Title: Special%20Open%20Meeting%20of%20the%20Arizona%20Corporation%20Commission%202005%20Summer%20Assessment
1SpecialOpen Meeting of the Arizona Corporation
Commission2005 Summer Assessment
- March 18, 2005
- Arizona Public Service Company
- Steve Wheeler Executive Vice President
- Jan H. Bennett Vice President, Customer Service
- Cary B. Deise Director, Transmission Operations
and Planning
2Overview
- Westwing Update
- Load/Resources Adequacy
- Transmission Adequacy
- Planned Maintenance Activities
- Contingency Planning
- Coordination/Training
- Future Plans
- Conclusions
3- Westwing Update
- Jan Bennett
4Original Schedule
- One transformer scheduled to arrive each week
starting March 30th - T-1 bank scheduled to be back in service before
summer peak - Replacement of BPA unit scheduled to follow T-1
installation - Replacement of spare to follow BPA replacement
5Issue Identified
- The schedule has been revised
- First two of seven transformers did not pass
initial testing - Corrections required before units could be
shipped - Manufacturer was on schedule prior to the initial
test results - Continuing to work with manufacturer on revised
schedule
6Revised Schedule
- Mid-June BPA replacement unit commissioned
- Mid-July The T-1 Bank commissioned
- By year-end The original two transformers
in the T-4 Bank and the spare unit will be
in service - Removed units will
become spares - Sale pending on BPA unit
7The Issue
- Gassing occurred during testing that indicates a
hot spot - Results are similar for both units
- Unit One has been un-tanked
- All connections inspected
- All internal components inspected
- Tanks shunts removed
- Problem has been identified and corrections are
being made to all units - Consultation with Jim Templeton on test
procedures and corrective action
8The Issue
9Actions Taken
- APS and SRP sent technical teams to Canada to
work with ABB - Notified all owners
- Consulted with independent experts on the issue
- Made ABB aware of the critical need for this
equipment
10Next Steps
- Corrections will be made first to units one and
five - Unit one has been un-tanked
- Unit five is yet to be tanked
- Allows for quickest delivery of one unit to
replace BPA unit -
11Summary
- With the replacement of the BPA transformer we
will have adequate capacity to meet our load
under expected conditions - Full capacity and redundancy will be restored
with the installation of the new T-1 bank - The problem has been identified and corrections
are being made - We do not anticipate any voluntary or involuntary
curtailment of customer load this summer - ABB is working diligently to remedy the problem
12- Summer Preparedness
- Cary Deise
13Valley Maximum Load Serving Capability
Westwing Update
12,000
11,000
10,000
MW
9,000
8,000
7,000
6,000
14APS Peak Load Forecast
Loads/Resources Adequacy
6954 MW
6402 MW
Adding 160 APS customers every day
2005 Forecast
2004 Actual
Phoenix is the second fastest-growing
metropolitan area in U.S.
15Fuel
Loads/Resources Adequacy
- Nuclear
- Full requirements under contract.
- Coal
- Cholla
- Current inventory and contract commitments
provide adequate coal for the projected 2005
burn. - 43 days of inventory on the ground.
-
16Fuel, continued
Loads/Resources Adequacy
- Coal (cont.)
- Four Corners
- Mine mouth plant with full supply contract in
effect. - 30 days of inventory on the ground by May.
- Gas
- 85 of supply is under contract
- Firm transportation contracts with EPNG in
effect. - Fuel oil back-up at the Yucca, West Phoenix and
Saguaro Plants.
17APS Resources Existing Generation
Loads/Resources Adequacy
Fuel Type Capacity - MW
Nuclear 1107
Coal 1725
Gas 1054
Oil 70
Other 5
Total 3961
18Resources Existing PWEC/Other
Loads/Resources Adequacy
APS Committed Capacity MW
Redhawk 1020
Saguaro 76
West Phoenix 640
Sundance 325
Total 2061
Plant
19Resources
Loads/Resources Adequacy
- Generation 2005 (MW)
- Existing Generation 3961
PWEC/Other 2061 - Subtotal 6022
- Long-term Contracts
- Pacificorp Exchange 480
- SRP 364
-
- Subtotal 844
- Market Contracts 900
- Total Resources 7766
20APS System Load and Resources
Loads/Resources Adequacy
812 MW
21Substation Transformers
Transmission Adequacy
- NEW Xfmr Banks
- 69/12kV 15
- 115/69kV 1
- 230/69kV 1
- 500/69kV 1
- UPGRADED
- 69/12kV 8
- 230/69kV 5
- 345/230kV 1
- Total 32
22Transmission Lines
Transmission Adequacy
- Line Sections
- New
- 69kV 4
- Upgraded
- 69kV 9
23Transmission Adequacy
APS EHV SystemTransmission Capacity less
wheeling obligations
Navajo
Four
315 MW
Corners
782 MW
Mead
559 MW
Moenkopi
1175 MW
236 MW
Cholla
Yavapai
615 MW
1683 MW
Transmission Capacity
Generation Capacity
500kV
345kV
Pinnacle
Westwing
Peak
Rudd
2380 MW
Palo Verde
Kyrene
1107 MW
Jojoba
Saguaro
140 MW
Gila
310 MW
River
N.Gila
24Transmission Adequacy
APS EHV System
25Yuma Maximum Load Serving Capability
Transmission Adequacy
435 MW
450
60 MW
60 MW
400
375 MW
375 MW Forecasted Peak
350
2004 Peak 347 MW
300
MW
Generation Transmission
250
200
150
100
2004
2005
26Planned Maintenance
Generation
- APS Planned Maintenance Scheduled to be completed
by May 31 - Palo Verde 2 3
- Cholla 2
- Navajo 1
- Four Corners 1 and 5
- W. Phoenix Combined Cycle 1 3 and CT 1 2
- Saguaro Steam 1 2 and CT 1 2
- Yucca CT 1-4
- Ocotillo Steam 1 2 and CT 1 2
- Douglas CT
27Transmission
Planned Maintenance
- Key lines/substations on schedule
- Special emphasis on critical transformers
- Tree trimming in northern area due to damage from
snow storms
28- Contingency Planning
- Jan Bennett
29Contingency Planning
Contingency Planning
- Updated Load Curtailment Plans will be filed with
ACC by June 1, 2005 - Essential
- Critical
- Major-use customers/other with notice
- Other
- EMS Load Shedding program annual update by May
16, 2005 - Coordination with emergency organizations
30Emergency Equipment
Contingency Planning
- Mobile 69/12kV Transformers
- Emergency Towers
- Two Lindsey towers
Location Xfmrs
Phoenix 4
Flagstaff 2
Yuma 1
Total 7
31- Training Drills
- Cary Deise
32Training Drills
Coordination / Training
- Regional Black Start Drill March
- Usage of Load Curtailment tools April
- Summer Studies May
- Transmission Path Operations May
- Emergency Operations March-June
- Power Simulator
- NERC policies addressing March-June
- emergency operations
- DOE simulator training March-Oct.
33EHV Transmission
Future Plans
34West Valley 230kV
Future Plans
35East Valley 230kV
Future Plans
TO
RACEWAY
2
0
0
9
(
T
S
B
R
D
P
)
NE3
2010
J/O
(SRP)
(
S
R
P
)
345KV
Substation locations and line routings depict an
electrical connection only and
do
not
reflect any assumed physical locations or
routing.
36- Conclusions
- Steve Wheeler
37Conclusions
- Adequate resources to meet load and reserve
requirements - Sufficient transmission to import remote
generation and purchases - Plans in-place to respond to extreme conditions
- Coordination/training has been established with
various State and local agencies - Anticipate meeting customers needs