San%20Francisco-Oakland%20Bay%20Bridge%20East%20Span%20Seismic%20Safety%20Project - PowerPoint PPT Presentation

About This Presentation
Title:

San%20Francisco-Oakland%20Bay%20Bridge%20East%20Span%20Seismic%20Safety%20Project

Description:

San Francisco-Oakland Bay Bridge. East Span Seismic Safety Project ... Holiday Inn Bay Bridge. 1800 Powell Street. Emeryville, California ... – PowerPoint PPT presentation

Number of Views:131
Avg rating:3.0/5.0
Slides: 57
Provided by: pcho7
Learn more at: https://dot.ca.gov
Category:

less

Transcript and Presenter's Notes

Title: San%20Francisco-Oakland%20Bay%20Bridge%20East%20Span%20Seismic%20Safety%20Project


1
San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project In Bay Foundation/SAS
Superstructure Constructability Workshop Nov. 20,
2002
2
In Bay Foundation/SAS Superstructure
Constructability Workshop
3
November 20, 2002Holiday Inn Bay Bridge1800
Powell StreetEmeryville, California
4
900 Welcome905 Opening Remarks915
Where we are now930 Business Enterprise
Outreach945-1030 Technical Issues/Changes
since May 13, 20021030-1045
Break1045-100 Open discussion with
contractors regarding above mentioned
issues
5
Who are we?
  • SFOBB Project Manager
  • Heavy Civil Construction Contractors
  • Fabricators, Suppliers

6
Why are we here?
  • meeting is mechanism to inform the contracting
    community of the upcoming SAS Superstructure and
    In Bay foundation contracts.
  • meeting is a way to create a dialogue with
    contractors, especially on issues of concern.
  • for example we heard at May 13, 2002 workshop,
    mobilization payment for an "over the water" job
    does allow an acceptable cash flow for primes. We
    effected a change to the Public Contract Code for
    jobs of 25 million over water

7
Tools
  • PowerPoint
  • Meeting notes
  • Handouts

8
Ground Rules
  • no decisions to be made
  • discussion only to take place
  • speakers keep to their time
  • dialogue to follow decorum in order to create an
    atmosphere of respect

9
What can we accomplish
  • understand changes made to Construction Contract
    since May 13, 2002 meeting
  • understand Contractor Constructability concerns
    with In Bay Foundation and SAS Superstructure
    Contracts

10
Other Introductions
  • Brian Maroney - Project Manager
  • Mike Halverson and Rob Kobal note takers
  • Bill Zanetich - Duty Senior
  • Design Team

11
Bid Schedule
12
Project Limits
13

OAKLAND TOUCHDOWN
SKYWAY
YBI
SAS
Existing Bridge
14
SAS/YBI Discretization
  • Smaller contracts that focus specific types of
    construction work create more opportunities for
    DBE and small business participation

15
T1/E2 foundations (04-0120E4)
Transition structure (04-0120H4)
E2
Retrofit/Substation (04-0120G4)
T1
SAS superstructure (04-0120F4)
W2 foundation (04-0120C4)
Building demolition (04A1701)
Yerba Buena Island
YBI/SAS Contracts
16
San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
17
W2 Structures 04-0120C4
  • bid open December 10, 2002
  • Gross Quantities
  • 16,000 cubic meter structural excavation
  • 12,000 cubic meter structural concrete
  • 2,300,000 kg bar reinforcing steel
  • 258,500 kg structural steel

18
YBI Substation Retrofit 04-0120G4
  • advertise the YBI Substation and Viaduct Retrofit
    in December, 2002
  • Bid Open Feb 25, 2003
  • Gross Quantities
  • 66,900 kg bar reinforcing steel
  • 350 cubic meter structural concrete

19
SAS E2/T1 Structures 04-0120E4
  • Gross Quantities
  • 1640 cubic meter structural concrete, bridge
  • 3,960,000 kg structural steel (bridge)
  • 2,550,000 reinforcing steel
  • 62 structure plans sheets, 100 log of test
    borings


20
SAS Superstructure 04-0120F4
  • Gross Quantities
  • 8000 cubic meter structural concrete
  • 42,600,000 kg structural steel (corrected Nov 25,
    2002)
  • 1,349,000 kg bar reinforcing steel
  • 600 structural plans sheets


21
YBI Superstructures 04-0120H4
  • Gross Quantities
  • 54,700 cubic meter structural concrete
  • 9,800,000 kg bar reinforcing steel
  • 250 plans sheets


22
Oakland Touchdown 04-012044
  • Gross Quantities
  • 14,500 cubic meter structural concrete
  • 3,400,000 bar reinforcing steel kg
  • 300 plans sheets

23
Business Enterprise
  • exceed goals
  • participate and document
  • Outreach to inform the contracting community
    which includes primes, subcontractors, suppliers
    and business enterprises on Construction Contract
    out to bid
  • Jan 7, 2003 530 p.m. at District 4 and Jan 8,
    2003 1230 pm in South San Francisco

24
San Francisco-Oakland Bay BridgeEast Span
Seismic Safety Project
25
Technical Issues/Changes since May 13, 2002
  • presented by Brian Maroney
  • May 13, 2002 Constructability Workshop
  • November 20, 2002 is last workshop before SAS
    Superstructure advertises

