Hydropower Development Policy - PowerPoint PPT Presentation

1 / 32
About This Presentation
Title:

Hydropower Development Policy

Description:

Other relevant Acts & Regulations Foreign Investment and Technology Transfer Act Company Act Electricity Tariff Fixation Regulation, etc. – PowerPoint PPT presentation

Number of Views:157
Avg rating:3.0/5.0
Slides: 33
Provided by: Rajendr5
Category:

less

Transcript and Presenter's Notes

Title: Hydropower Development Policy


1
Hydropower Development PolicyRegulatory
Framework
  • Keshab Dhoj Adhikari
  • Senior Divisional Engineer
  • Ministry of Water Resource
  • 23 September 2008

2
What Constitute HP Policy
  • Hydropower Development Policy-2001
  • Water Resources Strategy-2002
  • Electricity Act 1992 Rules 1993
  • Periodic plans, annual budget speech, EPA EPR,
    custom tax provisions, etc.

3
What Constitute HP Policy contd
  • Other relevant Acts Regulations
  • Foreign Investment and Technology Transfer Act
  • Company Act
  • Electricity Tariff Fixation Regulation, etc.

4
Other important Acts on anvil
  • Electricity Act and Rules (proposed)
  • Nepal Electricity Regulatory Commission Act
    (proposed)

5
Institutions currently involved
  • MoWR and DoED
  • Electricity Tariff Fixation Committee
  • Ministry of Environment, Science and Technology
  • Ministry of Forest and Soil Conservation

6
Objectives of HP-2001
  • Generate electricity at low cost
  • Provide reliable and quality electricity at a
    reasonable price
  • Combine electrification with the economic
    activities
  • Extend rural electrification and
  • Develop hydropower as an export commodity

7
Key Policy Provisions (HP-2001)
  • Competition emphasized
  • BOOT model first sector to adopt one (not under
    the BOOT ACT)
  • In case of multipurpose projects, GoN may
    participate
  • Environment- 10 d/s release (min)
  • Facilitate property acquisition

8
Key Policy Provisions (HP-2001) contd
  • Water rights guaranteed
  • Various provisions for RE
  • No expropriation
  • Foreign exchange facility for dividend and loan
  • Additional 5 year term (max) for projects at risk

9
Other Important Aspects of Policies
  • Terms of License
  • Survey License for 5 years
  • Generation License
  • Internal consumption 35 years
  • Export Oriented 30 years
  • In case of reservoir 5 years extension on the
    basis of construction period
  • Captive Plant as it remains in operation
  • Transmission and Distribution 25 years with ten
    years renewable

10
Some Important Aspects of Policies (contd..)
  • Transfer of Projects
  • Every hydropower project has to be transferred to
    the government, free of costs, after the
    completion of license period
  • Licensee has to involve the government in the
    operation of the project two years prior to the
    completion of license period

11
Some Important Aspects of Policies (contd..)
  • Utilization of Local Resources
  • Developers are encouraged to-
  • utilize Nepalese labour, skill, means and
    resources to the maximum extent possible and have
    to give priority to utilize local labour
  • carry out works in such a way so as to transfer
    technology to the Nepalese citizens

12
Private Sector Participation
  • Ever since Hydropower Development Policy 1992
    was formulated, Government hasnt turned back and
    made adequate policy commitments for the
    enhanced participation of private sector.

13
Emerging Institutions
  • Independent Electricity Regulatory Commission
    (NERC) to replace ETFC with enhanced regulatory
    role
  • Existing vertically integrated utility(ies) to be
    unbundled
  • One agency will be allowed to do business either
    generation or transmission or distribution
  • Separate Rural Electrification Fund

14
Establishment of Grid Authority
  • Operation and control of the National Grid shall
    be in accordance with the Grid Code
  • A Licensee may transmit the electric powers
    inside or outside the country by obtaining access
    to the National Grid
  • No discrimination in accessing grid

15
Special provisions in new EA
  • gt100 kW developer-registered firm lt100 kW
    individual and firm
  • After completion of submission, award of license
  • Survey within 21 days
  • Cap. lt10 MW within 60 days
  • 10 MWltCap.lt50 MW within 90 days
  • Cap.gt 50 MW within 120 days
  • T D within 90 days Trade within 45 days

15
16
Special provisions in new EA
  • A developer to get license either for generation
    or for transmission or for distribution except in
    special cases
  • Security deposit for construction license
  • Duration
  • Survey license initially for 2 years and
    extension up to a total maximum of 5 years
  • Generation 35 years for domestic consumption 30
    years for export

