S2 Project Management - PowerPoint PPT Presentation

1 / 12
About This Presentation
Title:

S2 Project Management

Description:

Project Countdown. Project Management. Tasks Status ... Countdown. 7 weeks to submission (6/23) 6 weeks to final draft (6/16) ... PM budget report & 'countdown' ... – PowerPoint PPT presentation

Number of Views:15
Avg rating:3.0/5.0
Slides: 13
Provided by: rjwi6
Category:

less

Transcript and Presenter's Notes

Title: S2 Project Management


1
S2 Project Management
  • Robert J. Wilson
  • Dept. of Physics
  • Colorado State University

2
Outline
  • Project Countdown
  • Project Management
  • Tasks Status
  • Budget Status
  • Related additional projects/funds
  • Summary

3
Countdown
  • 7 weeks to submission (6/23)
  • 6 weeks to final draft (6/16)
  • 5 weeks to last pre-submission collaboration
    meeting (6/9)
  • 4 weeks to 100 completion of all tasks and 3rd
    draft (6/2)
  • 2 weeks to post-workshop (2nd) draft (5/19)
  • 0 weeks to Capstone Workshop (5/4)
  • Review of conceptual design by International
    Advisory Board
  • 0 weeks to 1st drafts (4/28)
  • - 5 weeks NSF Site Visit (3/28-29)
  • This presentation is an update of that PM report
    designed to demonstrate that we could manage a
    complex project with a diverse, large and
    growing collaboration

4
Project Tracking
  • Monthly collaboration meetings
  • PM budget report countdown
  • Each committee chair gives status report on
    progress with S2 tasks
  • Overlapping responsibilities identified and
    resolved
  • Individual follow-up by PM and PI
  • Tasks completion spreadsheet
  • Sent to committee chairs/co-chairs individual
    follow-up by PM
  • Bi-weekly Executive Committee and/or Council
    teleconference
  • Budget
  • Each month PM provides updated budget spreadsheet
    to CSM, CU, CSU, SBU and UNL PIs they update
    with actual expenditures for previous months and
    projections through project completion
  • S2 Interim Report (Jan. 06)
  • Dry run for CDR over-length drafts edited to
    size
  • Happy with the result

5
Project Tasks
  • S2 proposal tasks (55 in all)
  • CD Developing a Plan for Short-term and
    Long-term Experiments at Henderson DUSEL
  • DP Developing the Infrastructure
  • GS Geological and Geotechnical Site
    Characterization
  • CU Handling Construction Uncertainty
  • HS Health and Safety
  • EA Environmental Considerations
  • PM Permitting
  • SI Shared Infrastructure Considerations
  • PS Assessing Public Support
  • CO National and International Cooperation
  • EO Broader Impact Plan
  • These map very well onto CDR requirements
    outlined in Cooperative Agreement NSF 05-506

6
Tasks Tracking
  • Essentially all critical tasks on track for
    completion by 6/02/06
  • This workshop is a significant completion
    activity for several tasks
  • Some tasks identified as more appropriate for TDR
  • HS-4 Complete safety assessment after design
    completion procedures for review and risk
    assessment are specified in the license agreement
  • EA-2 Complete environmental assessment after
    design completion procedures for review and risk
    assessment are specified in the license agreement
  • PM-2 Permitting for specific experiments
    approval process is specified in the license
    agreement
  • Some tasks (hatched) essentially complete at CDR
    level continue into TDR

7
Budget
  • 499,971 project funds received at SBU Oct. 05
    indirect costs waived at all institutions
    200,000 contribution
  • 4/1/06 43 of budget expended at month 6 of 9
    (66 project period elapsed)
  • Expenditures and projections are tracking well to
    original S2 proposalsome re-direction within
    institutions
  • Henderson characterization - opportunity to do
    additional bio-sampling too good an opportunity
    to pass up!
  • Engineering expenditures lower in 1st half due to
    engineering consultant change
  • Some salaries and capstone workshop back-loaded
  • Additional personnel added for EO (plus donation
    from The Arapaho Project Inc.)
  • Lower first workshop costs and use of additional
    sources of funds (institutions)
  • 25 travel increase due to collaboration growth
  • MS budget reduced institutional contributions
  • No significant S2 tasks budget concerns!

