Title: American Recovery and Reinvestment Act Projects for Bechtel Jacobs Company LLC
1American Recovery and Reinvestment Act Projects
for Bechtel Jacobs Company LLC
- June 25, 2009 Roane County Alliance
2East Tennessee Technology Park Remediation
- Deactivated 295 facilities
- Characterized 277 facilities
- Demolished 220 facilities
- Reduced footprint by about 1.2 million ft2
3ARRA Bechtel Jacobs Company LLC
- Five Projects approved for American Recovery and
Reinvestment Act (ARRA) funds - ARRA projects must be completed by September 30,
2011 - Work performed by BJC and subcontractors
4(No Transcript)
5ARRA Staffing
-
- Total
Staffed Open -
- Salaried 89 (9/30/09) 46
43
-
- Craft Labor 130 (9/30/09) 23
107
6Project Overview
K-27 Pre-Demolition
7K-27 Building
8K-27 Pre-Demolition
Overview
- K-27 Building is one of the early gaseous
diffusion facilities at ETTP - Has been shut down since 1964
- Covers 383,000 ft2
- Contains 540 stages of gaseous diffusion
equipment
- Similar in construction to the K-25 Building with
structural challenges
9K-27 Pre-Demolition Scope of Work
- Prepare the K-27 Building for demolition and
disposition of all waste generated. The K-27
Building consists of nine building units
occupying a 383,000 ft2 "footprint" with over 1.1
million ft2 of total floor area. - Deactivation of utilities
- Asbestos abatement, hazardous material abatement,
and universal waste removal - Vent, purge, drain, and foam operations
- Characterization of system and building structure
- High risk equipment (HRE) removal, HRE
segmentation, and mining - Criticality incredible determination
10K-27 Pre-Demolition Execution/Technical Approach
- Majority work to be self performed
- Asbestos abatement to be subcontracted
- Support subcontractors include Radcon/IH,
electrical, nuclear safety, training,
administrative, engineering, characterization,
and NDA - Packaging and transport for disposal of Tc-99
cylinders to be subcontracted
11K-27 Pre-Demolition Staffing
- 72 non-manual (130 manual) Total Positions
- 39 (42) Filled Positions
- 33 (88) Open
- Craft 88
- Eng 5
- Operations 6
- Performance/ Quality 2
- Field Services 11
- Waste Generator - 4
- Administrative Services 1
- ESH 3
- Human Resources (Training) - 1
- Staffing for the first 120 days will be adjusted
after detailed estimates - are completed and a baseline schedule is
established.
12K-27 Pre-Demolition
Schedule
- Complete planning and preparation activities
- Duration of field work
- Project Completion
4 months from funding release 27 months from
start of field work September 2011
13Project Overview
Environmental Management Waste Management
Facility (EMWMF) Expansion
14EMWMF Expansion
Overview
- EMWMF was constructed as a repository for waste
generated as part of BJC's cleanup work - Currently accepting waste from K-25 Demolition
project, K-1070 Burial Ground, and other ETTP DD
Projects
- Current capacity is 1.2 million yd3 (Cells 1-4)
Cell 5 expansion will increase capacity to 1.65
million yd3
15EMWMF Expansion (contd.)
Scope of Work
- Construction
- Site preparation on-siteborrow area
development - Geologic buffer
- Structural fill
- Low perm clay liner
- Geomembrane geosynthetics
- Leachate system including 6th leachate tank
- Security fence lights
- Instrumentation controls, and support
facilities - Construction quality assurance
- Construction quality control
16EMWMF Expansion (contd.)
- Staffing - peak man/non-man
- FY2009 55/20
- FY2010 50/20
17EMWMF Expansion (contd.)
Schedule Milestones
- Start of field work (parallel with design)
- Low perm clay geomembrane complete
- Construction complete
- Cell 5 availability
28 May 2009 (A) 24 November 2009 18 June
2010 31 August 2010
18Project Overview
ORR Landfill Expansion
19ORR Landfill Expansion
Overview
- Landfill V is located near Y-12
- Disposal of sanitary, industrial, construction,
and demolition waste - Expansion and upgrades needed for increased
disposal rates from ARRA work
Expansion Area
- Expansion will increase capacity by 385,000 yd3
20ORR Landfill Expansion (contd.)
Scope of Work
- Design and construct Landfill V, Area IV
- Construction Quality Assurance
- Upgrade refurbish support facilities and
equipment - New truck inspection station
- Leachate header from ILF-IV to Y-12 sewer
- New leachate pumps for ILF-V
21ORR Landfill Expansion (contd.)
- Staffing peak man/non-man
- FY2009 0/6
- FY2010 30/6
- FY2011 30/6
22ORR Landfill Expansion (contd.)