26
May 13, 2002
  • mobilization
  • bonding
  • wire
  • welding
  • certification
  • Buy America
  • temporary ramp on YBI
  • Domestic Fabrication of SAS box and tower
  • tower erection
  • Jones Act
  • schedule

27
Mobilization Payments
  • Caltrans recognizes significant front end
    mobilization cost for complex marine projects
  • Amend Section10264 of Public Contract Code, Add
    Section 284 to the Streets and Highway Code,
    relating to public works Chaptered September 27,
    2002
  • over water and over 25 million

28
Mobilization Payments
  • specification prepared and to be inserted into
    04-0120F4 and 04-0120E4
  • Public Contract Code language in handout

29
Bonding
  • Caltrans recognizes that for very large projects
    the current bonding market has constraints
  • Proposed legislation to reduce payment bond from
    100 to 50, possible bonding cap
  • pursuing every opportunity

30
Wire
  • waiver from buy America

31
Welding/Tolerance
  • ongoing

32
Steel Fabricator Certification
  • Caltrans recognizes importance of early approval
  • currently developing specification language for
    partial payment for early approvals of Fabricator
    Shop Audits
  • see handout, very very draft

33
Buy America
  • main cable wire supplier
  • can this project be fabricated domestically
  • allow alternative bid process for Buy America,
    foreign source total bid (foreign steel) bid
    lower by 25 domestic total bid (domestic steel)
    bid
  • temporary works

34
Buy America Waivers
  • PPWS Strand (includes production of wire rod)
  • Tower Saddle (single cast upper portion of 175
    tons)
  • S-Wire cable wrapping
  • Macalloy bars - 75 mm dia high strength A722 bars
    ( w2, bent and hinge)

35
Jones Act 46 U.S.C. App Section 883
  • see handout
  • issue - foreign crane, domestic barge coastwise
    trade violation
  • holding - not - provided barge meets
  • issue - foreign crane, foreign barge coastwise
    trade violation
  • holding - is a use

36
Temporary Structures on YBI
37
Domestic fabrication of tower and box
38
Tower Erection
  • Two bolted splices added to tower
  • from survey of US cranes
  • Regions of allowable welded field splices
    identified on the plans

39
SAS Box Superstructure field splices
  • we want to minimize field splices
  • low bidder discretion allowed

40
Schedule
  • Cert.
  • Shop drawing review/approval
  • begin fabrication
  • cable erection

41
Shop drawing review
  • considering milestone payment for shop drawing
    approval
  • exploring ways to expedite Caltrans processes
  • CT engineer in contractors engr. Office to work
    together

42
Shop drawing review
  • staged processing at Caltrans
  • streamlining Caltrans decision-making process re
    shop drawing technical decisions
  • Campus approach of CT office next to contractors
    office
  • encourage partnership between Caltrans and
    Contractor
  • Early meeting

43
Sole Source Items
  • Macalloy bars - 75 mm dia high strength A722 bars
  • Swivel joint seal assembly
  • Epoxy Asphalt Concrete (deck surface riding on
    steel box)
  • Tower Saddle (single cast upper portion of 175
    tons)
  • S-Wire cable wrapping
  • Suspension cable paint system (noxide paint)

44
Payments for materials on site
  • distribution of cash flow over life of project
  • if in United States
  • see handout

45
What if seismic event during construction?
  • reduce risk to contractor in case of earthquake,
    new limit is 5 contract amount, cap at 20
    million

46
Bidders not liable for terrorism
  • terrorism bidder inquiry
  • see handout

47
Under Development
  • modified the TRO spec to provide for a max of 15
    ( bid amount divide by number of working days
    bid) for progress payment purposes in lieu of
    standard 20, see handout
  • Caltrans will work with contractor on electronic
    submittal
  • stipend to do engineering during bid

48
Mass Concrete
  • thermal control plan adds flexibility
  • ACI methods were created for very very large
    elements

49
South - South Detour
  • Mixed message for industry
  • Some want in on design of detour
  • Others will not perform design

50
Oakland Touchdown
  • well over 100 million
  • discretize to ?
  • west bound and east bound contracts
  • west bound east bound frame (in water)

51
(No Transcript)
52
Other Issues
  • s-wrap desired because of maintenance appeal
  • locks out moistureits a better surface for
    painting
  • PPWS goes up faster, less air, less water, less
    splices
  • Caltrans is anxious to hear any aerial spun cable
    option - Contractors must show reasonable
    supporton anchorage strand jacks, space issue

53
space is an issue
54
Open Discussion with Contractors
  • 1045am 100pm
  • your chance to express concerns over what youve
    learned today
  • your chance to let us know what your questions are

55
What do contractors think
  • schedule
  • Interface with adjacent projects
  • Construction oversight from a distance
  • weather days
  • submittal fabrication overlap
  • Environmental protections
  • shop certification

56
What do contractors think
  • Business Enterprise
  • Is bonding a no bid item?
  • Shop drawing review
  • Number of bidders

57
Are there any Constructability issues?
  • Erection sequence
  • Tolerance welding
  • Buildability
Write a Comment
User Comments (0)
About PowerShow.com