Title:

Solid Waste Permitting Process

Description:

Solid Waste Permitting Process Presented by: Joan Litton, Manager Solid Waste Permitting February 22, 2010 Tonight s Presentation Solid Waste Permitting Process ... – PowerPoint PPT presentation

Number of Views:75
Avg rating:3.0/5.0
Slides: 21
Provided by: daven154
Learn more at: http://www.scdhec.gov
Category:

less

Write a Comment
User Comments (0)
Transcript and Presenter's Notes

Title: Solid Waste Permitting Process


1
Solid Waste Permitting Process
  • Presented by Joan Litton, Manager
  • Solid Waste Permitting

February 22, 2010
2
Tonights Presentation
  • Solid Waste Permitting Process
  • Solid Waste Permitting Requirements
  • Public Involvement
  • Questions

3
Regulation of Municipal Solid Waste Incinerators
Air Quality
Solid Waste
Solid Waste
Ash Residue Storage
MSW Storage
Incinerator
4
Permit Application Process
  • Application Received
  • Administrative Review
  • Technical Review
  • If complete, notice sent to contact mailing list
    for opportunity to review and comment

5
Public Involvement
  • DHEC will hold additional meetings to answer
    questions
  • During technical review, the application will be
    available for review and staff will be taking
    comments

6
Draft Permit Decision
  • If Department staff determines the application to
    be technically complete, will prepare DRAFT
    Permit
  • Notice sent to newspaper and contact mailing list
    when DRAFT Permit issued
  • Public can view application, DRAFT Permit, and
    submit comments

7
Public Hearing
  • If 10 or more people request a Public Hearing,
    the Department will conduct one
  • Public will be informed of hearing by newspaper
    and mail
  • Public Hearing will be held in the community
  • Citizens will have opportunity to speak

8
Final Permit Decision
  • DHEC staff reviews all public comments received
    on the application and DRAFT Permit
  • DHEC staff makes decision to issue or deny the
    FINAL Permit
  • Notice of FINAL Permit decision sent to contact
    mailing list

9
Permitting Requirements for MSW Incineration
Facility
  • Consistency with State and Local Solid Waste
    Management Plans
  • Consistency with local zoning and other
    ordinances
  • Maximum Daily capacity ? 600 tons/day

10
Permitting Requirements
  • Prohibited wastes
  • Hazardous waste
  • Infectious waste

11
Permitting Requirements
  • Engineering Report
  • Overall description of facility
  • Types and quantities of waste to be received
  • Location of waste storage areas

12
Permitting Requirements
  • Location Restrictions - Incinerator shall not be
    located within
  • 500 feet of any surface water
  • 500 feet of any drinking water well
  • 100 feet of any property line
  • 1,000 feet of any residences, schools, day-care
    centers, hospitals or recreational park areas

13
Permitting Requirements
  • Operations Plan
  • Describes the general operation of the facility
  • Describes how the facility will meet all
    applicable regulatory requirements

14
Permitting Requirements
  • Waste Control Plan
  • Waste approval procedures (for making
    determinations to accept or refuse waste streams)
  • Unauthorized waste handling procedures (for
    separation and removal from facility)

15
Permitting Requirements
  • Ash Management Plan
  • Provides procedures for how the ash will be
  • Handled
  • Stored
  • Transported
  • Treated
  • Disposed

16
Permitting Requirements
  • Closure Plan
  • Lists steps that must be taken to close the
    facility in an environmentally safe manner
  • Provides a cost estimate for third-party
    completion of all closure activities

17
Permitting Requirements
  • Financial Responsibility
  • Facility required to provide funds to the
    Department to cover the costs to close the
    facility
  • Funding mechanism must be approved by the
    Department

18
Summary of Public Involvement Opportunities
  • Tonights Public Meeting
  • Departments Notice of Receipt of Application
  • Future Public Meeting/QA Session
  • Departments Notice of Draft Permit Issuance
  • Public Hearing on Draft Permit
  • Department staff available by phone and e-mail
  • Dedicated web page at www.scdhec.gov

19
For More Information
  • Please contact Nancy Whittle
  • at
  • (803) 896-8967
  • or at
  • whittlnc_at_dhec.sc.gov

Thank you for coming.
20
Questions?