LQS01 Test Preparation and Test Plan - PowerPoint PPT Presentation

About This Presentation
Title:

LQS01 Test Preparation and Test Plan

Description:

In this case system would not only detect a fault to ground but ... system will be used to investigate instabilities and conductor motion during quench studies. ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 16
Provided by: technical87
Category:

less

Transcript and Presenter's Notes

Title: LQS01 Test Preparation and Test Plan


1
LQS01 Test Preparation andTest Plan
  • LARP Collaboration Meeting 12
  • LBNL - April 8-10, 2009

2
Outline
  • Introduction
  • LQSD Test Experience
  • LQS01 Test Preparation
  • Quench Detection System with Adaptive Thresholds
  • Symmetric Coil Grounding
  • Active Ground Fault Monitoring System (Proposal)
  • Reconfiguration of the Magnet Protection System
  • Modified Strain Gauge Readout System
  • LQS01 Test Plan (Draft)
  • Summary

3
Introduction
  • LQS01 test at Fermilab in Aug.-Sep. 2009 is an
    important milestone for the LARP magnet program
  • LQS01 the first 4-m long Nb3Sn quadrupole to
    test in the Vertical Magnet Test Facility (VMTF)
    at Fermilab
  • 4-m long Nb3Sn dipole coils previously were
    successfully tested
  • More technological and mirror quadrupoles will be
    tested to investigate different magnet and cable
    parameters
  • pre-load settings, new cable design, collar
    style
  • Various elements of test facility need to be
    modified in order to meet LQ test program
    requirements

4
LQSD test experience
  • LQSD Long quadrupole mechanical structure with
    dummy coils was successfully tested at Fermilab
    in 2nd half of March
  • One of the important goals of the test was a
    cryogenic performance
  • Trying to hold a certain temperature gradient ?T
    along the body of the magnet.
  • Cool down performed using a helium
  • gas flow. At 100 K, the vessel was filled
  • with a liquid nitrogen.
  • 48 hrs of cool down will be necessary
  • for LQS01 to reach 4.5 K if temperature
  • constraint is ?Tlt150 K
  • Total of 4 days including overnight idling
  • It will take 4 times longer if ?Tlt 50 K
  • LQSD Temperature at the top (black) and
  • bottom (red) during helium cooldown

T (K)
30 hrs To 200 K
?T50 K 15 hrs
?T150 K 24 hrs
5
LQSD test experience (contd)
  • LQSD warm up took 6 days, 14 hrs were spent
    just to evaporate LN2. For
  • LQS01 we will use a helium gas to warm up the
    magnet. We expect to reach 300 K in 4 days.
  • Liquid helium volume in the vessel is 500 L
  • LQSD test was very useful in
  • preparation to LQS01 test
  • To study mechanical performance
  • To study cryogenic performance
  • Obtained valuable experience of handling
  • a 4-m long and 14000 lbs magnet

T (K)
LQSD Temperature at the top (black) and bottom
(red) during the N2 warm up
6
LQS01 Test Preparation
  • Various improvements and upgrades are expected at
    the Fermilabs Vertical Magnet Test Facility
    (VMTF) in preparation to LQS01 test
  • Some of these modifications were planned long
    time ago (symmetric coil grounding), while some
    improvements were initiated after LQSD test
    (modification of the SG readout system)
  • All modified systems will be examined in advance
    when testing technological mirror quadrupoles
    (TQM)
  • Detailed handling procedure was very helpful for
    LQSD test. We will prepare it for LQS01 test too
    along with the detailed run plan.

7
Quench Detection System with Adaptive Thresholds
  • The Nb3Sn superconductor used in the 4-m long LQ
    magnets will produce relatively large voltage
    spikes. Raising the coil quench detection
    threshold adds delay to the quench detection time
    and the MIITs developed at high currents would
    exceed acceptable levels.
  • Voltage spike analysis in various
  • Nb3Sn magnets showed that both the
  • magnitude and quantity of voltage
  • spikes peak at a relatively low
  • current, and then drop off as magnet
  • current increases.
  • This behavior will allow us to adjust the
  • threshold dynamically to avoid trips at low
    currents while providing enough sensitivity at
    high current.

8
Quench Detection System with Adaptive Thresholds
  • Proposed solution is to use the FPGA based quench
    management (QM) system already developed and used
    to test HINS solenoids at Fermilab.
  • New FPGA based will work in parallel to the
    existing
  • VxWorks based QM system.
  • Interfacing an FPGA based
  • quench management system
  • to VMTF has already been
  • tested.
  • First full scale test will be done in
  • 2nd half of April at the end of
  • TQM02 test.

