON appoints Chairperson and members of NERC
- Recommendation Committee
- VC (NPC), Coordinator
- Power sector expert from private sector (GON
nominee), Member - MOWR Secretary, Member
25
26Draft NERC Act
- Eligibility criterion- Master degree in Economics
or Commerce or Management or Accounts or Law or
Engineering and a minimum of 10 years experience
in relevant field - 5 year term and can be reappointed for one more
term
26
27Roles and responsibilities
- Technical aspect
- Regulate for maintaining safety and quality
- Formulate policy and action plan for the
reliability and effectiveness of power system - Prepare OM procedure code
- Prepare and enforce Grid code and distribution
code - Review LCGE and see whether a project fits it
(not applicable for lt10 MW)
27
28Roles and responsibilities
- Tariff fixation
- Declare bases of tariff
- Determine wholesale price
- Determine PPA process and buy back rate for 1 to
10 MW plants - Fix wheeling charge and retail tariff
- Review and provide consent to PPAs, etc.
28
29Roles and responsibilities
- Maintain competition and protect consumers
interest - Avoid monopoly or find out ways and means to
avoid monopoly - Regulate merging, sale of plant, acquisition or
takeover, etc. - Capacity building and enhancing good governance
in companies - Advise GoN in related matters
29
30Roles and responsibilities
- Monitoring and inspection
- Dispute resolution
- Impose fines- up to Rs. 500,000.00
- Public hearing in the process of tariff fixation
- Employ a NGO to advocate on behalf of consumers
- NERC may review its own doing
30
31Some other provisions in NERC Act
- NERC will get 1 of revenue from companies
(except generation) - Appeal in Appellate Courts
31
32THANK YOU