Schedule Milestones
- Complete Design
- Start Construction of Landfill V, Area IV
- Finish Construction of Landfill V, Area IV
Support Facilities
05 February 2010 08 April 2010 11 January 2011
Challenge
- Interface of the expansion activities with
operational activities of the landfill and other
nearby facilities
23Project Overview
Tank W-1A
24Tank W-1A Removal Action
25Graphite Reactor (3001)
Bethel Valley Road
Central Ave
First Street
Tank W-1A
Tank W-1A
26Tank W-1A Removal Action (contd.)
- Scope of Work
- Excavate, package, and transport 250 cy of LLW
soil to NTS for disposal - Excavate, package, and transfer 110 cy of RH-TRU
soil to temporary storage - Load TRU soil drums into RH canisters and load
canisters into 72-B shipping casks for shipment
to Waste Isolation Pilot Plant (WIPP) in New
Mexico - Concrete pad, tank
- shell, and tank support
- to NTS
27Tank W-1A Removal Action (contd.)
- Staffing peak man/nm
- FY2009 10/13
- FY2010 10/14
- FY2011 7/14
28Tank W-1A Removal Action (contd.)
Schedule
- Build weather
- enclosure
- Complete Operational Readiness Review
- Complete TRU Waste Removal and Packaging
- Waste Transfer to WIPP
3Q FY10 4Q FY10 1Q FY11 4Q FY11
29Project Overview
Melton ValleyMonitoring Wells
30Melton Valley Offsite Monitoring Wells
- Overview
- Routine monitoring detected constituents of
concern in Picket Wells (Sentinel Wells) - Regulatory decision to modify the monitoring plan
and install 16 offsite monitoring wells to expand
monitoring beyond Clinch River
31Melton Valley Offsite Monitoring Wells (contd.)
- Scope of Work
- Develop new drilling subcontract (small business)
- Develop monitoring plan for regulator approval
- Develop project planning documents
- Survey properties and layout wells
- Construct access roads with BJC resources
- Drill and install 16 wells
- Perform borehole tests
- Collect groundwater samples for 4 quarters
- Develop completion letter to regulators
32Melton Valley Offsite Monitoring Wells (contd.)
- Staffing average BJC/SC
- FY2009 5/1
- FY2010 4/4
- FY2011 .5/.7
33Melton Valley Offsite Monitoring Wells (contd.)
Schedule
- Pre-field planning and documentation
- DOE obtain access rights
- Install monitoring wells
- Post-construction monitoring starts
- Project completion
4Q FY09 4Q FY09 2Q FY10 2Q FY10 3Q FY11
34Required Skills for ARRA Funded Projects
Manual
- Building Trades Craft
- Laborers
- Iron workers
- Carpenters
- Electricians
- Pipe fitters
- Teamsters
- Operating Engineers
35Required Skills (contd.)
Non-Manual
- Engineers (mechanical, electrical, structural,
project, construction, civil) - Superintendents
- Nuclear safety/criticality safety engineers
- ESH
- IT
- Project controls (estimators, schedulers)
36Job Postings
- Bechteljacobs.org
- Salaried only
- Check dailypostings change
- Must post for specific job
- BJC does not maintain resumes
- Subcontractors
- Majority of work performed by subcontractors
- List of BJC Subcontractors posted on the BJC
external website
37www.bechteljacobs.com
38.
39Q A
- The following slides are for reference during the
QA
40 Subcontractor Support
- K-27 Characterization Pre-Demolition
- Asbestos Abatement
- SB Set-Aside Issue RFP Est. 8/6/09
- Tc-99 Cylinders 2nd Qtr FY11
- MV Monitoring Well Scope
- Install four GW well clusters (16 wells total)
offsite to monitor for contamination. - SB Set-Aside RFP Issued 6/19/09
- Tank W-1A Removal Action
- Open Competition RFP Issued 6/23/09
41Subcontractor Support (cont'd.)
- EMWMF Cell 5 Expansion
- Construction Awarded 4/22/09 Avisco, Inc.
- Quality Assurance Awarded 5/18/09 Aquaterra
- Geocomposite Liner Supply and Install Award
Pending - Quality Control Existing Blanket w/
Professional Engineers - Security Fencing / Lighting
- SDB Set-Aside - RFP 1st Qtr FY10
- ORR Sanitary Landfill Expansion
- Construction Services
- SB Set-Aside Est. RFP 1st Qtr FY10
- Construction Quality Assurance
- SB Set-Aside Est. RFP 1st Qtr FY10
- Construction Quality Control
- Existing Blanket w/ Professional Engineers
42Subcontractor Support (cont'd.)
- Utilization of existing Subcontract Blanket
Agreements wherever possible to support ARRA
funded work - Utilization of existing Blanket Purchase Orders
wherever possible to fulfill material and
equipment requirements for ARRA funded work