16
17
Special provisions in new EA
  • Duration contd..
  • 15 years for thermal
  • 35 years for captive hydro and in case of captive
    thermal till the industry is operated
  • May be extended by 5 years, at the most, for
    storage projects
  • May be extended by 5 years, at the most, if the
    project suffers from serious geological and
    hydrological uncertainties
  • 25 years for transmission, distribution and
    trading

17
18
Provisions in new EA
  • National Grid
  • GoN, in consultation with NERC, to declare
    national grid and its codes
  • Indiscriminate access to grid
  • Power purchase import/export
  • Price to be set on the basis of fixed percentage
    of avoided cost or average tariff or ROE
  • Also by bidding following a NERC declared
    procedure
  • NERC may declare other methods once power whole
    sale market is established

18
19
Provisions in new EA
  • Import/Export
  • Trade license for power import and export
  • No separate export license needed for export
    oriented generation licensee
  • GoN may ask for selling 10(max) of energy for
    domestic consumption
  • Royalty (as per HP-2001)
  • Applicable only for gt 2 MW projects
  • Currency of royalty payment same as the currency
    of power purchase

19
20
Water rights environment
  • Water rights ensured for generation period
  • Downstream release of 10 of mean monthly flow or
    as stipulated in approved EIA report whichever is
    greater

20
21
Land acquisition, resettlement
  • Govt. land and forest area to be provided on
    lease
  • Govt. to facilitate acquiring private land and
    property
  • Developers to compensate for land and properties
    thus acquired
  • Developers to prepare and implement RR plan

21
22
Tax Exemption
  • custom duty 1 of cost of imported material and
    equipment and NO VAT
  • Above exemption only for the construction period
    and applicable for spare parts also
  • No income tax for gt 2MW
  • Income tax holiday for first 10 years after
    commissioning and first 7 years incase of
    transmission and distributio

22
23
Other incentives
  • 15 tax on the annual income for generation
    companies
  • Expatriates to get other incentives like foreign
    exchange, duty free and visa facilities
  • Protection from change in law regarding tax
    exemption for the entire license period

23
24
Some other important provisions
  • No expropriation
  • All power projects to be considered as Priority
    Projects and incentives to be provided
    accordingly
  • A bonus of 2 of net income (not exceeding annual
    salary) for the employees the surplus in welfare
    fund
  • Annual Reports to be submitted to NERC and DOED

24
25
Draft NERC Act
  • NERC- 5 man strong commission (including at least
    a woman)
  • GON appoints Chairperson and members of NERC
  • Recommendation Committee
  • VC (NPC), Coordinator
  • Power sector expert from private sector (GON
    nominee), Member
  • MOWR Secretary, Member

25
26
Draft NERC Act
  • Eligibility criterion- Master degree in Economics
    or Commerce or Management or Accounts or Law or
    Engineering and a minimum of 10 years experience
    in relevant field
  • 5 year term and can be reappointed for one more
    term

26
27
Roles and responsibilities
  • Technical aspect
  • Regulate for maintaining safety and quality
  • Formulate policy and action plan for the
    reliability and effectiveness of power system
  • Prepare OM procedure code
  • Prepare and enforce Grid code and distribution
    code
  • Review LCGE and see whether a project fits it
    (not applicable for lt10 MW)

27
28
Roles and responsibilities
  • Tariff fixation
  • Declare bases of tariff
  • Determine wholesale price
  • Determine PPA process and buy back rate for 1 to
    10 MW plants
  • Fix wheeling charge and retail tariff
  • Review and provide consent to PPAs, etc.

28
29
Roles and responsibilities
  • Maintain competition and protect consumers
    interest
  • Avoid monopoly or find out ways and means to
    avoid monopoly
  • Regulate merging, sale of plant, acquisition or
    takeover, etc.
  • Capacity building and enhancing good governance
    in companies
  • Advise GoN in related matters

29
30
Roles and responsibilities
  • Monitoring and inspection
  • Dispute resolution
  • Impose fines- up to Rs. 500,000.00
  • Public hearing in the process of tariff fixation
  • Employ a NGO to advocate on behalf of consumers
  • NERC may review its own doing

30
31
Some other provisions in NERC Act
  • NERC will get 1 of revenue from companies
    (except generation)
  • Appeal in Appellate Courts

31
32
THANK YOU
Write a Comment
User Comments (0)
About PowerShow.com