About This Presentation
Title:

Development of Rail Infrastructure in the North East Region

Description:

Development of Rail Infrastructure in the North East Region. Ministry of Railways . New Delhi. 08.06.2012 – PowerPoint PPT presentation

Number of Views:132
Avg rating:3.0/5.0
Slides: 50
Provided by: mdonerGo
Category:

less

Write a Comment
User Comments (0)
Transcript and Presenter's Notes

Title: Development of Rail Infrastructure in the North East Region


1
Development of Rail Infrastructure in the North
East Region
Ministry of Railways New Delhi 08.06.2012
2
OBJECTIVES
  • Connectivity to all State Capitals .
  • Strengthening International Borders Improving
    trade and connectivity with neighbouring
    countries.
  • Augmentation of network capacity for handling
    growth of traffic in future.
  • Uni-gauge Broad gauge network.
  • Expansion of network to unconnected areas of the
    region.

3
SCENARIO IN THE NORTH EAST REGION - 1990
  • Broad Gauge Line Upto Guwahati. All lines beyond
    Guwahati were MG lines.
  • Only One route between New Jalpaiguri to
    Guwahati. No alternative in case of disruption
    due to floods, accidents, bandhs, strikes etc.
  • Mostly Single BG Line beyond Katihar and Malda.
  • Most Express Trains Take 40 to 48 hrs upto
    Guwahati from Delhi.
  • Time taken to reach Dibrugarh/Tinsukia upto 65
    hours.from Delhi.
  • Only One Railway Bridge across River Brahmaputra
    Rail-cum-Road Bridge at Saraighat (Guwahati)
  • Along North Bank of Brahmaputra MG Line from
    Rangiya to Murkongselek.
  • No Connectivity to Capital city of any State
    except Assam.

4
SCENARIO IN THE NORTH EAST REGION - 2010
  • Broad Gauge Line Upto Dibrugarh and Tinsukia
    Gauge Conversion of Guwahati Tinsukia
    Dibrugarh completed including Furkating Jorhat
    Mariani and Simaluguri Sibsagar Moranhat
    Branch Lines.
  • A Complete alternative BG route from New
    Jalpaiguri to Guwahati commissioned by Gauge
    Conversion of Siliguri-New Jalpaiguri-New
    Bongaigaon MG Line and Jogighopa Guwahati New
    Line.
  • Rajdhani Express introduced which Takes 28 hrs
    upto Guwahati from Delhi.
  • Time taken to reach Dibrugarh/Tinsukia 40
    hours from Delhi.
  • Second Railway Bridge across River Brahmaputra
    Rail-cum-Road Bridge at Jogighopa opened.
  • Capital of Tripura (Agartala) connected by MG
    line.

5
SCENARIO IN THE NORTH EAST REGION - 2020
  • All the State Capitals will be on Broad Gauge.
  • A third alternative BG route from New Maynaguri
    to Jogighopa will be commissioned.
  • Doubling of New Jalpaiguri Samuktala will be
    completed.
  • The Entire Barak Valley will be on BG network.
  • Third Railway Bridge across River Brahmaputra
    Rail-cum-Road Bridge at Bogibeel will be
    completed.
  • Entire North Bank of Brahmaputra will be on BG
    network and get connected to South Bank at
    Dibrugarh through Bogibeel.

6
RAILWAY NETWORK IN NE REGION
Year Length of BG Route Length of MG Route Length of NG Route Total
1990 772.47 2986.56 87.48 3846.51
2010 2775.72 1389.80 87.48 4253.00
2020 5806.14 50 87.48 5943.62
7
RAILWAY INVESTMENT IN NORTH EAST REGION
  • Outlay 2012-13 Rs. 2333 crores for NE Region
    out of Total Budget Outlay of Rs 9875 cr. for
    entire Indian Railways for NL, GC Doubling
    Projects.