8
Additional Funding (1)
  • Harrison Mountain characterizationSubstantial
    amount of geologic information from surface and
    the adjacent Red Mountain, but decided that
    additional subsurface information was essential
  • Pre-S2 submission core drill 1 to Central
    Campus region
  • Post-S2 award core drill 2 to Lower Campus
    region
  • Core Drill 1 - cost
  • Core drill bid 104,000 standby estimate
    (Henderson) 16,000 120,000
  • Plus contingency (15) 18,000 Total cost
    estimate 138,000
  • Actual invoice 116,172.50
  • Funding sources
  • Contributions Stony Brook 60,000 CSU 30,000
    CU 17,000 CSM 10,000 Arapaho 3,000 40,000
    from Dept. of Local Affairs (DOLA)/Clear Creek
    County
  • Total direct contributions 160,000
  • Large indirect contributions
  • CSU management of funds and contracts waived
    indirect costs (CSU) core analysis (CSM)
    drilling subcontract, management and oversight
    provided by Henderson countless hours of other
    collaborators especially from SBU, CSU, CSM,
    Arapaho, UNL etc.

9
Additional Funding (2)
  • Core Drill 2 - cost
  • Core drill bid 201,000 standby (Henderson)
    30,150 231,150
  • Plus contingency (15) 34,673 Total cost
    estimate 265,823
  • In-progress At 75 completion, we are well
    within TEC
  • Funding sources
  • Contributions Stony Brook 100,000 CSU 50,000
    CU 50,000 CSM 50,000 75,000 from Dept. of
    Local Affairs (DOLA) award to Clear Creek County
    40,000 Colorado Office Economic Development and
    International Trade (COEDIT)
  • Total direct contributions 365,000
  • Continued significant indirect contributions from
    collaborators and their institutions
  • Balance of contributions
  • Core logging and analysis geophysical
    visualization biological sampling and analysis
    collaboration meetings, capstone travel etc.

10
Additional State Funding
  • Colorado Senate Bill SB06-229
  • Allocates 20 million towards DUSEL Visitor
    Center and Administration buildings.
  • Last week passed Senate committees unanimously
    Monday - senate floor vote 34-1!
  • Yesterday passed House State Affairs committee
    unanimously - testimony by Colorado Lt. Gov. Jane
    Norton, Colorado Dept. of Natural Resources
    Director Russell George, Arapaho Project Inc.
    Exec. Director Steve Schultz
  • State House floor vote within a few days
  • HUSEP State Commission
  • Established by Executive Order of the Governor
  • Heads of all relevant State agencies
  • Monthly meetings chaired by Lt. Governor Jane
    Norton
  • Have identified additional gt1 million potential
    funds for next round good faith contribution to
    Henderson DUSEL proposal development

11
CDR Status
  • Required content as directed by Cooperative
    Agreement NSF 05-506
  • 100 pages long
  • No attachments
  • Most essential S-2 tasks 90-100 complete
  • Deadline for all tasks except document prep June
    2nd
  • Draft section page allocations issued
  • Committees to provide Long and CDR-ready
    documents
  • More than 130 pages in-hand
  • CDR Goal Conceptual design for presentation at
    capstone workshop andreview by International
    Advisory Board - Saturday afternoon
  • Writing retreat of HUSEP Council, June 5-8
    Estes Park, Colorado
  • Final S2 collaboration meeting, June 9th
    CSU-Denver Center

12
Summary
  • Original core team extended with addition of many
    experienced and next generation members across
    the whole spectrum of DUSEL science and
    engineering
  • Financial issues minimized thanks to strong
    institutional, CMC and State support
  • Valuable experience working as a broad-based team
    to get and spend money effectively
  • Essentially all S2 funds used as proposed have
    almost tripled the NSF investment with additional
    contributions
  • Climax Molybdenum Co/Phelps Dodge have invested gt
    400,000
  • State is likely to contribute gt 20 million to
    strengthen the Henderson DUSEL proposal
  • S2 Project is on track, on budget, on time.
  • Much hard work in the next weeks but we will
    deliver a compelling Henderson DUSEL CDR by June
    23!
Write a Comment
User Comments (0)
About PowerShow.com