Title: What will it take to get data out of the CFT
1What will it take to get data out of the CFT?
- Don Lincoln
- CFT Commissioning Czar
- Fermilab
- Run II Meeting
- May 12, Y2K
- thats Johns title, not mine........
2What will it take to get data out of the CFT?
- Work
- Lots and Lots of Work
3Central Fiber Tracker Status
- 8 layers
- Outer 6
- 2.52 m
- Inner 2
- 1.66 m
- r - .2 to .51 m
- Axial readout to south
- VLPC Readout
- Waveguide system
- 8-11.5 m
- Pipes light from detector to VLPCs
4CFT Status - Done Stuff
- Fiber Ribbons (roughly 400 ribbons)
- VLPC Characterization 17,000 chips tested, 15,500
OK - VLPC Recovery 2,200 tested, 1,100 recovered
- So total useful chips 16,600
5CFT Status - Ribbon Mounting
Going Very Well - To Spec
30 mm rms
Last cylinder (1) getting stereo ribbons attached
now Project Tomorrow completion
50 mm e-e offset
6CFT Status - Nesting
Cylinders 8,7,6,5,4 3 nested CFT Completion -
5/19/00 Delivered to DAB by 6/15/00
Global precision 15 mm (Measured vs Desired)
7CFT Status - Waveguides
- Waveguide Production
- CPS complete (IU)
- Fiber pulling/sheathing at ND 75 complete for
CFT - Fiber sorted
- Best (attn.L from Kuraray) - longest runs
8-11.5m - FPS at IU
- CFT WG Connectorization
- At ND Fermilab IU
- 50 with curved end connectors
- Expect to complete production in August (100
July 15) - CFT Hookup and commissioning complete by 9/1/00
8CFT Status - Readout System
- VLPC Characterization/test/sort now complete
- Cassette Assignment
- As shown (includes cassettes 1-10)
9CFT Status - Readout System II
- Cassette production
- Approximately 50 of sub-component complete
- All components in-house except Flex circuit
- Flex Circuit
- Production deliveries starting
- 600 of 2000 in hand
- 100/week
10CFT Status - Readout III
- Cassette Test - Going Well
- Noise low (Stereo Board)
- Good uniformity
11CFT Status - Cryo
- Fabrication delayed by delivery of top plates
- Now in house
- To spec
- Making up some time
- Welding going well
- Final Cryo Operational in June
12CFT Status - Conclusions
- CFT construction is going well
- Mechanical assembly is to specification
- Complete in mid-May
- VLPC Cryo
- VLPC characterization/selection complete
- 1024 channel cassettes working well
- Cassette production assembly underway
- Subcomponents 50 complete
- First 10 (11?) production cassettes assembled
- All cassettes leaving factory have met
specifications - CFT wave guide production
- Fiber pulling/sheathing going well (far along)
- Connectorization underway
13Major Installation Activities During Next 3 Months
April May
June July
Collision Wall down Hi Bay full
survey
to July 15
Collision Wall back up
Collision Wall down
Install/align CFT
Platform moves pick up EF north/south
Install gas/cooling lines in Collision Hall
Solenoid Test
Install CFT cable ductwork in platform
survey
Install VLPC cryostats in platform
End detectors installed (FPS, ICD, L0)
survey
Survey east PDTs
Forward Muon Installation
Rework/reassemble shielding mid-pieces
Rework EF shielding pieces
survey
Stage/survey N/S shielding
survey
survey
Install South truss in Hi Bay, re-weld arms
Install both EF shields
Install EMC-S MDTs and pixels
- Crane needed
- Platform occupied
- ICR occupied
- CF closed no cal preamp access
Disassemble EMC-S for move to sidewalk
survey
survey
Install N/S A-layer pixels
Install N/S A-layer MDTs
14DO TimelineVersion N
2000
2001
J
F M A M J J A S
O N D J F M
D
South half
North half
CFT install/hookup
Install/hookup/checkout SMT
Roll in detector
Platform moves
All VLPCs installed
1/2 VLPCs installed
Beam-ready
Install silicon front-end
Remove shield wall
Install final CFT electronics
Waveguide production
Run II begins Mar 1, 2001
1st CFT crate operational
Cosmic Ray Commissioning
Phase I Central muon, DAQ, RECO,
trigger, silicon front-end
Phase II Tracker Commissioning
(CFT, SMT, PS), VLPCs, Forward Muon
Phase III Full Cosmic Ray Run
(add CAL, full TRIG SMT)
15Commissioning Plan
- CFT arrives DAB mid-June, install and survey
(Gaston) - Cryostat install and hookup through mid June,
testing cooldown followed by cassette insertion,
end of June (Russ) - As waveguides hooked up (CPS, 8, 7, etc.),
testing is needed - Current plan
- 2 people/crew, 2 crews/shift, 2 shifts/day, 2
LG/crew/shift - 8 lightguides/day. (300 CFT light guides ? 8
weeks) - Initial test, LED pulsers on the ribbons,
secondary electrical. - Verify light continuity.
- Verify photoelectron noise consistent with
temperature and voltage - Electrical noise.
16Needed Components ?
- CFT cylinders In DAB mid-late June
- Cryostat Operational late-June
- Cassettes In DAB June/July (30-ish, 11 in
hand now) - LHe Tested already, hiatus early
July (end iron) - Lightguides In DAB June/July, all CPS, 100
CFT (7/8 S/A) - Cables In house (AFE ? sequencer ?
VRB) - DAQ Running now
- Unpacking SVX unpacking done, some mapping
remains. - Examines Available now, will need tweaking
for commissioning - Cosmics Piggyback on muon trigger
- Tracking Cosmic tracking mostly OK, minor
technical fixes - Event Display Ready in some form
17Needed Components ?
- Front End Electronics
- AFE not available, use stereo board, limited
availability - LED Electronics
- Two components, small card (300-ish), large
driver/control card (10-ish) - Small cards available early June
- Large controller cards maybe available
mid-August...Gack! - Sequencer ? VRB cable pull late July
- Silicon uses same cables, need splitter, not
available - Can pull the small number of CFT fiber optic
cables first - CFT Online guru
- CFT Calibration guru Not yet filled
- Control/Download guru
18Summary
- Much of the required components are in place for
mid-July hookup/commissioning - Some arent
- They will be