Title: Prisma Plus the tested switchboard, complying with standard IEC 60 439-1
1Prisma Plus the tested switchboard,complyin
g with standard IEC 60 439-1
2Contents
- The low voltage electrical switchboard
- The functions of an electrical switchboard
- Prisma Plus a structured switchboard based on
functional units
- Forms partitioning
- Forms separations within an assembly
- The minimum requirements to guarantee the safety
of a LV switchboard
- The tests of standard IEC 60439-1
- 7 type tests performed by the manufacturer
- 3 routine tests performed by the panelbuilder
- Switchboard builders and manufacturer, together
for the safety challenge IEC 60439-1
- Prisma Plus and the IEC 60439-1 standard an
international influence
3The low voltage switchboard
- A vital link for electrical distribution
- To satisfy the increasing needs of safety of
people and equipment and availability of
electrical power its realization is not
improvised
Safety
Reliability
Availability
Maintenability
- and to provide a continual balance between
- the needs of safety and availability
- and the constraints of reliability and
maintenability of the installation.
Contents
Definitions
4The low voltage electrical switchboard
- The safety is the aptitude of a system not to put
the people in danger .
- Availibilty is the percentage of time during
which the system functions correctly. MTBF (Mean
Time Between Failure) average time between two
failures of a reparable system is a means of
characterizing the availibility.
- Reliability is the aptitude of a system to
function correctly as long as possible. MTTF
(Mean Time To Failure) average time of good
working before the first failure is a means of
characterizing the reliability.
- Maintainability is the aptitude of a system for
being repaired quickly.La maintenabilité est
l'aptitude d'un système à être réparé rapidement.
MTTR (Mean Time To Repair) the average duration
of repair is a means of characterizing
maintainability.
Back
5The functions of an electrical switchboard
- To group and protect against external influences
the protection and control devices and all their
electrical and mechanical connections.
- To inform the end-user on the state of his
installation
- To protect the switchboard user against the risk
of accidents (direct and indirect contact). -
- To evolve with the activity.
Contents
Definitions
Cubicles up to 3200 A
Wall-mount and floor standing enclosures up to
630 A
6The functions of an electrical switchboard
- Definitions
- Some of the components or specificities of the
switchboard realize and/or guarantee its
finalities, - in functional term
- The architecture of LV network in centralized
distribution - It results in a cutting into various switchboard,
wall-mount enclosures... Distributed
geographically, which - carry out the installation drawing.
- Then various areas are defined within the
switchboard - equipment
- busbar
- connection
- auxiliary
- The distances from minimal insulation and safety
must already be respected.
- The functional units
- allow to realize the electrical functions
correspondint to the user s - each unit is intended to cover a function, for
example - - the incoming of current in the switchboard
- - the protection of a feeder or a feeders
whole- the motor control...
- The enclosure
- It materializes electric volume and ensures
simultaneously - the protection of electrical materials which it
contains against the external influences - the protection of people against electrical
shocks (direct and indirect contacts).
Back
7The IEC 60439-1 standard
- The IEC 60439-1 standard gives general rules for
switchboards construction to meet with safety
and availability needs required by the
application - guarantees the minimum level of safety of people
and equipment - concerns the low-voltage switchgear and
controlgear assemblies for the power
distribution and control. - states
- - the service conditions (temperature...)
- - the construction requirements (IP, IK,
forms,...) - - the tests requirements
- So conformity to the standard is, for the end
user, an insurance on switchboard realization
quality.
Contents
8Prisma Plus a structured switchboard based on
functional units
- This modular design brings much clearness to the
switchboard - incoming unit
- current distribution units
- feeder units
- distribution units
- connection units
- communication units
Contents
Definitions
9IEC 60439-1 Standard and Prisma Plus a
structured switchboard based on functional units
Definitions
- Incoming units incoming circuit breaker
(Masterpact, Compact NS, Interpact INS...).
- Current distribution units busbars (Linergy,
flat bars, Powerclip...).
- Feeder units feeders circuit-breaker and
contactors (Compact NS, Interpact INS, switch
INV, modulars devices...).
- Each device is part of a functional unit
comprising - a dedicated mounting plate for device
installation - a front plate to block direct access to live
parts - prefabricated busbar connections
- systems for on-site connections
- running of cables and auxiliary wires
- Connection units insulated flexible bars,
prefabricated junction
- Distribution units distribution block
(Polypact, Polybloc, Multiclip, terminal
block...).
