Title:

Implementing SAP R3 at the University of Nebraska

Description:

Database. Server. Windows 95/98/NT. OS/2, Unix. MacIntosh. RS/6000 SP. AIX v4.3. Client Workstations ... Resulted in identification of 53 gaps. Critical Gaps ... – PowerPoint PPT presentation

Number of Views:112
Avg rating:3.0/5.0
Slides: 19
Provided by: donmihulka
Category:

less

Transcript and Presenter's Notes

Title: Implementing SAP R3 at the University of Nebraska


1
Implementing SAP R/3 at the University of Nebraska
  • Tim Sieber, Keng Siau, Fiona Nah, Michelle Sieber
  • University of Nebraska-Lincoln

2
Case Objectives
  • Present the case of implementing SAP R/3 at the
    University of Nebraska (NU)
  • Expose students to the problems and challenges
    involved in ERP implementation
  • Students will confront, discuss and resolve these
    problems, issues, and challenges
  • Students will evaluate alternatives to resolve
    critical gaps in ERP implementation

3
About the University of Nebraska
  • Four campuses and central administration
  • Kearney, Lincoln, Omaha and Medical Center
  • 1998-1999 budget almost 1.1 billion
  • Almost 46,300 students enrolled
  • Over 11,300 faculty and staff
  • Over 400 departments and auxiliary operations
  • Approximately 150,000 orders/invoices and 360,000
    paychecks processed annually

4
Legacy System Deficiencies
  • Not Year 2000 compliant
  • Disparate systems (not integrated)
  • Does not provide executive-level information
  • Software platform that is outdated and user
    unfriendly
  • Encourage use of shadow systems

5
Strategic Framework
  • 1996 to 2001
  • Improve management information systems
    continuously improve technological capacities and
    address system deficiencies
  • Maximize resources to achieve the mission by
    adopting best planning and business practices for
    all areas
  • Continue to seek and adopt best business advice
  • Created Financial System Task Force (FSTF)

6
Milestones
  • May 1996 - Start needs assessment
  • August 1996 - Needs assessment completed and
    technology selection process began
  • August 1997 - SAP America publicly announces SAP
    America Public Sector as a new subsidiary
  • September 1997 - Board of Regents approves over
    10.1 million to implement SAP R/3
  • September 1997 - Implementation process begins

7
Implementation Process
  • Preparation Phase 9/97 - 11/97
  • project scope and team orientation
  • Analysis Phase 11/97 - 2/98
  • develop as is and to be models
  • Design Phase 2/98 - 11/98
  • map processes to SAP, fit/gap analysis, prototype
    configuration and technical conversions/interfaces
  • Implementation Phase 11/98 - 3/99
  • complete functional and technical design,
    testing, data migration and end user training
  • GO LIVE - 7/1/99

8
Implementation Team
  • Representatives from all four campuses
  • FSTF or Steering Committee (8 people)
  • Core and Extended Teams ( 25 people)
  • 7 functional and support work teams
  • several cross-functional teams
  • Implementation Consultants (varies)
  • Campus Primary Resources ( 60 people)
  • Technical Resources ( 25 people)
  • Campus Transition Teams ( 40 people)

9
Implementation Scope
Financial CO Controlling FI Financial
Accounting PS Project Systems Human
Resources HR Human Resources Logistics MM
Materials Management
10
Client/Server Infrastructure
Database Server
Application Servers
RS/6000 SP AIX v4.3
DB2 v5.1
S/390 Server OS/390 v2.5
Client Workstations
Windows 95/98/NT
A 3-tier client/server implementation
OS/2, Unix
MacIntosh
11
Fit/Gap Analysis
Business Function Fit to SAP Purchasing 85 Accoun
ts Payable 80 Projects 75 Financial
Management 65 Asset Management 65 General
Ledger 60 Costing 60 Human Resources 60 Treasur
y 50 Budgeting 30 Funds Management 30 Average 6
0 Resulted in identification of 53 gaps
12
Critical Gaps
  • 14 gaps identified as critical whereby resolution
    was imperative to ensure a fully configured
    system
  • 12 in Human Resources module
  • 1 in Financial Accounting module
  • 1 in Materials Management module
  • Potential impact of critical gaps on
  • project scope
  • resources (human and budgetary)
  • timeline
  • system configuration

13
Critical Gaps Resolution Options
  • SAP provides on-site development
  • change core program code, compatibility with
    future releases and resolve all gaps
  • moderate risk and low expected cost
  • IBM provides developers to create workarounds
  • temporary solutions, not part of core program
    code and wont resolve all gaps
  • high risk and high cost

Continued.
14
Critical Gaps Resolution Options II
  • Extend project timeline to July 1, 1999 and
    implement the next version of SAP R/3
  • delay entire project three months and
    simultaneous implementation of activities
  • high risk and moderate to high cost
  • University delays payroll until the next phase of
    implementing functionality
  • continue with non-HR schedule and interface SAP
    with current legacy system
  • low risk and moderate to high cost

15
Issues to Consider
  • Approximately 75 of the total project budget
    earmarked for consulting resources
  • SAP recognition of public sector industry
  • Significant turnover with consulting resources
    including four different consulting leads in HR
  • Business functions with lowest fit to SAP are
    more unique to public sector
  • Most of the critical gaps relate to HR
  • Y2K compliance of legacy systems

16
Suggested Questions
  • Characterize NUs existing competitive
    environment
  • role of IT in NUs central administration
  • importance of system success in relation to NUs
    competitive strategies
  • Decision to implement SAP R/3 in NU
  • strengths and weaknesses of SAP R/3 for NU
  • is it a good decision?

Continued.
17
Suggested Questions II
  • Evaluate goodness of fit
  • fit between functionality provided by SAP R/3 and
    NUs desired business processes
  • Analysis and recommendation
  • analyze and evaluate alternatives to resolve gaps
  • make recommendation and assess level of risk
  • Challenges ahead
  • how well positioned is NU to meet future
    challenges?

18
Subsequent Events
  • SAP provided developers and incorporated some of
    the needed functionality to resolve the gaps
  • IBM released due to financial issues
  • SAP took ownership and sub-contracted Prescient
    Consulting as consulting partner
  • FI/CO/PS/MM WENT-LIVE on July 1, 1999
  • HR/Payroll delayed till October 22, 1999