Year Rs. Cr.
2005-06 597.01
2006-07 840.85
2007-08 978.95
2008-09 1398.09
2009-10 1870.00
2010-11 2196.90
2011-12 2200.00
Total 10081.80
8
PROJECT OVERVIEW
Plan Head New Line Gauge Conversion Doubling Railway Electri-fication Total
Projects in progress 13 4 1 1 19
Total Cost 22575.88 7504.57 246.07 821 31147.52
Cumulative Expenditure up to March12 5080.16 5347.61 0 295 10722.77
Throw forward in Rs. crore as on 01.04.2012 12522 2851 0 526 20424.75
Length of ongoing works (Km) 965 1510 (893) 44.92 836 3355.92
National Projects (no.) 8 2 - - 10
9
ONGOING RAILWAY PROJECTS IN THE NORTH EAST REGION
10
ONGOING PROJECTS- NEW LINES
S. No Name of Project State Length (km) Remarks
1 Bogibeel Rail cum Road Bridge Assam 73 National Project
2 New Maynaguri-Jogighopa Assam W.Bengal 235.2
3 Tetaliya (Azra)-Byrnihat Meghalaya, Assam 30 National Project
4 Dudnoi-Mehendipather Meghalaya, Assam 19.75
5 Byrnihat Shillong Meghalaya 108 National Project
6 Harmuti-Itanagar Arunachal, Assam 33
11
ONGOING PROJECTS- NEW LINES
S. No Name of Project State Length (km) Remarks
7 Bhairabi- Sairang (Aizwal) Mizoram 51.38 National Project
8 Jiribam-Tupul (Imphal) Manipur 98 National Project
9 Dimapur-Zubza (Kohima) Nagaland 123 National Project
10 Sivok - Rangpo Sikkim, West Bengal 53 National Project
11 Agartala- Sabroom Tripura 110 National Project
12 Murkongselek - Pasighat Arunachal, Assam 30.62 Defence funded
13 Agartala-Akhaura (Bangladesh) Tripura, Bangladesh 13 Funded by MEA DoNER
12
ONGOING PROJECTS - GAUGE CONVERSION, DOUBLING
RAILWAY ELECTRIFICATION
S. No. Name of Project Name of Project State State Length (km) Length (km) Length (km) Remarks
Gauge Conversion Gauge Conversion Gauge Conversion Gauge Conversion Gauge Conversion Gauge Conversion Gauge Conversion Gauge Conversion Gauge Conversion
1 Lumding-Silchar-Jiribam Badarpur-Kumarghat Lumding-Silchar-Jiribam Badarpur-Kumarghat Lumding-Silchar-Jiribam Badarpur-Kumarghat Assam, Tripura, Manipur Assam, Tripura, Manipur 368 National Project National Project
2 Rangia-Murkongselek alongwith linked fingers Rangia-Murkongselek alongwith linked fingers Rangia-Murkongselek alongwith linked fingers Assam, Arunachal Pradesh Assam, Arunachal Pradesh 510 National Project National Project
3 Katakhal-Bhairabi Katakhal-Bhairabi Katakhal-Bhairabi Assam, Mizoram Assam, Mizoram 84
4 New Jalpaiguri-New Bongaigaon. Chalsa Naxalbari NL extn. New Jalpaiguri-New Bongaigaon. Chalsa Naxalbari NL extn. New Jalpaiguri-New Bongaigaon. Chalsa Naxalbari NL extn. Assam, West Bengal Assam, West Bengal Extension in progress. Extension in progress.
Doubling Doubling Doubling Doubling
1 Lumding-Hojai Doubling Lumding-Hojai Doubling Lumding-Hojai Doubling Assam Assam 44.92 Sanctioned in 2012-13 Sanctioned in 2012-13
Railway Electrification Railway Electrification Railway Electrification Railway Electrification Railway Electrification Railway Electrification Railway Electrification Railway Electrification Railway Electrification
1 Barauni Katihar-Guwahati Bihar, West Bengal, Assam Bihar, West Bengal, Assam Bihar, West Bengal, Assam Bihar, West Bengal, Assam 836
13
CONNECTIVITY TO STATE CAPITALS
S. No State Capital Name of Project Remarks Target date
1 Assam Guwahati (Dispur) Already connected.
2 Arunachal Pradesh Itanagar Harmuti-Itanagar (Naharlagun) Track linking in 20 Km done. It will be commissioned in March,2013 along with Rangapara Murkongselek GC.
3 Manipur Imphal Jiribam-Tupul Jiribam-Tupul March,2014 Tupul-Imphal March, 2016
4 Nagaland Kohima Dimapur-Zubza March, 2015(T)
14
CONNECTIVITY TO STATE CAPITALS
S. No State Capital Name of Project Remarks Target date
5 Mizoram Aizwal Bhairabhi-Sairang March, 2015 Extn. to Aizwal will be examined during detailed survey
6 Tripura Agartala Kumarghat-Agartala Commissioned (Oct.08) on dual gauge
7 Meghalaya Shillong Tetaliya(Azra)-Byrnihat-Shillong Tetaliya(Azra) -Brynihat - March, 2014
8 Sikkim Gangtok Sivok-Rangpo Sivok-Rangpo taken up. Dec 2015. Proposal of Rangpo-Gangtok processed. Min. of Fin. Has not agreed to take up this part as National Project.
15
FUNDING
  • As per the policy of the government, 10 of net
    budgetary support is to be spent in the region.
  • Non-lapsable rail development fund for national
    projects of NE Region has been approved by CCI.
    Contribution to this Fund is 25 through railway
    gross budgetary support and 75 as additionality
    by ministry of finance.