- Communication units measurement devices, BP,
Powerlogic, Digipact (Human/swichboard Interface).
Back
10Forms partitioning
- In most installations, Prisma Plus cubicles do
not require partitioning, Schneider Electric
offering options and features that go well
beyond the recommendations of the standard - front plates requiring a tool to be removed
- doors providing access to live parts are
keylocked - systematic installation of terminal shields on
Compact NS circuit breakers and Interpact INS and
INV switch-disconnectors - upstream and downstream terminals on the incoming
device are covered - The protection of people and equipment is ensured
on origin - However, Prisma Plus offers different levels of
partitioning to create separations inside the
cubicles and thus create Form 2,3 and 4, as
defined by the standard.
Contents
11Forms separations within an assembly
Prisma Plus
Prisma Plus
Prisma Plus
Prisma Plus
Contents
Definitions
12Forms separations within an assembly
Definitions
- Form 1 no separation within the enclosure.
- Form 2a the functional units are separated from
busbars, but not the terminals
- Form 2b the functional units and terminals are
separated from the busbars. The terminals are not
separated from each other.
- Form 3a the functional units are separated from
each other and from the busbars , but not the
terminals.
- Form 3b the functional units are separated from
each other and from the busbars. Terminals are
separated from busbars, but are not separated
from each other
- Form 4a the functional units are separated from
each other and from the busbars . Terminals which
are in the same compartment as the associated
functional unit are separated from each other
- Form 4b the functional units are separated from
each other and from the busbars. Terminals are
separated from each other and from the
functional units.
Back
13The minimum requirements to guarantee the
reliability of a LV switchboard
- First of all, it must comply with standards
- Switchboard construction standard
- IEC 60439-1 low voltage switchgear assemblies.
- Structural standards for incorporated switchgear
- IEC 60947-1 general provisions
- IEC 60947-2/3 circuit-breakers/switches
- IEC 60269-1 low voltage fuses.
- Installation standards
- IEC 60364 buildings electrical installation
- specific standards and rules to each country.
Contents
14The tests of standard IEC 60439-1
They guarantee that the switchboard complies with
standard and confirm its characteristics
- 7 type tests
- n1 - temperature rise limits
- n2 - dielectric properties
- n3 - short-circuit withstand
- n4 - protective circuit effectiveness
- n5 - clearances and creepage distances
- n6 - mechanical operation
- n7 - degree of protection
- 3 routine tests
- n8 - overall inspection cabling, electrical
operation - n9 - insulation/dielectric test
- n10 - protection measures .
Contents
157 type tests performed by the manufacturer
- The aim of these tests is to confirm the
switchboard characteristics.
- The 7 type tests are carried out on most
difficult and unfavourable system Prisma Plus
configurations. The assembled and cabled
switchboards are made up of their usual
components, connection system, equipped with
Merlin Gerin and Telemecanique switchgear and
assemblied and installed according to inductrial
standards
- The tests are conducted either in approved
laboratories (Asefa, Kema, Lcie,), or in
Schneider Electric ones
Contents
16Test n1(8-2-1) Temperature rise limits
- Guarantees the safety and reliability of the
switchboard, by avoiding problems such as - connection damages
- reduction in insulation performances
- risk of burn for maintenance operators
- electronic components damages
- faulty operation of the devices inopportune
release
Conditions
Contents
Results
17Test n1(8-2-1) Temperature rise limits
- Tests progress
- several switchboard configurations
- equipped with Merlin Gerin and Telemecanique
switchgear - 10 Clt ambient air temperaturelt40 C
- switchgear loaded to its rated current,
multiplied by the rated diversity factor
- Complying limits (temperature rise limits)
- when the temperature has stabilised, the
temperature rise should not exceed limits
admitted by materials or cause any burn - 70 C for terminal for external insulated
conductors - 15 C or 25 C , according to material type , for
manual operating means - 30 C or 40 C for accessible external enclosures
and covers
Back
18Test n1(8-2-1) Temperature rise limits
- The tests conducted with Prisma Plus have
recorded temperature rises less than or equal to
those stipulated by the standard.
