Risk-Informed Pressurized Water Reactor Vessel Inspection Interval Extension - PowerPoint PPT Presentation

1 / 25
About This Presentation
Title:

Risk-Informed Pressurized Water Reactor Vessel Inspection Interval Extension

Description:

Risk-Informed Pressurized Water Reactor Vessel Inspection Interval Extension Cheryl L. Boggess, Nathan A. Palm Westinghouse Electric Company, LLC – PowerPoint PPT presentation

Number of Views:210
Avg rating:3.0/5.0
Slides: 26
Provided by: palm
Category:

less

Transcript and Presenter's Notes

Title: Risk-Informed Pressurized Water Reactor Vessel Inspection Interval Extension


1
  • Risk-Informed Pressurized Water Reactor Vessel
    Inspection Interval Extension
  • Cheryl L. Boggess, Nathan A. Palm
  • Westinghouse Electric Company, LLC
  • 12th International Conference on Nuclear
    Engineering
  • Arlington, Virginia
  • April 2004

2
  • Risk-Informed Pressurized Water Reactor Vessel
    Inspection Interval Extension
  • Authors Cheryl L. Boggess, Nathan A. Palm
  • Bruce Bishop, Owen Hedden
  • Westinghouse Electric Company, LLC

3
Agenda
  • Introduction
  • Code Case N-691
  • NRC Pressurized Thermal Shock Risk Study
  • WCAP-16168-NP Methodology
  • Probabilistic Fracture Mechanics Computer tool
  • Probabilistic Fracture Mechanics Inputs
  • Results
  • Applicability to Other Plants
  • Conclusions

4
Introduction
  • Significant cost and man-rem exposure have been
    expended performing examination on ASME Category
    B-A, B-D, and B-J welds in the reactor vessel
    (RV)
  • Requirements for inspection have been in effect
    since the 1989 Edition of the ASME Boiler and
    Pressure Vessel Code, Section XI
  • Section XI requires 100 of RV welds to be
    inspected once each 10 years
  • No service-induced flaws found to date

5
Code Case N-691
  • Provides the justification for extending the
    reactor vessel (RV) in-service inspection (ISI)
    interval from 10 to 20 years
  • Applies to ASME Category B-A B-D welds in the
    RV and B-J welds to the RV nozzles
  • Approved by ASME in November 2003
  • Provides technical basis for WCAP-16168-NP

6
NRC PTS Risk Study
  • Significant work by the USNRC to investigate the
    effects of pressurized thermal shock (PTS) is
    ongoing
  • Risk of RV failure due to embrittlement and other
    plant characteristics critical to PTS is
    calculated for three PWR designs
  • Goal is to relax current PTS screening criteria
    using the latest information and risk-informed
    methods

7
NRC PTS Risk Study
8
WCAP-16168-NP Methodology
  • Probabilistic Fracture Mechanics (PFM) methods
    are used to calculate a conditional vessel
    failure probability
  • Methodology is consistent with NRC PTS Risk Study
  • Pilot plants are the same as those for the NRC
    PTS Risk Study, Beaver Valley Unit 1 and
    Palisades (for Westinghouse and CE plant designs,
    respectively)
  • Using ASME-XI flaw evaluation methods, a
    deterministic study identified beltline welds as
    the limiting locations

9
Reactor Vessel Beltline Study
10
PFM Computer Tool
  • PROBSBFD Code developed to include the effects of
    fatigue crack growth (FCG ) and in-service
    inspection (ISI)
  • Effects of ISI and FCG modeled in the same way as
    the NRC pc-PRAISE code and Westinghouse Win-SRRA
    tools for piping
  • Effects are included in surface breaking flaw
    density file for input to the FAVOR Code
    developed for the NRC PTS Risk Study

11
Key PFM Inputs
  • PTS Transients
  • Dominant PTS transients (each contributing ?1 to
    total PTS risk) considered in NRC PTS Risk Study
    for NSSS designs
  • Risk contribution of transients considered
    contributes gt 99 of Total Plant Risk
  • Transients which were considered resulted from
    loss of coolant accidents (LOCAs), stuck open
    relief valves, and large main steam line breaks
    (MSLBs)
  • Operational Transients
  • Design basis transients for pilot plants were
    reviewed and heatup/cooldown was determined to be
    the reference transient for the evaluation