16
RAILWAY NETWORK IN N E REGION (As on 01.04.12)
State BG MG Total Km
Arunachal Pra. - 1.26 1.26
Assam 1443.03 990.96 2433.99
Tripura - 151.40 151.40
Nagaland 11.13 1.72 12.85
Manipur - 1.35 1.35
Mizoram - 1.50 1.50
Meghalaya - - -
Sikkim - - -
Total 1387.35 1214.40 2602.35
17
NORTH EAST REGION VISION 2020
  • MAIN FEATURE CONNECTIVITY TO ALL STATE
  • CAPITALS
  • STATE CAPITAL OF ASSAM TRIPURA CONNECTED.
  • NEW LINES TAKEN UP FOR CONNECTING CAPITALS OF
    ARUNACHAL PRADESH, MANIPUR, NAGALAND, MIZORAM,
    MEGHALAYA.
  • NEW LINES FOR PART LENGTH TAKEN UP FOR SIKKIM
    FROM SIVOK TO RANGPO. THE PROPOSAL FOR EXTENSION
    TO GANGTOK SENT TO PLANNING COMMISSION.

18
RAILWAY PROJECTS IN ASSAM
19
RAILWAY PROJECTS IN ASSAM
20
Bogibeel Rail cum Road Bridge (73 km) National
Project - ASSAM
Latest Cost Rs.3230 cr.
Exp. Mar12 Rs.2406 cr. TDC December, 2015
Outlay 12-13 Rs. 330cr. Overall Progress 74
Present Status Issues of concern
Moranhat-Chalkhowa link completed. (44 km) Construction of major bridge sub-structure in progress. Guide bunds in advance stage. Major bridge super structure contract awarded. Mobilization Work started. Land acquisition for road links. Frequent disruptions due to militant activities.
21