Back
19Test n2 (8-2-2) dielectric properties
- Guarantees the switchboard safety and
reliability , to avoid problems such as - electrical arc generation
- insulation performance decreasing
- connection damages
Conditions
Contents
Results
20Test n2 (8-2-2) dielectric properties
Conditions
- Tests progress
- the test voltage is applied between all live
parts and interconnected exposed conductive parts
(frame), as well as between each pole and all the
other connected poles - dielectric test voltage
- - 3500 V for a rated insulation voltage 1000
V for busbars in cubicle and rear busbars in
enclosures - - 750 V for a rated insulation voltage 3000 V
according to the type of busbars in enclosure - - 500 V for a rated insulation voltage 2500 V
according to the type of busbars in enclosure - test duration 1 minute.
- Complying limits
- No arc flash-over or insulator perforation are
observed.
Back
21Test n2 (8-2-2) dielectric properties
- No arc flashover or insulator perforation for
the test voltage following the rated voltage of
busbars
Back
22Test n3 (8-2-3) short-circuit withstand
- This test simulates an incident which could occur
on site
- Withstanding the short-circuit currents is
- to avoid danger (rupture and projections of
components, arc generation and propagation
outside the switchboard,...) - it also means the installation can be quickly put
back into operation after the incident
Conditions
Contents
Results
23Test n3 (8-2-3) short-circuit withstand
Conditions
- Tests progress
- the short-circuit tests are carried out by using
bolted connections at the ends of the main or
secondary busbars - 25 kA rms/1 sec. for Prisma Plus System G
- 85 kA rms/1 sec. for Prisma Plus System P
- Complying limits
- the main conductors and the insulating parts must
retain their insulation and mechanical withstand
characteristics (lenght, cross-section,
dielectric properties,).
Back
24Test n3 (8-2-3) short-circuit withstand
- After a short-circuit test, the Prisma Plus main
conductors and the insulating parts keep on their
insulation and mechanical withstand
characteristics
- maximum rated short-time currents on busbars
- Prisma Plus System G Icw 25 kA rms/1 s
- Prisma Plus System P Icw 85 kA rms/1 s.
- the installation can be quickly put back into
operation after a simple inspection
Back
25Test n4 (8-2-4) effectiveness of the
protective circuit
- The effectiveness of the protective circuit is
verified by two tests - resistance measurement of the connection between
the exposed conductive parts and the protective
circuits - short-circuit withstand performed between the
protective conductor and the nearest phase
conductor.
Conditions
Contents
Results
26Test n4 (8-2-4) effectiveness of the
protective circuit
Conditions
- Tests progress
- the short-circuit tests are carried out by using
bolted connections at the ends of the main or
secondary busbars - 15 kA rms/1sec. for Prisma Plus System G
- 51 kA rms/1sec. for Prisma Plus System P.
- Complying limits
- the main conductors and the insulating parts must
retain their insulation and mechanical withstand
characteristics (lenght, cross-section,
dielectric properties,).
Back
27Test n4 (8-2-4) effectiveness of the
protective circuit
- After the test, continuity and short-circuit
withstand of the protective circuit, whether it
consists of a separate conductor or frame, is not
significantly impaired
- Continuity and short-circuit withstand of the
Prisma Plus protective circuit comply with the
standard.
Back
28Test n5 (8-2-5) clearance and creepage
distances
- Clearance control shortest distance between
two conductive parts. - Creepage distance control shortest distance
along the surface of an insulating material
between two conductive parts.
Conditions
Contents
Results
29Test n5 (8-2-5) clearance and creepage
distances
Conditions
- The values given in the standard apply to bare
live conductors and the switchgear.
- The minimum clearance in air depends on the rated
impulse withstand voltage and the degree of
pollution in the switchboard.
- The minimum creepage distance depends on the
rated insulation voltage, the degree of pollution
and the insulating material group separating live
parts.
Back
30Test n5 (8-2-5) clearance and creepage
distances
- The tests carried out on typical Prisma Plus
configurations, equipped with standard main
busbars, validate compliance with minimum
clearances and creepage distances for a voltage
of 1000V, degree of pollotion 3, IIIa material
group. - minimum clearance 14 mm
- minimum creepage distance 16 mm.
Back
31Test n6 (8-2-6) mechanical operation
- Endurance of material, guaranteeing the longevity
of the various mechanisms.
