Title: Moving Bed Biofilm Reactor Retrofit for Ammonia and Nitrate Removal
1Moving Bed Biofilm Reactor Retrofit for Ammonia
and Nitrate Removal
- BV SACWSD
- Lela Parsons, P.E. Greg Fabisiak
- Mark Maxwell, P.E. Joan Chavez
2002 RMSAWWA / RMWEA ANNUAL CONFERENCE
2Phase 2 Project Components
- Wastewater Collection System Master Plan
- Utility Plan
- Preliminary Design Report
- Detailed Plans Specifications
- Contract Administration
3Utility Plan Goals
- Provide information required by DRCOG and for SRF
Funding - Evaluation of existing facilities
- Population flow projections
- Environmental assessment to support FNSI
- Alternative analysis and recommendations
- Implementation and financial plans
- Public participation
- Determine necessary wastewater facilities for
capacity and regulatory compliance through 2020
4Site Layout
5WM WWTP Existing Unit Processes
East Trickling Filter
Final Clarifiers
Chlorination
P
Flow Splitter
Discharge to South Platte River
Raw Wastewater
Dechlorination
Mechanical Screenings
Primary Clarifiers
Rotating Biological Contactors
P
P
Chlorination
West Trickling Filter
Final Clarifier
Combined Primary MBBR Sludge
Accelerated Air Drying of Dewatered Biosolids
Prior to Ultimate Disposal of Class A Product
Degritting
Gravity Thickener
Anaerobic Digesters
Deskins Quick-Dry Filtration SystemTM
P
6WM WWTP Existing Unit Process Capacities
7Treatment Issues
- Regulatory Compliance
- Reclassification of the South Platte River
requires additional disinfection - Updated model of Segment 15 of the South Platte
River resulted in imposition of effluent ammonia
limit - Current and Future Water Quality Concerns
- Dissolved oxygen
- Ammonia
- Nitrates
- Nutrients
8South Platte Dischargers
9Treatment Issues (cont)
- WM WWTP Treatment Capacity
- Surge in residential and commercial activity in
the service area - Current treatment capacity of 4.4 mgd forecasted
to only be sufficient through 2003 - Limited room for additional expansion at the
existing site
10SACWSD Future Plan
- Complete Phase 2 expansion at WM WWTP by 2004
- Phase 2 will provide capacity until 2008
- New WWTP will be needed by 2009- could be
regional WWTP or SACWSD WWTP - Upgrade WM WWTP when appropriate to meet future
water quality regulations
11WM WWTP Expansion
- Increase treatment capacity from 4.4 to 7.0 mgd
- Notice to proceed issued September 2002
- Short-term - capacity expansion allows growth
while new WWTP is designed and constructed - Long-term - WM WWTP will continue to serve the
- southern area
- of the District
12Phase 2 Improvements
- Major Expansions
- Secondary Treatment Process
- Solids Handling Process
- Additional Improvements
- Replace Manual Bar Screen
- Demolish RBCs
- Upgrade Disinfection Facilities
- Add Stand-by Power Capacity
- Expand Administration Building/Garage
13Treatment Alternatives
Alternative A
Alternative B
- Activated Sludge
- Anoxic/oxic basins
- WAS Pumping Station and Blower Building
- New Aerobic Sludge Handling
- Centrifuge
- Aerated sludge holding
- Biological Nutrient Removal (future)
- Fixed Film
- MBBR
- Anoxic/oxic basins
- Blower Building
- Additional Anaerobic Solids Processing
- Convert secondary digester to primary digester
- New secondary digester
- Chemical Phosphorous Removal (future)
- Post Denitrification (future)
14Alternative Evaluation
- Alternative A slightly less expensive
- Alternative A more operationally complex-
requires separate solids handling process - Alternative B will require chemical addition for
future phosphorous removal - SACWSD has always utilized and prefers fixed film
processes
15Selected Alternative Moving Bed Biofilm Reactors
- Fixed film process manufactured by Kaldnes
- Employs high-density polyethylene plastic media,
coarse bubble aeration, and sieves - Biofilm grows on inside of the media
- Specific gravity
- of 0.96
- 150 ft2/ft3 media
- surface area
- 0.93 /ft clean
- water oxygen
- transfer rate
16Design Conditions
- 100 mg/L influent BOD
- 2 anoxic and 2 oxic reactors in series
- 60 fill in each reactor
- Coarse bubble diffuser system in oxic reactors
- Submersible propeller mixers in anoxic reactors
- 4 mg/L summer DO concentration
- 5 mg/L winter DO concentration
- 200 internal recycle for nitrate removal
17Treatment Requirements
- East Plant Effluent
- BOD5 reduction lt10 mg/L
- Total ammonia reduction lt2 mg-N/L (complete
nitrification) - Total nitrate reduction lt10 mg-NO3/L (partial
denitrification) - Blended Effluent (East and West Plant)
- CBOD reduction lt25 mg/L
- Total ammonia reduction lt10 mg-N/L
18Selected Alternative Flow Schematic
East Trickling Filter
Anoxic MBBR
Oxic MBBR
Final Clarifiers
Chlorination
P
P
Discharge to South Platte River
Raw Wastewater
Dechlorination
Mechanical Screenings
Primary Clarifiers
P
Flow Splitter
P
Chlorination
West Trickling Filter
Final Clarifier
Combined Primary MBBR Sludge
Accelerated Air Drying of Dewatered Biosolids
Prior to Ultimate Disposal of Class A Product
Degritting
Gravity Thickener
Anaerobic Digesters
Deskins Quick-Dry Filtration SystemTM
P
Existing Facilities
Phase 2 New
Phase 2 Modified
19Operational Issues
- Portion of primary effluent must be bypassed
around existing trickling filter - Requires construction of a new flow splitter
structure - Prevents hydraulic surcharging of underdrains
- Assures sufficient soluble BOD for
denitrification - Allows ETF pumping station to be taken out of
service - Trickling filter snail accumulation
- Installed an automatic, self-cleaning strainer
with 1/8- inch openings at the ETF pumping station
20Total Project Costs
- Engineers Construction
- Cost Opinion
- Low Bid Price
- Difference Between High
- and Low Bids
13,283,000 12,774,000 475,300