Title: Computer Simulation Model for the Stator Subassembly of an Electronic Hydraulic Power Steering Syste
1Computer Simulation Model for the Stator
Subassembly of an Electronic Hydraulic Power
Steering System
Third Update November 13th, 2001
- Juan Soto
- Hugo Sanchez
- Carlos Terrazas
2Project Goal
3Objective
Make the transfer of the production line from
London to El Paso feasible through computer
simulation of its critical subassembly and the
factors affecting it.
4Agenda
- Project Status
- Introduction
- Project Summary
- Problems Encountered
- Future Work
- Conclusions
- Open Forum
5Project Status
- Data Collection Completed
- Simulation Model is close to completion
- Project is on schedule
6Project Status
7Background
DANA Automotive components manufacturer. Electron
ic Hydraulic Power Steering System
(EHPS). Prototypes produced in England. El Paso
Facility responsible for transition from
prototypes to mass production.
8Team Approach
Identify Critical Assembly
Identify Process
Identify Tasks
MOST Analysis
Determine Allowances
Model Constraints
Implement Into Model
Build Learning Curves
Give Recomen- dation
Gather Results
9Project Summary(work completed)
- Meetings with Dana
- Operation Process Charts
- MOST Work Measurement Analysis
- Learning Curves
10Project Summary(work completed)
Motor
Motor
Stator
Stator
The Subassembly was divided into five
subassemblies.
Manifold
EHPS
Manifold
EHPS
Rotor
Rotor
Pump
Pump
EHPS Subassemblies
EHPS Subassemblies
11Project Summary(work completed)
12Project Summary(work completed)
13Project Summary(work completed)
- Assembly Sequence
- Operations for each Process
14Project Summary(work completed)
Routing Sheet for Stator Subassembly
15Project Summary(work completed)
Bill of Materials for Stator Subassembly
16Project Summary(work completed)
MOST Time Measure Units (TMU) conversion to time
in seconds and minutes
17Project Summary(work completed)
18Project Summary(work in progress)
Draft of Simulation Model for the Stator
19Problems Encountered
Lack of information from the company. Time study
was substituted with MOST Work
Measurement. Videos were not delivered.
20Future Work
- Final Report and Presentation
- Arena5.0 Simulation Results
- Recommendations
21Conclusions
- Even though some of the data was available later
than expected, the project is still scheduled to
be completed on time. - Additional factors such as production forecast,
scrap rates, delivery times, and machine
characteristics will be added to the final model.
22Open Forum