Title: Risk-Informed Pressurized Water Reactor Vessel Inspection Interval Extension
1- Risk-Informed Pressurized Water Reactor Vessel
Inspection Interval Extension - Cheryl L. Boggess, Nathan A. Palm
- Westinghouse Electric Company, LLC
- 12th International Conference on Nuclear
Engineering - Arlington, Virginia
- April 2004
2- Risk-Informed Pressurized Water Reactor Vessel
Inspection Interval Extension - Authors Cheryl L. Boggess, Nathan A. Palm
- Bruce Bishop, Owen Hedden
- Westinghouse Electric Company, LLC
3Agenda
- Introduction
- Code Case N-691
- NRC Pressurized Thermal Shock Risk Study
- WCAP-16168-NP Methodology
- Probabilistic Fracture Mechanics Computer tool
- Probabilistic Fracture Mechanics Inputs
- Results
- Applicability to Other Plants
- Conclusions
4Introduction
- Significant cost and man-rem exposure have been
expended performing examination on ASME Category
B-A, B-D, and B-J welds in the reactor vessel
(RV) - Requirements for inspection have been in effect
since the 1989 Edition of the ASME Boiler and
Pressure Vessel Code, Section XI - Section XI requires 100 of RV welds to be
inspected once each 10 years - No service-induced flaws found to date
5Code Case N-691
- Provides the justification for extending the
reactor vessel (RV) in-service inspection (ISI)
interval from 10 to 20 years - Applies to ASME Category B-A B-D welds in the
RV and B-J welds to the RV nozzles - Approved by ASME in November 2003
- Provides technical basis for WCAP-16168-NP
6NRC PTS Risk Study
- Significant work by the USNRC to investigate the
effects of pressurized thermal shock (PTS) is
ongoing - Risk of RV failure due to embrittlement and other
plant characteristics critical to PTS is
calculated for three PWR designs - Goal is to relax current PTS screening criteria
using the latest information and risk-informed
methods
7NRC PTS Risk Study
8WCAP-16168-NP Methodology
- Probabilistic Fracture Mechanics (PFM) methods
are used to calculate a conditional vessel
failure probability - Methodology is consistent with NRC PTS Risk Study
- Pilot plants are the same as those for the NRC
PTS Risk Study, Beaver Valley Unit 1 and
Palisades (for Westinghouse and CE plant designs,
respectively) - Using ASME-XI flaw evaluation methods, a
deterministic study identified beltline welds as
the limiting locations
9Reactor Vessel Beltline Study
10PFM Computer Tool
- PROBSBFD Code developed to include the effects of
fatigue crack growth (FCG ) and in-service
inspection (ISI) - Effects of ISI and FCG modeled in the same way as
the NRC pc-PRAISE code and Westinghouse Win-SRRA
tools for piping - Effects are included in surface breaking flaw
density file for input to the FAVOR Code
developed for the NRC PTS Risk Study
11Key PFM Inputs
- PTS Transients
- Dominant PTS transients (each contributing ?1 to
total PTS risk) considered in NRC PTS Risk Study
for NSSS designs - Risk contribution of transients considered
contributes gt 99 of Total Plant Risk - Transients which were considered resulted from
loss of coolant accidents (LOCAs), stuck open
relief valves, and large main steam line breaks
(MSLBs) - Operational Transients
- Design basis transients for pilot plants were
reviewed and heatup/cooldown was determined to be
the reference transient for the evaluation
12Key PFM Inputs
- Effectiveness of ISI
- Basis for probability of detection taken from
studies performed at the Electric Power Research
Institute NDE Center - Pilot plant evaluations assumed future
inspections conducted in accordance with ASME
Section XI Appendix VIII - Flaws detected were assumed to be turned to a
flaw free state, thus maximizing the change in
risk due to inspection
13Key PFM Inputs
14PFM Computer Tool Process Flowchart
15Results - Flaw Growth
16Results - Flaw Growth
17Results Failure Frequency
Vessel Failure Frequency Results Vessel Failure Frequency Results Vessel Failure Frequency Results
Beaver Valley Unit 1 Palisades
Upper Bound 8.22E-9 4.95E-8
10-Year ISI Only 7.18E-9 3.93E-8
ISI Every 10 Years 6.71E-9 3.58E-8
Lower Bound 5.11E-9 2.81E-8
Difference in Risk 3.11E-9 2.14E-8
18Change in Risk - ?LERF
- Upper and Lower Bounds were determined by adding
/ subtracting 2 times the standard error to /
from the 10 Year ISI Only and ISI Every 10
Year cases respectively. - Change in Vessel Failure Frequency is maximum
difference between Upper and Lower Bounds. - Reactor Vessel Failure is assumed to lead to a
Large Early Release ? ?TWCF ?LERF - ?LERF for pilot plants is an insignificant change
per RG 1.174 if the mean value is ? 10-7 per year
19Results Summary
- Proposed ISI interval for Category B-A, B-D, and
B-J welds is 100 inspection every 20 years after
initial 10-year ISI - Results support extension of reactor vessel
inspection interval to 20 years after initial
10-year ISI - Methodology does not address dissimilar metal
category B-F welds where PWSCC is a concern - Interval provides for detection of any potential
emerging degradation mechanisms - Interval maintains defense in depth
20Applicability to Other Plants
- Pilot plant results apply to similar NSSS designs
if the following parameters for a plant are
bounded by the pilot plant - Dominant PTS transients from NRC PTS Risk Study
are applicable - Degree of reactor vessel embrittlement, RTNDT
(defined in the NRC PTS Risk Study) - Frequency and severity of design basis transients
- Cladding layers (Single/Multiple)
- ISI meeting RG 1.150 or Section XI Appendix VIII
21Applicability to Other Plants
- A total of 24 plants with near term planned
inspections have committed, through the
Westinghouse Owners Group (WOG), to implement the
methodology - Current results of Oconee Unit 1 pilot plant
demonstrates applicability of methodology to BW
NSSS Design - Westinghouse Owners Group working to determine
schedule for fleet implementation
22WOG Implementation Schedule
- Summary of currently identified implementation
- Current 10 year interval inspection plans will
provide yearly inspection results - Implementation of 20 year interval inspection
plan provides inspection results at least every 2
years - These results reflect implementation commitments
from 50 of the WOG plants
23Conclusions
- The RV Beltline is the most limiting region
- Crack extension due to FCG during service is
small for the vessels considered - Change in risk is insignificant per RG 1.174
guidelines - Decrease in ISI frequency from 10 to 20 years
maintains safety margins for defense-in-depth and
provides a reduction in man-rem exposure - Methodology expanded to BW NSS design
- Results of pilot plant analyses are being applied
to other Westinghouse and CE plants - NRC SE expected in 2004
24 25RPV Inspection Scenarios