New Maynaguri-Jogighopa (235.2 km) ASSAM WEST
BENGAL
Latest Cost Rs.1655.80 cr.
Exp. Mar12 Rs.990.45 cr. TDC March, 2014 (Subject to fund availability)
Outlay 12-13 Rs. 225cr. Overall Progress 64.80
Present Status Areas of Concern
Work planned in four phases. Earthwork bridges in progress in all phases. 1st Phase-New Coochbehar-Golakganj (57.6 km) Physical works Completed in March 11. Progress of New Changrabanda- New Coochbihar is affected in West Bengal due to obstruction from land owners.
22
Gauge Conversion of Lumding-Silchar-Jiribam
Badarpur-Kumarghat (368.35 km) (National Project)
ASSAM,TRIPURA,MANIPUR
Latest Cost Rs.4255.4 cr.
Exp. Mar12 Rs.3141.68 cr. TDC Dec 2013
Outlay 12-13 Rs. 400cr. Overall Progress 71.80
Present Status Areas of Concern
Earthwork, Tunnel bridgeworks etc in progress. Progress of work affected due to insurgency problem in the hill section. MHA to coordinate for security arrangements Transfer of small area of land by defence authorities and forest department. Land acquisition in Hailakandi, Cachar and Karimganj Districts. Poor road condition in NC Hills area to be improved by NHAI/State Government.
23
Gauge Conversion of Rangia-Murkongselek with
linked fingers(510 km) (National
Project) ASSAM,ARUNACHAL PRADESH
Latest Cost Rs.1717.29 cr.
Exp. Mar12 Rs.1055.17 cr. TDC March, 2014
Outlay 12-13 Rs. 380 cr. Overall Progress 64.80
Present Status Areas of Concern
Earthwork bridgeworks etc are in progress in full length. Rangapara North- Rangia completed in March 12 Targets Rangpara North-North Lakhimpur March 2013 North Lakhimpur- Murkongselek- March 2014 Security arrangements.
24
Gauge Conversion of Katakhal-Bhairabi (84 km)
ASSAM,MIZORAM
Latest Cost Rs.223.01 cr.
Exp. Mar12 Rs. 121.17cr. TDC Mar 14
Outlay 12-13 Rs. 15cr. Overall Progress 47
Present Status Areas of Concern
Work is in progress. The commissioning will be dovetailed with Lumding-Silchar Gauge Conversion Land acquisition to be expedited by State Government in Hailakandi District.
25
RAILWAY PROJECTS IN MEGHALAYA
26
RAILWAY PROJECTS IN MEGHALAYA
27
Dudhnoi-Mehndipathar (19.75 km) MEGHALAYA, ASSAM
Latest Cost Rs.178.47 cr.
Exp. Mar12 Rs.60.11 cr. TDC March, 2013
Outlay 12-13 Rs.20 cr. Overall Progress 45.08
Present Status Areas of Concern
Land acquisition completed except Meghalaya portion Earthwork, bridges etc in progress. Delay in land acquisition by State Government. All land in 9.5 km received in Assam but land acquisition in Meghalaya is slow. Frequent bandhs called by Rabha Community.
28
Tetaliya (Azra)-Byrnihat (21.5 km) National
Project MEGHALAYA, ASSAM
Latest Cost Rs.385.2 cr.
Exp. Mar12 Rs. 106.05 cr. TDC March 2014
Outlay 12-13Rs. 70 cr. Overall Progress 2
Present Status Area of Concern
Due to public resistance, alternative alignment Tetelia-Brynihat examined and found feasible. Land acquisition papers have been submitted to State Government. Land acquisition to be expedited by State Government of Assam and Meghalaya.
29
Byrnihat-Shillong (108.4 km) National
Project MEGHALAYA, ASSAM
Latest Cost Rs.4083 cr.
Exp. Mar12 1.81 cr. TDC March 2017
Outlay 12-13 Rs.30cr. Overall Progress Nil
Present Status Area of Concern
Final Location Survey in progress. Tender for geo-tech investigation awarded and work in progress. Khasi Students Union stopped the work of FLS Geotech Investigation.
30
RAILWAY PROJECTS IN ARUNACHAL PRADESH
31
RAILWAY PROJECTS IN ARUNACHAL PRADESH
32
Harmuti-Itanagar (33 km) ARUNACHAL PRADESH, ASSAM
Latest Cost Rs.-254.29 cr. Harmuti-Naharlagun (20 km)
Exp. Mar12 Rs.160.72 cr. TDC March, 2012 (Upto Naharlagun)
Outlay 12-13 Rs.87 cr. Overall Progress 95
Present Status Area of Concern
State Government has agreed to terminate line at Naharlagun. Work completed in Mar,12
33
RAILWAY PROJECTS IN NAGALAND
34
RAILWAY PROJECTS IN NAGALAND
35