12
Key PFM Inputs
  • Effectiveness of ISI
  • Basis for probability of detection taken from
    studies performed at the Electric Power Research
    Institute NDE Center
  • Pilot plant evaluations assumed future
    inspections conducted in accordance with ASME
    Section XI Appendix VIII
  • Flaws detected were assumed to be turned to a
    flaw free state, thus maximizing the change in
    risk due to inspection

13
Key PFM Inputs
  • Probability of Detection

14
PFM Computer Tool Process Flowchart
15
Results - Flaw Growth
16
Results - Flaw Growth
17
Results Failure Frequency
Vessel Failure Frequency Results Vessel Failure Frequency Results Vessel Failure Frequency Results
Beaver Valley Unit 1 Palisades
Upper Bound 8.22E-9 4.95E-8
10-Year ISI Only 7.18E-9 3.93E-8
ISI Every 10 Years 6.71E-9 3.58E-8
Lower Bound 5.11E-9 2.81E-8
Difference in Risk 3.11E-9 2.14E-8
18
Change in Risk - ?LERF
  • Upper and Lower Bounds were determined by adding
    / subtracting 2 times the standard error to /
    from the 10 Year ISI Only and ISI Every 10
    Year cases respectively.
  • Change in Vessel Failure Frequency is maximum
    difference between Upper and Lower Bounds.
  • Reactor Vessel Failure is assumed to lead to a
    Large Early Release ? ?TWCF ?LERF
  • ?LERF for pilot plants is an insignificant change
    per RG 1.174 if the mean value is ? 10-7 per year

19
Results Summary
  • Proposed ISI interval for Category B-A, B-D, and
    B-J welds is 100 inspection every 20 years after
    initial 10-year ISI
  • Results support extension of reactor vessel
    inspection interval to 20 years after initial
    10-year ISI
  • Methodology does not address dissimilar metal
    category B-F welds where PWSCC is a concern
  • Interval provides for detection of any potential
    emerging degradation mechanisms
  • Interval maintains defense in depth

20
Applicability to Other Plants
  • Pilot plant results apply to similar NSSS designs
    if the following parameters for a plant are
    bounded by the pilot plant
  • Dominant PTS transients from NRC PTS Risk Study
    are applicable
  • Degree of reactor vessel embrittlement, RTNDT
    (defined in the NRC PTS Risk Study)
  • Frequency and severity of design basis transients
  • Cladding layers (Single/Multiple)
  • ISI meeting RG 1.150 or Section XI Appendix VIII

21
Applicability to Other Plants
  • A total of 24 plants with near term planned
    inspections have committed, through the
    Westinghouse Owners Group (WOG), to implement the
    methodology
  • Current results of Oconee Unit 1 pilot plant
    demonstrates applicability of methodology to BW
    NSSS Design
  • Westinghouse Owners Group working to determine
    schedule for fleet implementation

22
WOG Implementation Schedule
  • Summary of currently identified implementation
  • Current 10 year interval inspection plans will
    provide yearly inspection results
  • Implementation of 20 year interval inspection
    plan provides inspection results at least every 2
    years
  • These results reflect implementation commitments
    from 50 of the WOG plants

23
Conclusions
  • The RV Beltline is the most limiting region
  • Crack extension due to FCG during service is
    small for the vessels considered
  • Change in risk is insignificant per RG 1.174
    guidelines
  • Decrease in ISI frequency from 10 to 20 years
    maintains safety margins for defense-in-depth and
    provides a reduction in man-rem exposure
  • Methodology expanded to BW NSS design
  • Results of pilot plant analyses are being applied
    to other Westinghouse and CE plants
  • NRC SE expected in 2004

24
  • Background

25
RPV Inspection Scenarios
Write a Comment
User Comments (0)
About PowerShow.com