Moving Bed Biofilm Reactor Retrofit for Ammonia and Nitrate Removal - PowerPoint PPT Presentation

1 / 20
About This Presentation
Title:

Moving Bed Biofilm Reactor Retrofit for Ammonia and Nitrate Removal

Description:

Times New Roman Perpetua Monotype Sorts Arial Narrow AvantGarde Bk BT bludiags Moving Bed Biofilm Reactor Retrofit for Ammonia and Nitrate Removal Phase 2 Project ... – PowerPoint PPT presentation

Number of Views:280
Avg rating:3.0/5.0
Slides: 21
Provided by: scott305
Category:

less

Transcript and Presenter's Notes

Title: Moving Bed Biofilm Reactor Retrofit for Ammonia and Nitrate Removal


1
Moving Bed Biofilm Reactor Retrofit for Ammonia
and Nitrate Removal
  • BV SACWSD
  • Lela Parsons, P.E. Greg Fabisiak
  • Mark Maxwell, P.E. Joan Chavez

2002 RMSAWWA / RMWEA ANNUAL CONFERENCE
2
Phase 2 Project Components
  • Wastewater Collection System Master Plan
  • Utility Plan
  • Preliminary Design Report
  • Detailed Plans Specifications
  • Contract Administration

3
Utility Plan Goals
  • Provide information required by DRCOG and for SRF
    Funding
  • Evaluation of existing facilities
  • Population flow projections
  • Environmental assessment to support FNSI
  • Alternative analysis and recommendations
  • Implementation and financial plans
  • Public participation
  • Determine necessary wastewater facilities for
    capacity and regulatory compliance through 2020

4
Site Layout
5
WM WWTP Existing Unit Processes
East Trickling Filter
Final Clarifiers
Chlorination
P
Flow Splitter
Discharge to South Platte River
Raw Wastewater
Dechlorination
Mechanical Screenings
Primary Clarifiers
Rotating Biological Contactors
P
P
Chlorination
West Trickling Filter
Final Clarifier
Combined Primary MBBR Sludge
Accelerated Air Drying of Dewatered Biosolids
Prior to Ultimate Disposal of Class A Product
Degritting
Gravity Thickener
Anaerobic Digesters
Deskins Quick-Dry Filtration SystemTM
P
6
WM WWTP Existing Unit Process Capacities
7
Treatment Issues
  • Regulatory Compliance
  • Reclassification of the South Platte River
    requires additional disinfection
  • Updated model of Segment 15 of the South Platte
    River resulted in imposition of effluent ammonia
    limit
  • Current and Future Water Quality Concerns
  • Dissolved oxygen
  • Ammonia
  • Nitrates
  • Nutrients

8
South Platte Dischargers
9
Treatment Issues (cont)
  • WM WWTP Treatment Capacity
  • Surge in residential and commercial activity in
    the service area
  • Current treatment capacity of 4.4 mgd forecasted
    to only be sufficient through 2003
  • Limited room for additional expansion at the
    existing site

10
SACWSD Future Plan
  • Complete Phase 2 expansion at WM WWTP by 2004
  • Phase 2 will provide capacity until 2008
  • New WWTP will be needed by 2009- could be
    regional WWTP or SACWSD WWTP
  • Upgrade WM WWTP when appropriate to meet future
    water quality regulations

11
WM WWTP Expansion
  • Increase treatment capacity from 4.4 to 7.0 mgd
  • Notice to proceed issued September 2002
  • Short-term - capacity expansion allows growth
    while new WWTP is designed and constructed
  • Long-term - WM WWTP will continue to serve the
  • southern area
  • of the District

12
Phase 2 Improvements
  • Major Expansions
  • Secondary Treatment Process
  • Solids Handling Process
  • Additional Improvements
  • Replace Manual Bar Screen
  • Demolish RBCs
  • Upgrade Disinfection Facilities
  • Add Stand-by Power Capacity
  • Expand Administration Building/Garage

13
Treatment Alternatives
Alternative A
Alternative B
  • Activated Sludge
  • Anoxic/oxic basins
  • WAS Pumping Station and Blower Building
  • New Aerobic Sludge Handling
  • Centrifuge
  • Aerated sludge holding
  • Biological Nutrient Removal (future)
  • Fixed Film
  • MBBR
  • Anoxic/oxic basins
  • Blower Building
  • Additional Anaerobic Solids Processing
  • Convert secondary digester to primary digester
  • New secondary digester
  • Chemical Phosphorous Removal (future)
  • Post Denitrification (future)

14
Alternative Evaluation
  • Alternative A slightly less expensive
  • Alternative A more operationally complex-
    requires separate solids handling process
  • Alternative B will require chemical addition for
    future phosphorous removal
  • SACWSD has always utilized and prefers fixed film
    processes

15
Selected Alternative Moving Bed Biofilm Reactors
  • Fixed film process manufactured by Kaldnes
  • Employs high-density polyethylene plastic media,
    coarse bubble aeration, and sieves
  • Biofilm grows on inside of the media
  • Specific gravity
  • of 0.96
  • 150 ft2/ft3 media
  • surface area
  • 0.93 /ft clean
  • water oxygen
  • transfer rate

16
Design Conditions
  • 100 mg/L influent BOD
  • 2 anoxic and 2 oxic reactors in series
  • 60 fill in each reactor
  • Coarse bubble diffuser system in oxic reactors
  • Submersible propeller mixers in anoxic reactors
  • 4 mg/L summer DO concentration
  • 5 mg/L winter DO concentration
  • 200 internal recycle for nitrate removal

17
Treatment Requirements
  • East Plant Effluent
  • BOD5 reduction lt10 mg/L
  • Total ammonia reduction lt2 mg-N/L (complete
    nitrification)
  • Total nitrate reduction lt10 mg-NO3/L (partial
    denitrification)
  • Blended Effluent (East and West Plant)
  • CBOD reduction lt25 mg/L
  • Total ammonia reduction lt10 mg-N/L

18
Selected Alternative Flow Schematic
East Trickling Filter
Anoxic MBBR
Oxic MBBR
Final Clarifiers
Chlorination
P
P
Discharge to South Platte River
Raw Wastewater
Dechlorination
Mechanical Screenings
Primary Clarifiers
P
Flow Splitter
P
Chlorination
West Trickling Filter
Final Clarifier
Combined Primary MBBR Sludge
Accelerated Air Drying of Dewatered Biosolids
Prior to Ultimate Disposal of Class A Product
Degritting
Gravity Thickener
Anaerobic Digesters
Deskins Quick-Dry Filtration SystemTM
P
Existing Facilities
Phase 2 New
Phase 2 Modified
19
Operational Issues
  • Portion of primary effluent must be bypassed
    around existing trickling filter
  • Requires construction of a new flow splitter
    structure
  • Prevents hydraulic surcharging of underdrains
  • Assures sufficient soluble BOD for
    denitrification
  • Allows ETF pumping station to be taken out of
    service
  • Trickling filter snail accumulation
  • Installed an automatic, self-cleaning strainer
    with 1/8- inch openings at the ETF pumping station

20
Total Project Costs
  • Engineers Construction
  • Cost Opinion
  • Low Bid Price
  • Difference Between High
  • and Low Bids

13,283,000 12,774,000 475,300
Write a Comment
User Comments (0)
About PowerShow.com