Conditions
Contents
Results
32Test n6 (8-2-6) mechanical operation
Conditions
- The mechanical operation test is carried out on
an assemblied switchboard.
- The standard requires that 50 operating cycles be
carried out.
- Verification of locking mechanisms are included
in this range of tests.
Back
33Test n6 (8-2-6) mechanical operation
- After 50 operating cycles, the interlocking
mechanisms and other moving parts of the
switchboard preserve their initial properties
- operation, - operating force. - Some more solicited moving parts of Prisma Plus
have passed until 10000 operating cycles (door
handles, hinges).
Back
34Test n7 (8-2-7) degree of protection
- The tests carried out define the capacity of an
equipped switchboard to - protect persons against contact with live parts
- protect equipment against penetration of solid
objects and liquids - protect equipment against external influences
such as impacts (shocks).
Conditions
Contents
Results
35Test n7 (8-2-7) degree of protection
Conditions
- Tests for solid objects penetration (test
finger, stem and wire). - Tests for water ingress (jets of water, drop
vaps).
Back
36Test n7 (8-2-7) degree of protection
- Results of tests confirm the characteristics of
Prisma Plus switchboard IP30 to IP55 and IK7 to
IK10 according to the different configurations.
- Prisma Plus system P - IP30/31/55- IK07 with
fixed panelling frame- IK08 with door IP30-
IK10 with door IP55.
- Prisma Plus system G
- enclosure - IP30/31/43- IK07 without door -
IK08 with door - IP55 enclosure IK10
- Pack enclosure- IP30- IK07 without door -
IK08 with door.
Back
37The IP degrees of protection (IEC 60529/EN
60529)
- 1st digit
- protection of persons
- protection against solids.
- 2nd digit
- protection against liquids.
- Additional letter (optional) protection of
persons against contact with live parts - A protect againts access of the back of the
hand - B protect against access of fingers Ø 12 mm
- C protect against access of a tool diameter 2.5
mm - D protect against access of a tool diameter 0.1
mm
Contents
Definitions
38Degree of protection
Definitions
- The IEC 60529 standard (02/ 2001) gives , by the
IP code, the different degrees of protection
provided by an electrical enclosure.
- The IP code is described by 2 specific digits
an additional letter , in option, can complete
the IP code when the real protection of persons
against contact with live parts is better than
the protection given by the first digit - the 1st digit gives the level of protection of
equipment against penetration of solid objects
and protection of persons - the 2nd digit gives the level of protection of
equipment against penetration of liquids.
- Additional letter
- it is used only when the effective protection of
persons is better than the one given bythe
first IP digit - in case of only protection of persons is needed,
the 2 IP digits are replaced by x. - Example IPxxB.
Back
39Degree of protection IK (IEC 62262)
- IK code 2 digits giving the level of shock
energy, in Joules - IK 01 0,14
- IK 02 0,2
- IK 03 0,35
- IK 04 0,5
- IK 05 0,7
- IK 06 1
- IK 07 2
- IK 08 5
- IK 09 10
- IK 10 20.
- The IEC 62262 standard defines a IK code which
gives the equipment capacity to resist to
mechanical impacts , on all the enclosure
surfaces.
Contents
403 routine tests performed by the panelbuilder
- The 3 routine tests, easily and rapidly
performed, must be carried out by the
panelbuilder. - overall inspection according to the mounting
instructions and technical documents (right
device ratings, tightening torques) - insulation checking by a dielectric test
- checking of protective measures and of the
electrical continuity of the protective circuits.
- They complete the 7 manufacturer type tests and
guarantee professionnalism and responsability of
panelbuilder.
- Schneider Electric supplies a full range of tools
for assistance - Quality inspection guide
- switchboard assembly and installation guide
- Prisma Plus System P and G assembly guides
Contents
41Test n8 (8-3-1) cabling, electrical operation
- Check of mechanical actuating elements,
interlocks, ... effectiveness
- Check of proper laying of conductors and cables
and proper mounting of device
- Check of connections adequate contact, especially
screwed and bolted connections.
Conditions
Contents
Results
42Test n8 (8-3-1) cabling, electrical operation
Conditions
- Check of conformity with
- drawings, circuit and wiring diagrams
- cabling (power and auxiliary connection)
- cabling quality (cross-section, crimping...)
- information and marking (cables and devices).