9
Symmetric Coil Grounding
  • The 30kA DC power system used for testing magnets
    in VMTF is grounded at one point on the negative
    current bus via a 25 Ohm current limiting
    resistor.
  • This "asymmetric" grounding configuration will be
    changed to a symmetric grounding scheme in
    which both the positive and negative bus will be
    grounded via two100 Ohm resistors to a center
    tap, which will be connected to ground through
    another 100 Ohm current limiting resistor.
  • With symmetric grounding the
  • maximum coil to ground voltage
  • will be 500 V (the power system
  • is designed for a max. of 1000 V)
  • Symmetric grounding was tested
  • several times and will be implemented on a
    permanent base in April.

10
Active Ground Fault Monitoring System (Proposal)
  • An active ground fault monitoring system at VMTF
    was recently proposed in order to increase
    sensitivity to the detection of ground faults
    which would not depend on the location of the
    fault or the ramp rate and magnet inductance.
  • An active ground fault detection circuit would
    include an isolated 5V voltage source in series
    with the ground resistor. Since this is the only
    point
  • grounded there would be no ground
  • current as long as there are no
  • faults to ground we just raise the
  • ground level of the symmetric
  • grounding scheme to 5V above
  • ground.
  • In the event that a coil is shorted to ground
    then a voltage drop would develop across the 100
    Ohm ground resistor, which would trip the
    detection circuit when it reaches the desired
    threshold.

11
Active Ground Fault Monitoring System (contd)
  • It is proposed that the strip heaters also be
    grounded using the symmetric grounding scheme and
    that the active ground fault detection be
    implemented as well.
  • In this case system would not only detect a fault
    to ground but a fault
  • between the coil and the strip heater.
  • Currently internal review in progress
  • to estimate required time and
  • expenses. More discussions
  • are expected.

12
Magnet Protection System
  • Re-designed Magnet Protection System at VMTF
    includes 4 Heater Firing Units (HFU) for
    protection heaters and two HFUs for spot heaters.
  • Heater distribution box was designed to
  • accommodate up to 8 strip heaters in
  • total.
  • For LQS01 test we plan to connect 4 strip
  • heaters in parallel internally and then
  • connect to a separate HFU.
  • All elements of the system are ready and
  • will be tested by the end of April.

13
Modified Strain Gauge Readout System
  • In order to boost the strain gauge signals in
    LQS01 magnet we plan to use 4 current sources.
  • 2 Keithley current sources were used for 36
    strain gauges in LQSD magnet providing a maximum
    current of 1.25 mA.
  • We plan to increase data saving rate by splitting
    the SG and RTD (temperature) scans
  • Reference bridge was built at Fermilab for the
    calibration and monitoring of the strain gauge
    readout systems. Measurements with the LBNL
    portable and Fermilab SG readout systems showed
    very good agreement with the reference numbers.
  • LQSD SG data were read out with the LBNL portable
    system before and after the test. During the test
    we used the Fermilab SG readout system. We will
    continue the same practice for LQS01 test.
  • Modified SG readout system will be tested in
    June.

14
LQS01 Test Plan
  • Primary test goal is to demonstrate performance
    with scale-up of coil length in Nb3Sn magnets.
    Among other objectives are study how a thermal
    cycle affects the quench behavior, quench
    training performance vs. temperature and ramp
    rate. Voltage Spike Detection system will be used
    to investigate instabilities and conductor motion
    during quench studies.
  • 1st thermal cycle
  • Quench training at 4.5 K followed with the cool
    down to 3 K.
  • We will not test the magnet at a super-fluid
    temperature in 1st thermal cycle to avoid
    possible damage of coil.
  • Temperature dependence study
  • Warm up the magnet before 2nd thermal cycle
  • RRR measurements
  • 2nd thermal cycle
  • Quench training at 4.5 K
  • Quench training at 1.9 K
  • Protection Heater Study

15
Summary
  • Preparation to LQS01 test is in progress.
  • Various elements of the vertical magnet test
    facility at Fermilab will be modified to meet LQ
    test program requirements
  • FPGA based quench management system with adaptive
    thresholds
  • Symmetric coil grounding
  • Improved SG readout system
  • Modified magnet protection system
  • Active ground fault monitoring system (review in
    progress).
  • All modified systems will be tested in advance -
    before the LQS01 test
  • Mirror quadrupole (TQM) tests will be used for
    such a commissioning.
  • Run plan with 2 thermal cycles is drafted for
    LQS01 test.
Write a Comment
User Comments (0)
About PowerShow.com