Dimapur-Zubza-Kohima (123 km) National
Project NAGALAND
Latest Cost Rs.850 cr.
Exp. Mar12 Rs.8.97 cr. TDC March, 2015(T)
Outlay 12-13 Rs.7 cr. Overall Progress 1
Present Status Area of Concern
Extension of line upto Kohima found feasible. Tentative alignment approved by State Govt. total length 123 km. Final Location Survey completed for entire length. State Government had requested for change of alignment for 1st 18 km. Proposal for modified alignment was found feasible. Now State Govt. has advised on 17.8.10 that original alignment should be retained. Land rates given by State Government were very high. Reduced rates received recently. State Government to communicate approval for alignment passing through zoological park.
36
RAILWAY PROJECTS IN MANIPUR
37
RAILWAY PROJECTS IN MANIPUR
38
Jiribam-Imphal (125 km) National Project MANIPUR
Latest Cost Rs.4444 cr.
Exp. Mar12 Rs. 795.18 cr. Target March, 2014 upto Tupul March, 2016 upto Imphal
Outlay 12-13 Rs.450 cr . Overall Progress 24
Present Status Action by Center Govt.
Earthwork, bridges and tunneling in progress in Jiribam-Tupul section. Jiribam-Dholakal 12.5 km completed in 11-12 Tupul-Imphal Survey also completed. Security situation in Manipur and frequent prolonged bandhs. Condition of road and bridges on NH 53 need to be strengthened.
39
RAILWAY PROJECTS IN MIZORAM
40
RAILWAY PROJECTS IN MIZORAM
41
Bhairabi-Sairang (51.38 km) National
Project MIZORAM
Latest Cost Rs. 2384.41 cr .
Exp. Mar12 Rs. 2.89 cr Target March, 2015
Outlay 12-13 Rs. 80 cr. Overall Progress 0.1
Present Status Area of Concern
Final Location Survey and geo-tech investigation taken up. FLS completed and alignment staked on ground. 3 Km geotech investigation completed. Expeditious land acquisition and forest clearance by State/Central Governments. State Government to provide security
42
RAILWAY PROJECTS IN TRIPURA
43
RAILWAY PROJECTS IN TRIPURA
44
KUMARGHAT-AGARTALA(109km) NATIONAL PROJECT TRIPURA
  • Completed and Commissioned in October 2008 with
    meter gauge on dual gauge sleepers.
  • Will be converted to broad gauge once
    Lumding-Silchar-Kumarghat is converted.

45
Agartala-Sabroom (110 km) National Project
TRIPURA
Latest Cost Rs. 1141.75 cr.
Exp. Mar12 Rs. 320.74 cr Target March, 2014
Outlay 12-13 Rs. 180cr. Overall Progress 31
Present Status Area of Concern
About 50 land acquired and earthwork, bridges etc taken up. Agartala-Udaipura is targeted for Dec 2012. 10km completed in 2011-12. Acquisition of forest land. Survey for land could not be done for 5 km near Bishalgarh due to opposition by local villagers. This need to be resolved. State Government to expedite land acquisition.
46
RAILWAY PROJECTS IN SIKKIM
47
RAILWAY PROJECTS IN SIKKIM
48
Sivok Rangpo (52.70 km) - Sikkim
Latest Cost Rs. 3380 cr.
Exp. Mar12 Rs. 87.63 cr Target Dec, 2015(T)
Outlay 12-13 Rs.38cr. Overall Progress 0.1
Present Status Area of Concern
Work has been entrusted to IRCON for execution. FLS completed. IRCON has started the development of the project. Line is passing through dense forest and will require acquisition of forest land. Expeditious acquisition of land by State Government.
49
THANK YOU