- Visual inspection
- degree of protection, creepage distances and
clearancess - technical data document (diagrams,
characteristics...).
- Mechanical and electrical functioning test
- check of cabling and most sensitive parts of the
switchboard (mechanical control
facilities,interlocks...).
Back
43Test n8 (8-3-1) cabling, electrical operation
- The design of the switchboard , a structure based
on functional units, insures conformity to this
test.
- Schneider Electric gives the basic rules of
assembly and installation in its documentation
for assistance
Back
44Test n9 (8-3-4) insulation resistance /
(8-3-2) dielectric test
- No arc flash-over or insulator perforation must
be observed between the live parts each other and
between the live parts and the conductive
structural parts.
Conditions
Contents
Results
45Test n9 (8-3-4) insulation resistance /
(8-3-2) dielectric test
Conditions
- 2 possibilities of test depending on the
panelbuilder s means - either insulation measuring (8-3-4)
- or dielectric test (8-3-2).
- all electrical equipment shall be connected for
the test, except those apparatus which are
designed for a lower test voltage - the test voltage is applied
- - between each pole and interconnected exposed
conductive parts - between each pole of main
circuit and the other poles - - between each auxiliary control circuit and
main circuit and exposed conductive parts - - between supply and withdrawable part of a
switchgear .
- Insulation test (8-3-4)
- insulation measurement using an insulation
measuring device at a voltage of at least 500V.
- Dielectric test (8-3-2)
- for a rated operational voltage of 240/400 V, the
dielectric test voltage of 2500 V must be applied
during 1 s.
Back
46Test n9 (8-3-4) insulation resistance /
(8-3-2) dielectric test
- Verification of insulation resistance (8-3-4)
- The test is passed if there is no perforation or
flashover between the different tested parts
- Dielectric test (8-3-2)
- The test is passed if the insulation resistance
between circuits and exposed conductive parts is
at least 1000 Ohms/V..
- The standardization of the distribution and
conenctions is the best guarantee.
Back
47Test n10 (8-3-3) protective measures
- Checking of protective measures and of the
electrical continuity of the protective circuits
for metallic assemblies
Conditions
Contents
Results
48Test n10 (8-3-3) protective measures
Conditions
- Visual inspection
- Checking of protective measures against direct
and indirect contacts - Checking of the electrical continuity of the
protective circuits for metallic assemblies
(screwed and bolted connections shall be checked
for adequate contact) possibly by random tests.
Back
49Test n10 (8-3-3) protective measures
- Compliance of mechanical and electrical assembly
instructions guarantees good electrical
continuity of protection circuits.
Back
50Panelbuilder and manufacturer, together to offer
maximum safety and realibility
- Manufacturer
- products tested in real configurations
- detailed instructions for fautless construction.
- Installer
- it has to its disposal informations, by means of
tools of switchboard assembly and installation
guide (catalogs, internet) - confidence in products and swichboards systems,
the result of many years of experience
- A shared success
- this complementarity must fall under the duration
to consolidate our professionalism.
Contents
Customers advantages
51Panelbuilder and manufacturer, together to offer
maximum safety and realibility
Customers advantages
- Panelbuilders (and installators workshops)
- they complete a work of quality, simply
- they minimize the risk related to their
responsibility for realization of a switchboard
of which they know and ensure the level of safety - they carry out very simply the conformity to the
standard, therefore CE marking - they develop their professionalism by making
known it - they are different from the other panelbuilders
- they profit from the transfer of Schneider
Electric s experiment and tools
- Installators
- for them, a certified switchboard is the
guarantee of the safety of installation and the
good completion of work - it is also the certainty to fulfill the user s
requirements - they minimize the risk related to their
responsibility for installation - they show professionalism.
- Users
- They have the certainty to have a switchboard
ensuring - - the safety and whose the quality is proven
- - maintenance and evolutivity easy thanks to the
prefabrication and the standardization of the
components - They are ensured of the equipment and components
perennity. - They minimize the risks related to their
responsibility for exploitation
- Specifiers/consultants
- For them it is the certainty to prescribe a
switchboard which ensures the level of safety
required by the user.
Back
52Prisma Plus and IEC 60439-1 standard an
international influence
- IEC 60439-1 the same standard for all the
professionals of switchboards
IEC
UL
IEC
IEC
IEC
IEC
Contents