What will it take to get data out of the CFT - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

What will it take to get data out of the CFT

Description:

Cassette production. Approximately 50% of sub ... production cassettes assembled. All cassettes leaving factory have ... Cassettes: In DAB June/July (30-ish, ... – PowerPoint PPT presentation

Number of Views:34
Avg rating:3.0/5.0
Slides: 19
Provided by: AlanD152
Category:
Tags: cft | cassettes | data | out | take

less

Transcript and Presenter's Notes

Title: What will it take to get data out of the CFT


1
What will it take to get data out of the CFT?
  • Don Lincoln
  • CFT Commissioning Czar
  • Fermilab
  • Run II Meeting
  • May 12, Y2K
  • thats Johns title, not mine........

2
What will it take to get data out of the CFT?
  • Work
  • Lots and Lots of Work

3
Central Fiber Tracker Status
  • 8 layers
  • Outer 6
  • 2.52 m
  • Inner 2
  • 1.66 m
  • r - .2 to .51 m
  • Axial readout to south
  • VLPC Readout
  • Waveguide system
  • 8-11.5 m
  • Pipes light from detector to VLPCs

4
CFT Status - Done Stuff
  • Fiber Ribbons (roughly 400 ribbons)
  • VLPC Characterization 17,000 chips tested, 15,500
    OK
  • VLPC Recovery 2,200 tested, 1,100 recovered
  • So total useful chips 16,600

5
CFT Status - Ribbon Mounting
Going Very Well - To Spec
30 mm rms
Last cylinder (1) getting stereo ribbons attached
now Project Tomorrow completion
50 mm e-e offset
6
CFT Status - Nesting
Cylinders 8,7,6,5,4 3 nested CFT Completion -
5/19/00 Delivered to DAB by 6/15/00
Global precision 15 mm (Measured vs Desired)
7
CFT Status - Waveguides
  • Waveguide Production
  • CPS complete (IU)
  • Fiber pulling/sheathing at ND 75 complete for
    CFT
  • Fiber sorted
  • Best (attn.L from Kuraray) - longest runs
    8-11.5m
  • FPS at IU
  • CFT WG Connectorization
  • At ND Fermilab IU
  • 50 with curved end connectors
  • Expect to complete production in August (100
    July 15)
  • CFT Hookup and commissioning complete by 9/1/00

8
CFT Status - Readout System
  • VLPC Characterization/test/sort now complete
  • Cassette Assignment
  • As shown (includes cassettes 1-10)

9
CFT Status - Readout System II
  • Cassette production
  • Approximately 50 of sub-component complete
  • All components in-house except Flex circuit
  • Flex Circuit
  • Production deliveries starting
  • 600 of 2000 in hand
  • 100/week

10
CFT Status - Readout III
  • Cassette Test - Going Well
  • Noise low (Stereo Board)
  • Good uniformity

11
CFT Status - Cryo
  • Fabrication delayed by delivery of top plates
  • Now in house
  • To spec
  • Making up some time
  • Welding going well
  • Final Cryo Operational in June

12
CFT Status - Conclusions
  • CFT construction is going well
  • Mechanical assembly is to specification
  • Complete in mid-May
  • VLPC Cryo
  • VLPC characterization/selection complete
  • 1024 channel cassettes working well
  • Cassette production assembly underway
  • Subcomponents 50 complete
  • First 10 (11?) production cassettes assembled
  • All cassettes leaving factory have met
    specifications
  • CFT wave guide production
  • Fiber pulling/sheathing going well (far along)
  • Connectorization underway

13
Major Installation Activities During Next 3 Months
April May
June July
Collision Wall down Hi Bay full


survey
to July 15
Collision Wall back up
Collision Wall down
Install/align CFT
Platform moves pick up EF north/south
Install gas/cooling lines in Collision Hall
Solenoid Test
Install CFT cable ductwork in platform
survey
Install VLPC cryostats in platform
End detectors installed (FPS, ICD, L0)
survey
Survey east PDTs
Forward Muon Installation
Rework/reassemble shielding mid-pieces
Rework EF shielding pieces
survey
Stage/survey N/S shielding
survey
survey
Install South truss in Hi Bay, re-weld arms
Install both EF shields
Install EMC-S MDTs and pixels
  • Crane needed
  • Platform occupied
  • ICR occupied
  • CF closed no cal preamp access

Disassemble EMC-S for move to sidewalk
survey
survey
Install N/S A-layer pixels
Install N/S A-layer MDTs
14
DO TimelineVersion N
2000
2001


J
F M A M J J A S
O N D J F M
D
South half
North half
CFT install/hookup
Install/hookup/checkout SMT
Roll in detector
Platform moves
All VLPCs installed
1/2 VLPCs installed
Beam-ready
Install silicon front-end
Remove shield wall
Install final CFT electronics
Waveguide production
Run II begins Mar 1, 2001
1st CFT crate operational
Cosmic Ray Commissioning
Phase I Central muon, DAQ, RECO,
trigger, silicon front-end
Phase II Tracker Commissioning
(CFT, SMT, PS), VLPCs, Forward Muon
Phase III Full Cosmic Ray Run
(add CAL, full TRIG SMT)
15
Commissioning Plan
  • CFT arrives DAB mid-June, install and survey
    (Gaston)
  • Cryostat install and hookup through mid June,
    testing cooldown followed by cassette insertion,
    end of June (Russ)
  • As waveguides hooked up (CPS, 8, 7, etc.),
    testing is needed
  • Current plan
  • 2 people/crew, 2 crews/shift, 2 shifts/day, 2
    LG/crew/shift
  • 8 lightguides/day. (300 CFT light guides ? 8
    weeks)
  • Initial test, LED pulsers on the ribbons,
    secondary electrical.
  • Verify light continuity.
  • Verify photoelectron noise consistent with
    temperature and voltage
  • Electrical noise.

16
Needed Components ?
  • CFT cylinders In DAB mid-late June
  • Cryostat Operational late-June
  • Cassettes In DAB June/July (30-ish, 11 in
    hand now)
  • LHe Tested already, hiatus early
    July (end iron)
  • Lightguides In DAB June/July, all CPS, 100
    CFT (7/8 S/A)
  • Cables In house (AFE ? sequencer ?
    VRB)
  • DAQ Running now
  • Unpacking SVX unpacking done, some mapping
    remains.
  • Examines Available now, will need tweaking
    for commissioning
  • Cosmics Piggyback on muon trigger
  • Tracking Cosmic tracking mostly OK, minor
    technical fixes
  • Event Display Ready in some form

17
Needed Components ?
  • Front End Electronics
  • AFE not available, use stereo board, limited
    availability
  • LED Electronics
  • Two components, small card (300-ish), large
    driver/control card (10-ish)
  • Small cards available early June
  • Large controller cards maybe available
    mid-August...Gack!
  • Sequencer ? VRB cable pull late July
  • Silicon uses same cables, need splitter, not
    available
  • Can pull the small number of CFT fiber optic
    cables first
  • CFT Online guru
  • CFT Calibration guru Not yet filled
  • Control/Download guru


18
Summary
  • Much of the required components are in place for
    mid-July hookup/commissioning
  • Some arent
  • They will be