Title: Safety%20Organization%20and%20Safety%20Measures%20for%20the%20Installation%20of%20LHC%20Experiments%20at%20CERN
1Safety Organizationand Safety Measures for the
Installation ofLHC Experiments at CERN
Marc Tavlet, GLIMOS / ALICE CERN, Switzerland,
Europe ?
2Safety Organizationand Safety Measures for the
Installation ofLHC Experiments at CERN
- Outline
- Safety Organization
- Safety Teams
- Procedures for personnel (and visitors)
- Procedures for the work
- However, accidents do happen
- Conclusions ?
3http//alice.web.cern.ch/Alice/Engineering/picture
s/alices2.gif
4http//maridor.home.cern.ch/maridor/pic_alice/LAYO
UT_2K/lay_out.html
5Safety Organization at CERN,according to
SAPOCO/42
- Safety responsibilities follow the managerial
lines - This scheme will be follow when the detectors are
commissioned and the experiments are put into
operation. - This scheme is valid outside LHC work-sites. Ex
Test beam areas. - SAPOCO/42 CERNs law in mater of safety
http//safety-commission.web.cern.ch/safety-commis
sion/sapoco42/index.html
DG / CEO
PH Dept Head
Tech. Coord. / GLIMOS
Project Leader
Project Engineer
Draftsmen, technicians, users
6BUT, Safety Organisation for LHC Experiment
Installations
Overall responsibility of the Experiment ( PH
Department )
Installation under the responsibility of
TS Department
Experimental Area Manager (EAM) TSO
Technical Coordinator / GLIMOS
RSO, FGSO
Work-Package Eng.
Project Leaders
Safety Coordinator
Work-Package Supervisors
Project Engineers
Designers, technicians, users
Workers, technicians, users
7Safety Team / Design
- GLIMOS Group Leader in Matter of
Safety, accountable to the PH Department
Head, responsible for the overall safety of the
Expt. - FGSO Flammable Gas Safety Officer
- RSO Radiation Safety Officer
- INB link-person (French legislation / Nuclear
Installations) - Safety Coordinators professionals who help the
Glimos, EAM and any supervisor - Experts of the Safety Commission
8Examples of Engineering Designs for better Safety
in the Detector
- Use of halogen-free flame-retardant cables
(IS-23) - Use of halogen-free flame-retardant materials
(IS-41) - Halogen-free Printed Circuit Boards wherever
possible - Avoid Polystyrene, Nylon (PVC is forbidden !)
- Metallic pipes for cooling instead of plastic
ones - Silicone rubber to replace EPDM
- Non-flammable gas mixtures
- Sniffer N2 inertion systems
- Safe switch-off of LV-PS in case of power failure
- Grounding of all LV- and HV-PS
- Fix ladders and platforms for better access
9Safety Team / Installation
- GLIMOS Group Leader in Matter of Safety
- TSOs Territorial Safety Officers
- EAM Experimental-Area Manager
- Safety Coordinators professionals who help the
Glimos and the EAM - Team for First-Aid (in any building)
- Fire-Fighters of the Safety Commission
- Inspectors of the Safety Commission
10Examples of measures taken for better Safety
during Installation
- Fire detection already operational
- Escape routes identified
- Priority to collective equipment vs personal ones
- Enforce wearing personal protective equipment as
well - Use scaffoldings (mounted by trained people)
instead of ladders - Any platform higher than 80cm must have
protection barriers plinths - Adapted ladders and platforms to access strange
devices
11Procedure for Staff-Members
- Safety Training for any new-comer
- specific training on the spot by Glimos
supervisor - specific training according to activities
(welding, lifting, work at height, ) - Access rights (for specific areas - ?)
- Safety equipment
- - standard
- specific
12Rules for Visitors
- Visitors must be accompanied by a trained guide
- Max 12 visitors/guide on surface
- Max 7 visitors/guide underground
- Visitors must wear comfortable shoes helmet
- Specific training (incl. Safety) for guides
- Dedicated visit circuits for guided tours
13Procedure prior the start of work at experimental
areas
A.O.C.
( Fire Permit )
W-P. Eng.
E.A.M.
Safety Coordinator
W-P. A.M.
Glimos
initiates
check
14Display of safety documents procedure at the
place of work
15Review of Accidents during ALICE installation
Place Dept Event Victim Damage
SXL2 PH Machining in the workshop (2 X) hands 0
SXL2 PH Fall from a 80 cm platform bassin 0
SXL2 PH Fall against a machine lip 0
SXL2 TS Break and fall of a hinge from a high door no hinge
SX-2 TS Overhead crane no major
UX-25 TS Overhead cranes (2 X) no minor
UX-25 PHTS Break of a tie-rod of dipole no tie-rod
UX-25 PHTS Scaffolding into the dipole no scaffolding
16The overhead-crane accident
- No precise written procedure
- Procedure not followed
- - Modification of attachment point.
- Modification of safety switches.
- - Crane hook went into crane frame.
17The scaffolding accident
- Precise procedure was written
- Procedure exclude the use of the steel
scaffolding - Staff ignored the interdiction.
- Consequence ?
- (fortunately, no one injured)
18Conclusions
- We do have
- a safety plan, a safety team,
- safety procedures for personnel,
- safety training adapted to places and activities,
- safety procedures, including safety visits for
work. - However, accident do happen !
- Ways to reduce accident occurrence
- More supervision on the spot,
- TALK to people (team spirit)
- any good idea ?